LIFT STATION NO 2-2A REHABILITATION - 08-0050-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALADMINISTRATIVE CHANGE ORDER Change Order 1 & Final
PROJECT:
Lift Staion No 2/2A Rehabilitation
CONTRACTOR:
TLC Diversified, Inc.
2719 17th Street East
Palmetto, Fl 34221
DATE: March 10, 2014
PROJECT NUMBER: 08- 0050 -UT
PO REFERENCE NO: ST109374
COUNCIL AWARD : April 4, 2014
DATE OF CONTRACT: April 26, 2013
CODE: 0327 - 96686- 563800 - 535 - 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decreasing and adding item according to field conditions - see attached
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin CO 1 & Final - CM
NEW CONTRACT AMOUNT
ATTEST:
$ 337,645.00
($8,365.00)
$ 329,280.00
Rosemarie Call, C.
Date:
CITY OF C EARWATER, in
PINELLAS COUNTY, FLORIDA
a0 L-1
Camilo Soto,
Page 2 of 2
Assistant City Attorney
ACCEPTED BY: TLC Diversified,. Inc.
Thurston Lamberson,
Date: (Q (a 14
Recommended By: City of Clearwater
Rob Fahey,PE, ' Project Manager
Michael D Quillen, PE,
City Engineer
RE; Administrative Change Order 1 & Final - Lift Station 2/2A Rehabilitation
ITEM DESCRIPTION
Decreases:
3.5 Unsuitable Material Removal & Replacement
5.1 10% Owner's Contingency
Additions:
3.6 Demolition of Structure
3.7 Retaining Wall
3.8 Gate credit
UNITS QTY UNIT COST
CY 50 $50.00
LS 1 $ 30,695.00
Total (Decreases):
LS
LS
LS
1 $6,635.00
1 $18,695.00
1 ($500.00)
Total Additions:
Total Net (Decreases) /Additions:
TOTAL COST
($2,500.00)
($30,695.00)
($33,195.00)
$6,635.00
$18,695.00
($500.00)
$24,830.00
($8,365.00)