ISLAND ESTATES BRIDGE REPLACEMENTS - 13-0004-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 & Final
PROJECT:
Island Estates Bridge Repairs
CONTRACTOR:
Date:
PROJECT NUMBEI
PO REFERENCE:
AWARD DATE:
Biltmore Constructin Co., Inc. CONTRACT DATE:
1055 Ponce de Leon Blvd
Belleair, Florida 33756 CODE:
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decreases and adds items according to field conditions - see attached
July 7, 2014
13- 0004 -EN
ST109863
September 19, 2013
September 19, 2013
0315- 92274 - 563800 -541- 000 -0000
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $ 173,143.04
Admin Change Order 1 & Final - City Manager - ($5,484.91) By ,,SEAL)
NEW CONTRACT A CrtJ T $ 167,658.13 Jeff P r, VicPrsirgnt�
oiN
7 hVg '
ACCEPTED BY:
tio�p19At6�1:11;;
Biltmorec Construction Co. C
APPROVED AS 0 F
Camilo Soto,
ATTEST:
Assistant City Attorney
Rosemarie Call,
Date:
CITY OF CLEARWATER, IN
PINELLAS COUNTY, FLORIDA
William B. Home, II,
City Manager
Date.
Witnesses:
4/,
Recommended By:City of Clearwater
Project Manager
ichael D. Quill e , City Engineer
•
•
Page 2 of 2
Administrative Change Order : Island Estates Bridge Repairs
ITEM DESCRIPTION JNI'. QTY UNIT COST
Decreases:
8 Contingency LS 1 $8,244.91
Total (Decreases):
Additions:
9 Windward Pressure grouting and spall LS
repairs
1 $2,760.00
Total Additions:
Total Net (Decreases) /Additions:
TOTAL COST
($8,244.91)
($8,244.91)
$2,760.00
$2,760.00
($5,484.91)