2011 SIDEWALK CONTRACT - 11-0012-EN - ADMINISTRATIVE CHANGE ORDER #5CHANGE ORDER 5
Date: October 30, 2013
PROJECT: 2011 Sidewalk Contract PROJECT NUMBER: 11- 0012 -EN
PO REFERENCE NO: ST108005
CONTRACTOR: CONTRACT AWARD: November 03, 2011
Central Florida Contractors, Inc. CONTRACT DATE: December 13, 2011
PO Box 3987
Seminole, Florida 33775 CODE: 0315- 92339 - 563700 -541- 000 -0000 A
CODE: 0315 - 92277 - 563700 -541- 000 -0000 B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Extends the contract for 360 days and increases the funding on a unit price basis for a not to exceed amount, with all
other terms and conditions remaining the same, see attached for details.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT $ 568,337.00
Admin CO 1 - CM - 2/15/2012 $ 56,832.00
Admin CO 2 - CM - 3/20/2012 $ -
Admin CO 3 - CM - 4/25/2012 $ -
CO 4 - CC - 09/20/2012 $ 400,000.00
CO 5 - CC - 11/ i /21 13 $ 200,000.00
NEW CON C ' A it UNT $ 1,225,169.00
APPR O D A s ;1' S T Ai le ►A
Camilo Soto, Assistant City Attorney
cteo<<< n ciAkt-0s
George N. Cretekos, Mayor
ATTEST:
Ari 0a-0--
Rosemarie Call, City Clerk
Date:. 8,un /to 4 JG /3
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
Niriltvt. k a i'9 ir1 Zvi;
iam B. Horne, II City Manager r/
Central Florida '
0,01,41.01P
I II es, esident
By:
George
Date:
ctors-, Inc:
/al 3
(SEA.L)
Recommended By: City of Clearwater
76(-A0(-
Tara L Kivett, Eng Construction Manager
/zc
Michael D Quillen, E, City Engineer
Page 2 of 3
Change Order 5 - 2011 Sidewalk Contract
ITEM DESCRIPTION Estimated UNIT UNIT COST TOTAL COST
Quantity
New Sidewalks Code A: 0315 - 92339 - 563700 -541- 000 -0000
Increases:
28 Construct New 4" Concrete 3500 SF $2.45 $8,575.00
Sidewalk (3000 PSI w/Fiber
Mesh)
29 Construct New 6" Concrete 1000 SF $3.80 $3,800.00
Sidewalk (3000 PSI w/Fiber Mesh
and 6 "x6" /#10 x #10 Welded
Wire Mesh)
30 Root Pruning 230 LF $3.00 $690.00
31 Install Detectable Warning Mat on 30 EA $250.00 $7,500.00
Existing Sidewalk
32 Preparation, installation and 1 EA $500.00 $500.00
maintenance of Project Sign
33 Construct 4 ft. Wide ADA Ramp 7 EA $500.00 $3,500.00
34 Construct 5 ft Wide ADA Ramp 7 EA $500.00 $3,500.00
35 Upgrade 4 ft. wide ADA Ramp 8 EA $1,050.00 $8,400.00
36 Upgrade 5 ft. wide ADA Ramp 8 EA $1,050.00 $8,400.00
39 Contingency 1 LS $4,486.00 $4,486.00
Total Increases Code A: $49,351.00
Remove and Replace Sidewalks Code B: 0315 - 92277 - 563700- 541 - 000 -0000
Increases:
40 Install Detectable Warning Mat on 1 EA $250.00 $250.00
Existing Sidewalk
41 Preparation, installation and 1 EA $500.00 $500.00
maintenance of Project Sign
42 Remove & Replace 4" Concrete 14500 SF $3.20 $46,400.00
Sidewalk (3000 PSI w/Fiber Mesh
Reinforcing)
43 Remove & Replace 6" Concrete 100 SF $3.80 $380.00
Sidewalk (3000 PSI w/Fiber Mesh
Reinforcing)
44 Remove & Replace Valley Gutter 312.5 LF $16.00 $5,000.00
Curb
45 Remove & Replace Type I Curb 20 LF $16.00 $320.00
46 Remove & Replace Modified 20 LF $16.00 $320.00
47 Remove & Replace Straight Curb 50 LF $16.00 $800.00
48 Construct 4 ft. wide ADA Ramp 30 EA $1,050.00 $31,500.00
49 Construct 5 ft. wide ADA Ramp 30 EA $1,050.00 $31,500.00
50 Sod 10000 SF $0.45 $4,500.00
51 Adjust Sanitary Sewer Manhole 2 EA $500.00 $1,000.00
52 Root Pruning 500 LF $3.00 $1,500.00
53 Install Gravity Wall (Maximum 5 LF $50.00 $250.00
Height 24 Inches)
54 Install Straight Curb 500 LF $16.00 $8,000.00
1
Page 2 of 3
Change Order 5 - 2011 Sidewalk Contract
ITEM DESCRIPTION Estimated UNIT UNIT COST TOTAL COST
Quantity
55 Removal of 4" sidewalk 100 LF $2.00 $200.00
57 Clearing & Grubbing 1 LS $5,007.00 $5,007.00
60 Contingency 1 LS $13,222.00 $13,222.00
Total Increases Code B: $150,649.00
Total Increases to the Contract: $200,000.00