SOUTHGATE SWALE - 14-0026-EN - ADMINISTRATIVE CHANGE ORDER #1ADMINISTRATIVE CHANGE ORDER 1
PROJECT:
Southgate Swale
CONTRACTOR:
Steve's Excavating & Paving Inc.
PO Box 303
Dunedin, F134697
DATE: February 4, 2015
PROJECT NUMBER: 14- 0026 -EN
PO REFERENCE NO: ST109739
DATE OF CONTRACT: July 15, 2014
CODE:0315- 96124 - 563700 -539- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order increases and adds items according to field conditions - see attached
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 - CM -
NEW CONTRACT AMOUNT
ATTEST:
Rosemarie Call,
Date: Je -J-4 -14._ 4,
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
$24,317.00
$8,393.76
$32,710.76
ACCEPTED BY:
Steve'
d Paving
SEAL
Cath 4:. rnago, President
Date: O /6 //c
W
William B. Horne, II
Recommended By: City of Clearwater
APPROV D AS 'O F
City Manager
Math fEw Smith, ' Assistant City Attorney
Sarah Josuns,
Project Manager
City Engineer
Michael D Quillen, PE,
Page 2 of 2: Administrative Change Order 1 - Southgate Swale
ITEM
Increases:
2 Clear and grub ditch area
3 Excavate per plan
5 Sodding
DESCRIPTION
QUANTITY UNIT UNIT COST TOTAL COST
2800 SF $0.85
123 CY $7.00
5137.5 SF $0.80
Total Increases:
$2,380.00
$861.00
$4,110.00
$7,351.00
Additions:
7 12" to 18" Tree Demo 1 LS $325.00 $325.00
8 Load and Haul 13 CY $35.00 $455.00
9 Dump Fee 13 CY $9.75 $126.75
10 Overhead 1 LS $136.01 $136.01
Total Additions: $1,042.76
Total Increases /Additions to the Contract: $8,393.76