MARSHALL STREET SALSNES FILTER DESIGN - 06-0022-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 & Final
PROJECT:
Marshall St. Salsnes Filter Design
CONTRACTOR:
TLC Diversified
2179 17th Street East
Tampa, FL 33610
Date:
PROJECT NUMBER
PO REFERENCE:
AWARD DATE:
CONTRACT DATE:
CODE:
April 24, 2014
06- 0022 -UT
ST108624
July 19, 2012
August 7, 2012
)315- 96654 - 563800 -535- 000 -0000 (A)
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decreases, increases and adds items according to field conditions - see attached
STATEMENT OF CONTRACT AMOUNT
ORIGINAL C
Administr
NEW CO
APPR
CT AMOUNT
rder 1 & Final - CM
UNT
Camilo Soto,
ATTEST:
Assistant City Attom
$ 2,378,307.80
($707,289.80)
S 1,671,018.00
Rosemarie Call,
Date:
CITY OF CLEARWATER, IN
PINELLAS COUNTY, FLORIDA
4 �V 1 / D Gths/r. 4C7Iiie For•
V °am B. Home, II, City Manager
ACCEPTED BY:
TLC Diversified, Inc.
Thurston Lamberson, President
Date: ( Ll1
q
Recommended By:City of Clearwater
aArj„. thiu,4
ara L. y tt, Co ion Manager
Michael D. Quill PE, City Engineer
1
Page 2 of 2
Administrative Change Order 1 & Final: Marshall St. Salsnes Filter Design
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Decreases:
5 Sludge Removal from Clarifiers CY 418 $ 11.00 $ (4,598.00)
6b Salsnes filters Sales Tax Savings EA 2 $ 20,931.00 $ (41,862.00)
7b Magnetic Flow Meters - Sales Tax Savings EA 4 $ 926.00 $ (3,704.00)
8 10% Contingency LS 1 $ 216,209.80 $ (216,209.80)
Total (Decreases): $ (266,373.80)
Additions:
9 Valve Changes LS 1 $ (4,261.00) $ (4,261.00)
10 Design Change Demolition LS 1 $ 13,772.00 $ 13,772.00
11 Locate Underground Piping LS 1 $ 2,731.00 $ 2,731.00
12 RAS Modification LS 1 $ 841.00 S 841.00
13 RAS Bypass LS 1 $ 2,066.00 $ 2,066.00
14 Labor for Valve Changes LS 1 $ 1,138.00 S 1,138.00
15 Relocate Stairs and Platform LS 1 $ 510.00 $ 510.00
16 Structural Crack Repair LS 1 $ 4,081.00 $ 4,081.00
17 30" Offset LS 1 $ 10,308.00 $ 10,308.00
18 Panel Rack modification LS 1 $ 4,841.00 $ 4,841.00
19 RAS Bypass Phase 3 LS 1 $ 5,369.00 $ 5,369.00
20 Doweling in Slab LS 1 $ 1,497.00 $ 1,497.00
21 30" Influent Line Repair LS 1 $ 57,495.00 S 57,495.00
22 6" Filter Drain Line LS 1 $ 10,538.00 $ 10,538.00
23 Filter Platform LS 1 $ 45,342.00 $ 45,342.00
24 Filter Influent pipe modification LS 1 $ 17,375.00 $ 17,375.00
25 Lower RAS Lie Tie In LS 1 $ 6,273.00 $ 6,273.00
26 Pipe Reroute LS 1 $ 22,375.00 $ 22,375.00
27 Cable to MCC9 LS 1 $ 788.00 $ 788.00
28 120v Power Feed to PLC LS 1 S 1,449.00 $ 1,449.00
29 Replace Reactor Panel Feeder LS 1 $ 5,392.00 S 5,392.00
30 Backup Floats, Influent Bldg LS 1 $ 3,143.00 $ 3,143.00
31 Relocate Analyzers LS 1 $ 3,544.00 $ 3,544.00
32 Sludge Tank Pump Out LS 1 $ 2,778.00 $ 2,778.00
33 Paving at Light LS 1 $ 2,205.00 $ 2,205.00
34 Milling and Overlay LS 1 $ 3,187.00 $ 3,187.00
35 Relocate Filter Feed Flow Meter Transmitter LS 1 $ 3,620.00 $ 3,620.00
36 Sludge Pump Drain and Water Supply LS 1 $ 2,075.00 $ 2,075.00
37 Temp Scaffold Rental Erectio LS 1 $ 6,872.00 $ 6,872.00
38 Wire From Infl Samplet to PLC in MCC9 LS 1 $ 303.00 $ 303.00
39 480v Feeder From MCC to Temp Sludge Pump LS 1 $ 1,061.00 $ 1,061.00
40 Filter Drain Tie In LS 1 $ 1,195.00 $ 1,195.00
41 Reroute Plant Water Line LS 1 $ 2,409.00 $ 2,409.00
42 Temp Sludge Pumping LS 1 $ 7,662.00 $ 7,662.00
43 16" Valve Handwheel Ext LS 1 $ 1,451.00 $ 1,451.00
44 Mudwell Discharge Splash Guard LS 1 $ 767.00 $ 767.00
45 Plant LS Discharge LS 1 $ 985.00 $ 985.00
46 Filter Effi Sample Prots LS 1 $ 5,078.00 $ 5,078.00
47 Repair Stucco to MCC9 LS 1 $ 1,861.00 $ 1,861.00
Decreases for Owner Direct Purchases (ODP):
6a Salsnes Filters Package (Equipment Only) - ODP EA 2 $ 322,016.00 (644,032.00)
7a Magnetic Flow Meters - ODP EA 4 $ 14,250.00 (57.000.00)
Total (Decreases) ODP: (701,032.00)
Total Additions: 260,116.00
Total Net (Decreases) /Additions to PO: (6,257.80)
Total Net (Decreases) /Additions to Contract: (707,289.80)