Loading...
TBE WORK ORDER INITIATION FORM - CLEARWATER AUTOMOTIVE SALVAGE YARD )0- CITY OF CLEARWATER ECONOMIC DEVELOPMENTIHOUSING DEPARTMENT TBE WORK ORDER INITIATION FORM Clearwater Automotive Salvage Yard Engineering Oversight and Completion Reporting Post Demolition and Foundation Removal Date: June 23, 2006 TBE Project No. City Project No. 1. PROJECT TITLE Engineering Oversight of Post Demolition Foundation and Impacted Soil Remediation Program - Clearwater Auto Salvage Yard - 205,317, and 319 S. Martin Luther King, Jr. Avenue, Clearwater, Florida 33756. Brownfields Site No. BF97493703. 2. PROJECT BACKGROUND The subject property is an approximately 3.5 acre site on the northeast comer of South M. L. King Jr. A venue and Gould Street that was historically utilized as an automobile parts salvage yard and storage facility. The property was designated as a Brownfields redevelopment site and was subsequently purchased by the City of Clearwater. Salvage operations were halted and the site was vacated in early 2006. Site assessment activities have been conducted for this property beginning in early 2004, culminating in the submittal of a Combined Phase II Environmental Site Assessment (ESA)/Brownfields Site Assessment Report (BSAR) to the Florida Department of Environmental Protection (FDEP) in January 2005. As summarized in the ESA/BSAR document, numerous shallow soil samples have been collected in the northern portion of the site and 21 monitor wells have been installed and sampled throughout the entire property. Based on these data, exceedances of the total recoverable petroleum hydrocarbons (TRPH) soil cleanup target levels (SCTLs) (Chapter 62-777, FAC) were confirmed at randomly distributed soil sample locations throughout the study area. Based on these findings, and due to the dynamic nature of the auto salvage yard activities at the time of the previous assessments (e.g., cars being moved and disassembled at ever-changing areas throughout the property), TBE recommended that additional soil assessment be delayed until the site was vacated and the building structures were demolished and removed from the property. A solicitation for bids remove building foundations and impacted soils was advertised by the City of Clearwater and bid openings were reviewed on June 12, 2006. The low bid was slightly lower than the engineers estimate and the award of this contract is anticipated for July 20, 2006. The bid calls for two phases of work; the initial foundation removal and excavation and disposal of any grossly contaminated soils or debris that are noted at that time. The contractor will then demobilize from the site while site-wide assessment of ( C:\Documents and Settings\dhufford\Local Settings\Temporary Internet Files\OLK17\EngineerOversightrev.doc \ o. ,. remaining native soils is completed (as authorized under a separate City of Clearwater Contract). Pending completion of this delineation sampling program, the Contractor will return to the site to remove remaining soils that are marginally impacted, and to provide a re- grading of the site. The purpose of this Contract is to provide Engineering oversight for the Contractor demolition, assessment, and disposal activities outlined in the above contract. In addition to providing oversight of field activities, TBE will also ensure appropriate documentation is provided for completion of an Interim Remediation Measures Completion Report, and for other requirements of the Brownfields grant programs (e.g., Davis Bacon Act compliance, appropriate disposal records, etc.). TBE will also review all Contractor invoices and other documentation to determine compliance with City of Clearwater requirements, and to ensure accuracy. 3. SCOPE OF WORK TBE will provide engineering oversight and completion report preparation for the Environmental Demolition, Debris and Soil Removal Program for the Clearwater Automotive Salvage Yard. Included in this scope of work will be a limited amount of waste assessment and negotiations with the Florida Department of Environmental Protection (FDEP) waste management division regarding impact delineation within the property boundaries. Negotiations regarding offsite impacts are excluded from this proposal. Engineering oversight will include field direction to the selected demolition/excavation contractor, review of waste profiles, review of waste disposal methods, collection of waste manifests and coordination of signatures/approvals by the City of Clearwater. Engineering oversight is included for the initial demolition and source removal program, as well as the follow-up soil removal program. TBE will also review Contractor invoices for accuracy and completeness, including an evaluation of waste disposal volumes. TBE will not be responsible for Contractor means or methods related to demolition activities or on-site safety programs. 