WATER TREATMENT PLANT NO. 2 - CONTRACT 4 - REVERSE OSMOSIS PLANT SITE EXPANSION PROJECT - 10-0039-UT-D - ADMINISTRATIVE CHANGE ORDER #1Administrative Change Order 1 Date: August 20, 2013 PROJECT: PROJECT NUMBER: 10- 0039 -UT (D) WTP 2 - Contract 4: Reverse Osmosis Plant Site Expansion CONTRACTOR: Poole & Kent Company of Florida 1781 NSW North River Drive Miami, Florida 33606 -1030 PO REFERENCE: COUNCIL AWARD: ST109476 Mav 1, 2013 DATE OF CONTRACT: May 31, 2013 CODE: 0315- 96767 - 563600 -533- 000 -0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT This change order swaps ODP items and increases and decreasess line items per Contractors schedule of values for no change in costs. STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT $20,787,325.00 Admin CO - C $0.00 By: ( —t (SEAL) NEW CON " ' T A t UNT $20,787,325.00 Patrick Carr, President ACCEPTED BY: Poole & Kent Co.of Fl APPR VED AS T RM: Camilo Soto, Assistant City Attorney ATTEST: /j k 1'W CC Oki"( Rosemarie Call, CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA iA) t Q.tt :un, William B. Horne, II City Manager Date: ' I/t Recommended By: City of Clearwater Rober Fahey, PE q- t t- 13 Project Manager Michael D Quillen, PE, City Engineer Page 2 of 5 Administrative Change Order 1 - WTP 2 - Contract 4: Reverse Osmosis Plant Site Expansion ITEM DESCRIPTION UNIT OUANTITY UNIT COST TOTAL COST Decreases: 2 Work Zone Traffic Control (MOT) 0.590163934 LS $12,200.00 ($7,200.00) 29 Asphalt Driveways and Parking 0.73 LS $100,000.00 ($73,000.00) Areas 34 Landscaping 0.540540541 LS $37,000.00 ($20,000.00) 35 Irrigation 0.285714286 LS $14,000.00 ($4,000.00) 37 Fencing -11 ft. Tall Chain Link 1740 LF $25.00 ($43,500.00) 39 Misc. Equipment Pads 0.25 LS $10,000.00 ($2,500.00) 40 Demo Existing HSP Facilities 0.6 LS $25,000.00 ($15,000.00) 41 Demo Existing Generator Building 0.714285714 LS $35,000.00 ($25,000.00) 42 Demo Existing Chemical Feed 0.545454545 LS $22,000.00 ($12,000.00) Facilities 43 Main Building 0.208024843 LS $4,790,000.00 ($996,439.00) 45A Furnish & Deliver RO Cartridge 0.292123077 LS $130,000.00 ($37,976.00) Filters - ODP Item 45B RO Cartridge Filters - Sale Tax 0.285714286 LS $7,560.00 ($2,160.00) Savings 46A Furnish & Deliver RO HP Feed 0.32895412 LS $861,342.00 ($283,342.00) Pumps - ODP Item 46B RO HP Feed Pumps - Sale Tax 0.359900794 LS $50,400.00 ($18,139.00) Savings 49 RO Clean-in -Place System 0.137479789 LS $192,341.00 ($26,443.00) Ozone Piping, Valves, and 0.082412914 LS $58,850.00 ($4,850.00) 52 Appurtenances 55 Iron Treatment Filter Package 0.226439692 LS $833,807.00 ($188,807.00) 58 Sodium Hypochlorite Chemical 0.323410014 LS $99,026.00 ($32,026.00) Equipment, Day Tanks, and Piping 64A Furnish & Deliver High Service 0.399637081 LS $316,875.00 ($126,635.00) Pumps - ODP Item 64B High Service Pumps - Sale Tax 0.444888889 LS $18,000.00 ($8,008.00) Savings 65 High Service Pump Piping, Valves, 0.757552021 LS $214,479.00 ($162,479.00) and Appurtenances 66 Finished Water GST (2.5 MG) 0.045753759 LS $1,230,500.00 ($56,300.00) 67 Recoat Existing Finished Water 1 LS $64,200.00 ($64,200.00) GST (5.0 MG) 68A Furnish & Deliver ATS - ODP Item 0.148166667 LS $30,000.00 ($4,445.00) 68B ATS - Sale Tax Savings 0.333333333 LS $1,800.00 ($600.00) 68C ATS - Installation, Testing, 0.736182562 LS $7,581.00 ($5,581.00) Warranty 69 Wiring and Conduit, Pull Boxes, 0.088043245 LS $1,347,849.00 ($118,669.00) Wiring Devices 70 MDP PNLs, MCC's 0.1466262 LS $341,351.00 ($50,051.00) 71 VFDs 0.894913829 LS $19,032.00 ($17,032.00) 72C Emergency Generator - Installation, 