WATER TREATMENT PLANT NO. 2 - CONTRACT 2 - RAW WATER TRANSMISSION MAIN US 19 CROSSING PROJECT - 10-0039-UT-B - ADMINISTRATIVE CHANGE ORDER #2 & FINALADMINISTRATIVE CHANGE ORDER Change Order 2 & Final DATE: July 23, 2014
PROJECT:
WTP 2 - Contract 2: Raw Water Tranmission
Main US19 Crossing Project
CONTRACTOR:
Young's Communication Co. Inc
424 West Drive
Melourne, F132904
PROJECT NUMBER: 10- 0039- UT -(B)
PO REFERENCE NO: ST109342
COUNCIL AWARD: March 21, 2013
DATE OF CONTRACT: April 11, 2013
CODE: 0315- 96767 - 563800 -533- 000 -00Q0
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT A r ') •`
Decreases and increases items according to field conditions - see attached
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
Young's Comm
ORIGINAL CONTRACT AMOUNT $ 934,611.70
Admin Change Order 1 - CM - 6/16/2014 $ By:
Admin Change 2 & Final - CM - $ (66,825.36) Steve You
NEW CONTRACT AMOUNT $ 867,786.34
ATTEST:
Rosemarie Call,
Date: O..LL
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
City Manager
Camilo Soto, Assistant City Attorney
Date: 1
Witnesses:
Recommended By: City of Clearwater
Robert Fahey, PE
oject Manager
Michael D Quillen, PE,
City Engineer
•
Page 2 of 2:
RE: Change Order 2 & Final - WTP2 - Contract 2: Raw Water Transmission Main US19 Crossing Project
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Decreases:
8 F &I 8" PotACIe Water HDPE DR11 Pipe by 20 LF $ 48.00 $ (960.00)
Horizontal Directional Drill
12 3" communication conduit, open cut 83 LF $ 7.50 $ (622.50)
13 Sanitary Sewer FM, Open Cut HDPE 20 LF $ 53.00 $ (1,060.00)
14 F &I 6" Backwash Water HDPE Pipe by Open Cut 130 LF $ 20.00 $ (2,600.00)
18 F &I 8" Raw Water HDPE Pipe by Open Cut 170 LF $ 22.00 $ (3,740.00)
19 F &I 8" Concentrate Water HDPE Pipe by Open Cut 101 LF $ 22.00 $ (2,222.00)
20 F &1 8" Concentrate Water DI Pipe by Open Cut 56 LF $ 105.00 $ (5,880.00)
22 F &I 12" Raw Water DI Pipe by Open Cut 35 LF $ 90.00 $ (3,150.00)
24 F &I 6" Restrained Joints for DI Pipe 5 EA $ 55.00 $ (275.00)
25 F &I 8" Restrained Joints for HDPE Pipe 30 EA $ 133.00 $ (3,990.00)
28 F &I 12" Restrained Joints for DI Pipe 4 EA $ 92.00 $ (368.00)
29 F &I 16" Restrained Joints for DI Pipe 5 EA $ 512.00 $ (2,560.00)
30 F &I Compact DI Fittings 147 LB $ 8.20 $ (1,205.40)
34 F &I 17" x 30" Pull Boxes for Communication Conduits 6 EA $ 980.00 $ (5,880.00)
34A F &I 30" X 48" Pull Boxes for Communication 1 EA $ 2,004.00 $ (2,004.00)
35 F &I Combination Air Valve - Type I 1 EA $ 2,536.00 $ (2,536.00)
40 Root Pruning 835 LF $ 3.00 $ (2,505.00)
42 Remove Trees 1 EA $ 448.00 $ (448.00)
48 Sod Restoration as Directed by the Owner or the 500 SY $ 4.54 $ (2,270.00)
Owner's Authorized Project Representative
49 Concrete Driveway Restoration as Directed by the 198 SY $ 42.32 $ (8,379.36)
Owner or the Owner's Authorized Project