4. PROJECT GOALS The purpose of this project is to complete, to the extent possible, removal of impacted debris and soils that could affect future development, and to ensure that impacted materials are appropriately managed. The determination of soil removal quantities from the site may include recommendations to the City to include institutional controls on the property (i.e., a deed restriction) that can reduce the costs associated with extensive soil removal. 5. BUDGET Due to the uncertainty of the volume of material requiring removal from the site, TBE is providing the following cost estimate based on approximate unit costs, and will invoice the City on a time and materials basis. The fees used for developing this cost proposal are approximate and are provided for budgetary purposes only. For project invoicing, TBE G: \ENV\Proposal\2006\Clearwater\Auto Demo \EngineerOversight.doc .' fees/rates will be consistent with our general engineering services contract with the City of Clearwater, originally dated July 24, 2003 (currently being revised by the City). Project Setup and Regulatory Negotiations (limited to on-site impacts) Project Manager/Director: 30 hours @ $150/hr................. .... .....................................$4,500 Engineering Oversight of Demolition / Excavation Contractor Senior ScientistlDirector: 40 hours @ $150.00 ............................. ........................... ..$6,000 Project Scientist/Engineer: 40 hours @ $95.00......................................................... $3,800 Project Technicians: 100 hours @ $80/hour............................................................$12,800 Additional Support Staff(GIS, Clerical, etc.)............................................... ..$8,000 Direct Cost Items (including Health & Safety Equipment)................................ .$2,000 Subcontracted laboratory (no markup) 20 samples @ $230 ea. .................................$4,600 Subtotal (Excavation Oversight) $37,200* Records Compilation and Completion Report Preparation Project Manager/Director: 20 hours @$150/hr............................................ .$3,000 Project Scientist: 40 hrs @ $95/hr ............... .............. .................... ....................... ......$3,800 Project Technician: 10 hrs @ $80/hr ........................................................................... .$800 Additional Support Staff (GIS, Clerical, etc.)............................................ ... .$800 Subtotal (Completion Report Preparation) $8,400 PROJECT TOTAL ...............................................................................................$ 50,100 * Note: *These time estimates are based on available information to date, which are related to unknown volumes of waste materials. Quantities may increase or decrease from those estimated, which could increase the project total. This work is being conducted on a time and materials basis and final invoices will be based on actual time and materials incurred (rates based on attached spreadsheet).TBE will not exceed the established budget projects without prior approval from the City of Clearwater. 6. SCHEDULE Contractor award is scheduled for July 20, 2006. It is anticipated that field work will commence on Monday, July 24. TBE anticipates approximately four weeks to complete demolition and initial debris and soil removal activities (by August 25, 2006). Approximately three weeks will be required to complete proposed post-demolition soil assessment and define additional soil excavation activities (assuming impacts are not extensive and regulatory review is not required). Approximately three weeks will likely be required to complete the supplemental soil removal, resulting in field activities being completed in early to mid October 2006. Final reporting can be submitted before the end of November 2006. G: \ENV\Proposal\2 006\Clearwater\Auto Demo \EngineerOversight. doc '- 7. TBE STAFF ASSIGNMENTS Proj ect Director - Project Manager- Project Engineer- Project Scientist/Technician - Sr. Field Technician - Administrative/Tech Writer - Brownfields/Economic Development Manager GIS Support Rick Hagberg, P.G. Terry Griffin, P.G. David O'Connor, PE Dana Kress Kevin Sanders Shawn Lasseter Miles G. Ballogg Nathan Kerr 8. CORRESPONDENCEIREPORTING PROCEDURES Correspondence shall be sent to Diane Hufford. 9. INVOICING/FUNDING PROCEDURES The budget for this work is a maximum $50,100 based on unit rates listed above and direct reimbursable costs expended. Invoicing Method A, Cost Times Multiplier shall be used. City Invoicing Code: 10. SPECIAL CONSIDERATIONS None. 11. PROJECT COMPLETION REPORT TBE will provide an Interim Source Removal Completion Report in accordance with Chapter 17 -785 The Florida Brownfields Cleanup Criteria. PREPARED / APPROVED BY: TBE: (Ci "'";"cl ~,rl4'( ,flA Terry Griffin, PG Senior Hydrogeologist Date: 6...2 ~ - D(P 6fiagber:, pc(v9 /' Environmental Services Director Date: (, ~~ r -' (), G: \ENV\Proposal\2006\Clearwater\Auto Demo \EngineerOversight. doc " 1f;/Lr Steven owarth, PE Vice President Date: ~ ,.. 2 B 'OG Date: ~- 07 - 200y ~~. a E. Goudeau, Countersigned: Approved as to form: G: \ENV\Proposal\2 006\Clearwater\Auto Demo \EngineerOversight.doc