0.261202024 LS $54,142.00 ($14,142.00) Testing, Warranty 73A Furnish & Deliver Fuel Storage 0.063967052 LS $69,442.00 ($4,442.00) Tank - ODP Item Page 3 of 5 Administrative Change Order 1 - WTP 2 - Contract 4: Reverse Osmosis Plant Site Expansion ITEM DESCRIPTION UNIT OUANTITY UNIT COST TOTAL COST 73B Fuel Storage Tank — Sale Tax 0.063850216 LS $4,166.00 ($266.00) Savings 76 Site Lighting 0.707355442 LS $86,453.00 ($61,153.00) 77 Permitting, Testing, Studies 0.689618948 LS $20,942.00 ($14,442.00) 78A Furnish & Deliver Magmeters — 1 LS $9,075.00 ($9,075.00) ODP Item 78B Magmeters — Sale Tax Savings 1 LS $545.00 ($545.00) 80A Furnish & Deliver Controllers & 1 LS $87,641.00 ($87,641.00) Analyzers — ODP Item 80B Controllers & Analyzers — Sales 1 LS $5,258.00 ($5,258.00) Tax Savings 82A Furnish & Deliver Citect SCADA 1 LS $24,870.00 ($24,870.00) and Historian Software — ODP Item 82B Citect SCADA and Historian 1 LS $1,492.00 ($1,492.00) Software — Sales Tax Savings 82C Citect SCADA and Historian 0.875996457 LS $56,450.00 ($49,450.00) Software — Installation, Testing, Warranty 83 Servers and Racks 0.462446513 LS $46,507.00 ($21,507.00) 84A Furnish & Deliver Ethernet 1 LS $21,988.00 ($21,988.00) Switches / Autodialer/Printers — ODP Item 84B Ethernet 1 LS $1,319.00 ($1,319.00) Switches /Autodialer/Printers — Sales Tax Savings 86 SCADA workstations 1 LS $7,441.00 ($7,441.00) 87A Furnish & Deliver Plant MCP, CIP 1 LS $63,879.00 ($63,879.00) Control Panel, and Radio Panel — ODP Item 87B Plant MCP, CIP Control Panel, and 1 LS $3,832.00 ($3,832.00) Radio Panel — Sales Tax Savings 88A Furnish & Deliver Plant LCP No. 1 1 LS $54,750.00 ($54,750.00) PLC Equip - ODP Item 88B Plant LCP No. 1 PLC Equip - Sales 1 LS $3,285.00 ($3,285.00) Tax Savings 89A Furnish & Deliver Plant LCP No. 2 1 LS $32,559.00 ($32,559.00) PLC Equip - ODP Item 89B Plant LCP No. 2 PLC Equip - Sales 1 LS $1,953.00 ($1,953.00) Tax Savings 90A Furnish & Deliver Remote Wells 1 LS $214,116.00 ($214,116.00) and Interconnect PLC Equip. and Radio Panels - ODP Item 90B Remote Wells and Interconnect 1 LS $12,845.00 ($12,845.00) PLC Equip. and Radio Panels - Sales Tax Savings 90C Remote Wells and Interconnect 0.000358362 LS $53,019.00 ($19.00) PLC Equip. and Radio Panels - Installation, Testing, Warranty 92 Yagi & Omni Antenna/cables 0.009670278 LS $8,583.00 ($83.00) Page 4 of 5 Administrative Change Order 1 - WTP 2 - Contract 4: Reverse Osmosis Plant Site Expansion ITE1V1 DESCRIPTION 93 Furnish and Install Security Poles and Conduit/Wire Al Concentrate GST (1.5 MG) Increases: 7 Earthwork 9 Stormwater Pond 13 FDOT Type J -7T Stormwater Manhole 17 10 -inch PVC Stormwater Pipe 18 8 -inch PVC Stormwater Pipe 19 6 -inch PVC Stormwater Pipe 20 Retaining Walls 24 6 -inch DIP Water Line 28 Sanitary Lift Station 31 Concrete Sidewalk 33 Dumpster Enclosure 36 Fencing - 7 ft. Tall Chain Link 38 Fencing - 7 ft. Tall Ornamental Steel 44 Ozone Generator Building 45C RO Cartridge Filters - Installation, Testing, Warranty 46C RO HP Feed Pumps - Installation, Testing, Warranty 47A Furnish & Deliver RO Skids - ODP Item 47B RO Skids - Sale Tax Savings 47C RO Skids - Installation, Testing, Warranty 48 RO System Piping and Valves 50C Ozone Generators and System - Installation, Testing, Warranty 51 Ozone Dissipation Chamber and Transfer Pump Wet Well 53A Furnish & Deliver Transfer Pumps - ODP Item 53B Transfer Pumps - Sale Tax Savings 53C Transfer Pumps - Installation, Testing, Warranty 54 Transfer Pump Piping, Valves, and Appurtenances 56 Backwash Pump Station 57 Antiscalant Chemical Equipment, Day