LIFT STATION 33 - 09-0003-UT & LIFT STATION 42 - 10-0051-UT - REHABILITATION PROJECTS - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 & Final
PROJECT:
Lift Stations 33 & 42 Rehabilitation
CONTRACTOR:
TLC Diversified, Inc.
2719 17th Street East
Palmetto, FL 34221
Date:
PROJECT NUMBER:
PO REFERENCE:
AWARD DATE:
CONTRACT DATE:
CODE:
May 27, 2014
09- 0003 -UT & 10- 0051 -UT
STI09472
May 1, 2013
May 29, 2013
0315- 96686 - 563800 -535- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decreases and adds items according to field conditions - see attached
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CO r AMOUNT
Admin Chang I rder; & Fins - CM
NEW CO
APPRO
989,560.00
($17,801.95)
971,758.05
Camilo So
ATTEST:
Rosemarie Call,
Date:
CITY OF CLEARWATER, IN
PINELLAS COUNTY, FLORIDA
William B. Horne, II, City Manager
TLC Divers
i
edlIMMEIMI
of Clearwate
Recommended By:
Project Manager
Michael D. Quill E, City Engineer
Page 2 of 3
Administrative Change Order 1 & Final: Lift Stations 33 & 42 Rehabilitation
ITEM DESCRIPTION UNIT Q UNIT COST TOTAL COST
Decreases:
2 Lift Station 42 line stop and valve insertion on LS 1 $10,500.00 ($10,500.00)
South Force Main complete in accordance with
section 01150, 3.O1B
7 Contingency LS 1 $89,960.00 ($89,960.00)
Total (Decreases): ($100,460.00)
Additions:
8 Restrain 3.5 ss pipes LS42 LS 1 $2,627.00 $2,627.00
9 Wet well liner replacement LS42 LS 1 $63,285.00 $63,285.00
10 Install light pole LS42 LS 1 $4,900.00 $4,900.00
11 Bypass port pipe relace LS42 LS 1 $4,615.00 $4,615.00
12 Install post rack for junction box LS I $2,466.00 $2,466.00
13 Driggers engineering services LS 1 $3,134.50 $3,134.50
14 LS42 Relocate 4" FM LS 1 $8,965.55 $8,965.55
15 Credit shop drawing reviews LS 1 ($7,335.00) ($7,335.00)
Total Additions: $82,658.05
Total Net (Decreases)/Additions: ($17,801.95)
L