Representative
50 Concrete Sidewalk Restoration as Directed by the 152 SY $ 42.32 $ (6,432.64)
Owner or the Owner's Authorized Project
Representative
51 Concrete Curb Restoration as Directed by the Owner or 174 LF $ 26.50 $ (4,611.00)
the Owner's Authorized Project Representative
52 Underdrain Restoration as Directed by the Owner or 200 LF $ 16.50 $ (3,300.00)
the Owner's Authorized Project Representative
53 Asphalt Paving Restoration as Directed by the Owner 128 SY $ 22.00 $ (2,816.00)
or the Owner's Authorized Project Representative
54 Unsuitable Material Excavation Below Grade as 416 CY $ 12.00 $ (4,992.00)
Directed by the Owner or the Owner's Authorized
Project Representative
55 Select Backfill Below Grade as Directed by the Owner 416 CY $ 25.00 $ (10,400.00)
or the Owner's Authorized Project Representative
56 Asphalt Overlay as Directed by the Owner or the 500 SY $ 17.00 $ (8,500.00)
Owner's Authorized Project Representative
57 Owner's 10% Contingency 1 LS $ 84,964.70 $ (84,964.70)
Total (Decreases): $ (178,671.60)
Increases:
4 F &I 6" Sanitary Sewer Force Main HDPE DR11 Pipe 4 LF $ 32.00 $ 128.00
by Horizontal Directional Drill
7 F &I 8" Raw Water HDPE DR11 Pipe by Horizontal 28 LF $ 54.00 $ 1,512.00
Directional Drill
11 F &I 22" Horizontal Directional Drill with 8" 128 LF $ 74.50 $ 9,536.00
Concentrate Water HDPE DR9 Pipe, 6" Backwash
Water HDPE DR9 Pipe and 3" Communication
Conduit HDPE DR9 Pipe
15 F &I 6" Sanitary Sewer Force Main DI Pipe by Open 2 LF $ 148.00 $ 296.00
Cut
16 F &I 6" Backwash Water DI Pipe by Open Cut 9.8 LF $ 50.00 $ 490.00
17 F &I 6" Backwash Water HDPE Pipe by Open Cut 25 LF $ 36.00 $ 900.00
21 F &I 12" Raw Water HDPE Pipe by Open Cut 33 LF $ 44.00 $ 1,452.00
23 F &I 6" Restrained Joints for HDPE Pipe 6 EA $ 105.00 $ 630.00
26 F &I 8" Restrained Joints for DI Pipe 18 EA $ 54.00 $ 972.00
32 F &I 8" Resilient Wedge Gate Valve & Valve Box 1 EA $ 1,283.00 $ 1,283.00
47 Video Inspect6ion, Pigging, Flushing, Hydrostatic Testis 1712 LF $ 10.50 $ 17,976.00
Total Increases: $ 35,175.00
Additions:
58 Drew St E of US 19 @ Sta 412 +20 to Sta 412 +40 1 LS $ 12,137.31 $ 12,137.31
Asphalt Patch in the turning lane of Best Buy on
Capital FDOT ROW was 14" thick.
59 Westside of US 19 in front of Tilted Kilt Sta 405 +10 1 LS $ 3,644.38 $ 3,644.38
Asphalt Patch to cap existing 6" pipe
60 Westside of US 19 in front of Tilted Kilt Sta 405 +20 1 LS $ 4,556.11 $ 4,556.11
Asphalt Patch to cap existing pipe at Verizon Manhole
61 Change Order 1 SR19 & Drew Street Wire Guide 1 LS $ 53,573.44 $ 53,573.44
Directional Bore
62 Change Order 2 Old Coachman Rd & Progress Energy 1 LS $ 2,760.00 $ 2,760.00
Utility Easement Sta 304 +50 Excavation for 16" Gate
Valve (could not be located)
Total Additions $ 76,671.24
Total Net (Decreases) /Increases /Additions: $ (66,825.36)