Tanks, and Piping 59 Ammonia Chemical Equipment, Day Tanks, and Piping 60 Caustic Chemical Equipment, Day Tanks, and Piping UNIT 0.933333333 0.058206897 0.315841837 1.333333333 17.77777778 116.3636364 43.33333333 156.8421053 1 143.9130435 1.8 285.7142857 0.285714286 3366.666667 17.85714286 0.312380952 2.738317757 1.03571759 0.0390968 0.04647619 1.36318408 0.215353491 1.925253231 1.696929239 7.338417708 7.325833333 24.23364486 0.488058152 0.780089004 0.25 0.712702021 0.167821725 QUANTITY LS UNIT COST $30,000.00 LS $725,000.00 Total (Decreases): LS $316,611.00 LS $30,000.00 EA $1,800.00 LF $22.00 LF $21.00 LF $19.00 LS $25,000.00 LF $69.00 LS $25,000.00 SY $14.00 LS $7,000.00 LF $15.00 LF $112.00 LS $210,000.00 LS $2,675.00 LS $10,807.00 LS $1,250,000.00 LS $63,000.00 LS $16,080.00 LS $454,750.00 LS $22,904.00 LS $37,450.00 LS $22,815.00 LS $1,200.00 LS $1,070.00 LS $48,150.00 LS $99,995.00 LS $36,000.00 LS $32,113.00 TOTAL COST ($28,000.00) ($42,200.00) ($3,188,934.00) $99,999.00 $40,000.00 $32,000.00 $2,560.00 $910.00 $2,980.00 $25,000.00 $9,930.00 $45,000.00 $4,000.00 $2,000.00 $50,500.00 $2,000.00 $65,600.00 $7,325.00 $11,193.00 $48,871.00 $2,928.00 $21,920.00 $97,932.00 $44,096.00 $63,550.00 $167,426.00 $8,791.00 $25,930.00 $23,500.00 $78,005.00 $9,000.00 $22,887.00 LS $52,234.00 $8,766.00 Page 5 of 5 Administrative Change Order 1 - WTP 2 - Contract 4: Reverse Osmosis Plant Site Expansion ITEM DESCRIPTION UNIT OUANTITY UNIT COST TOTAL COST 61 Corrosion Inhibitor Chemical 0.915219612 LS $23,496.00 $21,504.00 Equipment, Day Tanks and Piping 62 Bulk Chemical Storage Tanks 1.742424535 LS $51,779.00 $90,221.00 63 Yard Piping, Valves, Fittings, and 0.474112469 LS $1,192,099.00 $565,189.00 Appurtenances 64C High Service Pumps — Installation, 4.794392523 LS $5,350.00 $25,650.00 Testing, Warranty 72A Furnish & Deliver Emergency 0.048717949 LS $390,000.00 $19,000.00 Generator — ODP Item 72B Emergency Generator — Sale Tax 0.039102564 LS $23,400.00 $915.00 Savings 73C Fuel Storage Tank — Installation, 0.17370892 LS $13,632.00 $2,368.00 Testing, Warranty 74 Lighting and Power Panels and UPS 3.465738979 LS $43,621.00 $151,179.00 75 Lightning Protection 0.259954066 LS $46,589.00 $12,111.00 78C Magmeters — Installation, Testing, 0.045150502 LS $14,352.00 $648.00 Warranty 79 Pressure transmitters/ 2.024222445 LS $139,540.00 $282,460.00 switches /gages /ultrasonic level sensors and transmitters 80C Controllers & Analyzers — 0.036770805 LS $28,936.00 $1,064.00 Installation, Testing, Warranty 81 Programming, Integration and Start- 0.116694584 LS $42,984.00 $5,016.00 up 84C Ethernet 13.22656801 LS 11,352.00 $150,148.00 Switches /Autodialer/Printers — Installation, Testing, Warranty 85 Fiber Patch Panels /Cabinets/ 0.165032942 LS $12,446.00 $2,054.00 Terminations 87C Plant MCP, CIP Control Panel, and 69.45759142 LS $5,223.00 $362,777.00 Radio Panel — Installation, Testing, Warranty 88C Plant LCP No. 1 PLC Equip - 7.041355543 LS 1,741.00 $12,259.00 Installation, Testing, Warranty 89C Plant LCP No. 2 PLC Equip - 4.743825388 LS $1,741.00 $8,259.00 Installation, Testing, Warranty 91 Radios /antennas 5.010965057 LS $30,278.00 $151,722.00 Total Increases: $2,889,143.00 Additions: 55B Sale Tax Savings 1 LS $36,053.00 $36,053.00 55C Installation, Testing, Warranty 1 LS $88,000.00 $88,000.00 97A Chemical Feed & Transfer Pumps 1 LS $166,000.00 ODP Item $166,000.00 97B Chemical Feed & Transfer Pumps - 1 LS $9,738.00 $9,738.00 Sales Tax Savings Total Additions: $299,791.00 Total Net (Decreases)/Increases /Additions to the Contract: $0.00