Loading...
HILLCREST- BROOKHILL NEIGHBORHOOD TRAFFIC CALMING AND STORMWATER IMPROVEMENTS - 10-0002-EN & 10-0050-EN - ADMINSTRATIVE CHANGE ORDER #2Administrative Change Order 2 Date: May 9, 2014 PROJECT: Hillcrest- Brookhill Neighborhood Traffic Calming & Stormwater Improvements CONTRACTOR: David Nelson Construction Co., Inc. 3483 Alternate 19 Palm Harbor, Fl 34683 PROJECT NUMBER: 10-0002- EN &10- 0050 -EN PO REFERENCE: ST108969 COUNCIL AWARD: October 17, 2012 DATE OF CONTRACT: November 27, 2012 CODE: 0315- 92276- 563700- 541 - 000 -0000 (A) CODE: 0315 - 96169- 563700 -539 -000 -0000 (B) SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT This change order decreases, increases and adds items according to field conditions. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: David Nelson Construction Co. Inc ORIGINAL CONTRACT AMOUNT $2,560,836.36 Change Order 1 - CC - 2/20/2014 $618,029.02 Admin CO 2 50.00 By: NEW CONTRACT AMOUNT $3,178,865.38 APPROVED AS TO FORM: Camillo Soto, ATTEST: Assist City (Attorney ktaulttutt. Rosemarie Call, CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA William B. Horne, II Page 2 of 2 City Manager Date: ey D Witnesses: Recommended By: City of Clearwater Tara Kivett, Engineering Construction Manager Michael D. Quillen, PE," City Engineer Administrative Change Order 2 - Hillcrest- Brookhill Neighborhood Traffic Calming & Stormwater Improvements ITEM DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST Traffic Calming Code A: 0315- 92276- 563700 - 541-000-0000 Decreases: 4 Tree Barricade LF 500 $ 4.00 ($2,000.00) 18 Relocate Cleanout EA 1 $ 500.00 ($500.00) 19 Relocate Water Meter EA 3 $ 1,500.00 ($4,500.00) 20 Tree Removal EA 5 $ 1,200.00 ($6.000.00) 24 Unsuitable Material Removal CY 956 $ 25.00 ($23.900.00) 42 Concrete Valley Gutter Curb, Special LF 700 $ 14.00 ($9.800.00) 54 FDOT Inlet Type J -5 (3.5'x7') EA 1 $ 6,500.00 ($6.500.00) 55 FDOT Inlet Type J -5 (3.5'x8') EA 1 $ 6,600.00 ($6.600.00) 56 FDOT Inlet Type J -5 (3.5'x9') EA 1 $ 6,600.00 ($6,600.00) 58 FDOT Inlet Type J -6 (3.5'x5') EA 1 $ 5,000.00 ($5.000.00) 61 FDOT Manhole Type J -7 (4' x 7') EA 1 $ 3,000.00 ($3,000.00) 62 FDOT Manhole Type J -8 (5' DIA) EA 1 $ 2,100.00 ($2.100.00) 65 Lower Sanitary Structure EA 1 $ 350.00 ($350.00) 103 Water Meter / Back Flow Preventor EA 24 $ 2,600.00 ($62,400.00) Assembly Total (Decreases) to Code A: ($139,250.00) Increases: 6 Asphalt Driveway Removal SF 525.5 $ 6.50 $ 3,415.75 11 Concrete Sidewalk Removal SF 190 $ 3.00 $ 570.00 17 Fire Hydrant Removal EA 1 $ 1,500.00 $ 1,500.00 23 Excavation, Roadway CY 2148 $ 20.00 $ 42,960.00 27 12" Type B Stabilization SY 2546.6 $ 10.50 $ 26,739.30 28 8" Crushed Concrete Base SY 129.188667 $ 15.00 $ 1,937.83 34 Concrete Driveway SF 605 $ 3.50 $ 2,1 17.50 35 Concrete Sidewalk, 4" SF 747 $ 2.50 $ 1,867.50 46 Concrete Spillway SF 148 $ 5.00 $ 740.00 67 6" Ductile Iron Pipe (WM) LF 173 $ 45.00 $ 7,785.00 68 6" Water Valve EA 2 $ 3,200.00 $ 6,400.00 69 6" Pipe Restraint (Megalug) EA 46 $ 75.00 $ 3,450.00 74 Adjust Manhole EA 5 $ 500.00 $ 2,500.00 89 Sign Relocation EA 8 $ 75.00 $ 600.00 Total Increases to Code A: $ 102,582.88 Additions: 157 Remove & Replace Sanitary Lateral EA 5 $ 1,783.11 $ 8,915.55 & Cleanout (6 ") 158 24" MES (SD) EA 1 $ 900.00 $ 900.00 159 Remove & Replace Water Main EA 2 $ 817.55 $ 1,635.10 Services 160 FDOT Manhole Type P -8 (S -28) EA 1 $ 3,088.75 $ 3,088.75 161 Clearwater Inlet Type A Wing (6') (S- EA 1 $ 5,479.67 $ 5,479.67 12) 162 Clearwater Inlet Type A Double Wing EA 1 $ 5,584.67 $ 5,584.67 (6') (S -21) 163 Replace Clearwater Type A Top (S -13 EA 2 $ 2,451.84 $ 4,903.68 & 15) 164 Replace Top Slab and Ring and Cover EA 2 $ 3,079.85 $ 6,159.70 on Manholes (S -10 & S -17) Total Additions to Code A: $ 36,667.12 Total Net (Decreases)/Increases/Additions to Code A: $0.00 Stormwater Code B: 0315- 96169- 563700 - 539 -000 -0000 Decreases: 129 Underdrain, 6 -Inch LF 400 $ 20.00 ($8.000.00) 130 Underdrain, 8 -Inch LF 400 $ 25.00 ($10.000.00) 137 FDOT Inlet Type J -1 (5' DIA) EA 1 $ 3,300.00 ($3,300.00) Total (Decreases) to Code B: ($21,300.00) Increases: 112 Concrete Curb & Gutter Removal LF 387.475 $ 4.50 $ 1,743.64 135 42" RCP LF 38.5 $ 110.00 $ 4,235.00 149 8" Ductile Iron Pipe LF 88.5 $ 80.00 $ 7,080.00 152 8" Pipe Restraint (Megalug) EA 18 $ 90.00 $ 1,620.00 Total Increases to Code B: $ 14,678.64 Additions: 165 Clearwater Inlet Type A Single EA 1 $6,621.36 $ 6,621.36 (5'X5.5') (S -55) Total Additions to Code B: $ 6,621.36 Total Net (Decreases)/Increases /Additions to Code B: $ (0.00) Total Net (Decreases) /Increases /Additions to Contract: $ (0.00)