JEFFORDS ST CHANNEL GABIONS PROJECT - 11-0009-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 & Final
PROJECT:
Jeffords St Channel Gabions
CONTRACTOR:
Keystome Excavators, Inc.
371 Scarlet Blvd
Oldsmar, FL 34677
Date: September 22, 2014
PROJECT NUMBER: 11- 0009 -EN
PO REFERENCE: ST109979
COUNCIL AWARD: October 16, 2013
DATE OF CONTRACT: October 17, 2013
CODE: 0315- 96181 - 563700- 539 - 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order decreases, increases and adds items according to field conditions - see attached.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY KeystoneFoXcyvaforSi.Inc.'
ORIGINAL CONTRACT AMOUNT $1,491,820.00
Administrative Change Order 1 & Final - CM ($100,263.70) By:
NEW CONTRACT AMOUNT $1,391,556.30
ATTEST:
WiLieytaA 6(1_
Rosemarie Clark Ca 11 •
Robert C. Fornwalt, Jr.,
Date:
f (6E;)
lent
czkkIL 2014,
Witnesses: (two)
Date: e ?,�
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
L0-1146-, .1414‘.117-
William B. Horne, II
APPROVE AST FORM:
Matthew ith, Assistant City Attorney
City Manager
Recommended By: City of Clearwater
(4 -
Tara Ki etI Construction Manager
Michael D. Quillen, E, City Engineer
Page 2 of 2
Administrative Change Order 1 & Final Jeffords St Channel Gabions
ITE DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Decreases:
8 Excavation, Unsuit. Mat'l CY 100 $ 33.00 $ (3,300.00)
12 Conc CL IV, Misc CY 8 $ 620.00 $ (4,960.00)
14 Gabion Basket Retaining Wall, w/Filter CY 45.5 $ 247.00 $ (11,238.50)
Fabric
15 Reno Mattress at Channel Bottom, 12" SY 68 $ 78.00 $ (5,304.00)
Thick
17 Fence DOT Type B, 4' (vinyl coated LF 35 $ 13.00 $ (455.00)
w /top rail)
18 6 "x 8" Edge Curb, (behind fence, at top LF 278 $ 18.00 $ (5,004.00)
of gabions)
19 SOD, Bahia SY 311 $ 3.50 $ (1,088.50)
22 10% Contingency LS 1 $ 135,620.00 $ (135,620.00)
Total (Decreases): $ (166,970.00)
Increases:
13 Rubble RIPRAP, Bank & Shore Size, TN 15.5 $ 179.00 $ 2,774.50
w/Filter Fabric under
Total Increases: $ 2,774.50
Additions:
23 Remove Sediment at Creek Bottom, Haul CY # # ## $ 20.00 $ 30,240.00
offsite
24 Installation of Stairs, per building code EA 2 $ 5,100.00 $ 10,200.00
25 Remove Inlet Struc & Slab LS 1 $ 1,840.00 $ 1,840.00
26 Remove Storm Pipe, 42" RCP LF 24 $ 15.00 $ 360.00
27 42" RCP Storm Pipe LF 32 $ 196.00 $ 6,272.00
28 3' Flume at Evergreen (KT) LF 40 $ 30.00 $ 1,200.00
29 J -6 Curb Inlet with Dbl -sided EA 1 $ 5,418.00 $ 5,418.00
wing/throat/top
30 Remove and Replace Driveway - 1361 SF 183 $ 9.60 $ 1,756.80
Betty Lane South
31 Remove Curb LF 107 $ 5.00 $ 535.00
32 Curb LF 107 $ 26.00 $ 2,782.00
33 Remove, Regrade Pavement Base SY 111 $ 18.00 $ 1,998.00
34 Remove, Re- Install Guardrail, Posts LS 1 $ 1,330.00 $ 1,330.00
Total Additions: $ 63,931.80
Total Net (Decreases)/Increases /Additions:
($100,263.70)