SMALLWOOD CIRCLE DRAINAGE IMPROVEMENTS - 11-0057-EN AND EDGEWOOD AVENUE SANITARY SEWER IMPROVEMENTS - 10-0027-UT - CHANGE ORDER #1Change Order 1
PROJECT
Smallwood Circle Drainage Improvements and
Edgewood Avenue Sanitary Sewer Improvements
CONTRACTOR:
Rowland, Inc.
6855 102nd Avenue, North
Pinellas Park, FL 33782
OCT 2 l 2014
Date: October 10, 2014
PROJECT NUMBER: $1- 0057 -EN & 10- 0027 -UT
PO REFERENCE NO.:
COUNCIL AWARD:
DATE OF CONTRACT:
ST110040
November 7, 2013
December 4, 2013
CODE: 0315 - 96178 - 563700 -539- 000 -0000 A
CODE:
0327 - 96665- 563800- 535 - 000 -0000 B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Change order approves a time extension of 95 days and adds replacement of curb to the project. �'•'
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: Rowland, Inc.
ORIGINAL CONTRACT AMOUNT
Change Order 1 - City Council 11/6/14
NEW CONTRACT AMOUNT
- Ct&) /WCn Crt\t $
George N. Cretekos
Rosemarie Cdt./ t
Date:
$2,345,142.97
$148,718.00
$2,493,860.97
aCi
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA r,
William B. Horne, II
APPROVED AS
Matthew Smi
City Manager
By:
Kevin Rowland,
Date: 10/17/1y
Recommended By: City of Clearwater
/t. ,/4
Tara Kivett
Construction Manager
Assistant City Attorney ' Michael D. Quillen,
City Engineer
le
Page 2 of 2
Change Order 1: Smallwood Cir Drainage Improvements/Edgewood Avenue Sewer Improvements
ITEM DESCRIPTION UNIT Qty UNIT COST TOTAL COST
Stormwater Code A: 0315 - 96178 - 563700- 539 -000 -0000
Additions:
50 Remove and replace curb LF 2968 $ 28.06 $83,282.08
Total Additions for Code A: $83,282.08
Sewer Code B: 0327 - 96665 - 563800- 535 - 000 -0000
Additions:
130 Remove and replace curb
LF
2332 $ 28.06
Total Additions for Code 13:
$65,435.92
$65,435.92
Total Additions to the Contract: $148,718.00