2011 UNDERDRAINS PROJECT - 10-0016-EN - ADMINISTRATIVE CHANGE ORDER #2 & FINALAdministrative Change Order #2 & Final
Date: July 31, 2013
PROJECT: 2011 Underdrain Contract PROJECT NUMBER: 10- 0016 -EN
CONTRACTOR: Adkins Contracting, Inc.
3516 Gulf City Road
Ruskin, Florida 33570
PO REFERENCE NO.: ST 107955
AWARD DATE: October 20, 2011
CONTRACT DATE: November 04, 2011
CODE: 0315-92277-563700-541-000-0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order decreases and increases items according to field conditions, adds 30 days to contract and closes out the project.
STATEMENT OF CONTRACT AMOUNT
ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
Change Order 1 - CC - 1/17/2013
Adm. CO#2 & Final
NEW CONTRACT AMOUNT
Camilo Soto, Assistant City Attorney
ATTEST:
, Lfl ./2/ i.i
Rosemarie Call, City Clerk
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
ifka,, 644,,,,E---xt,
William B. Horne, II City Manager
$538,012.84
$253,010.89
(510,223.81)
5780,799.92 • ckie Dean Adkins, President
Adkins Contracting, Inc.
Fi< V
AL) Y
Date: g// j 2(143
Witnesses:
RECOMMENDED BY:
CITY OF CLEARWATER
Tara L.Kivett, Eng. Construction Manager
e7V6
Michael D. Quillen, E, City Engineer
Page 2 of 2
Admininstrative Change Order 2 & Final - 2011 Underdrain Contract
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Code B: 0315-92277-563700-541-000-0000
Decreases:
1 Mobilization 1 EA $612.53 (8612.53)
3 Maintenance of Traffic - Under Drain, Multi 2 EA , $597.40 ($1,194.80)
Lane
6 Sediment & Erosion Control 3 EA $83.17 (8249.51)
8 Root Pruning 694 LF $6.00 ($1,164.00)
9 Tree Barricades 930 LF $3.80 ($3,534.00)
11 Remove Existing Concrete Sidewalk, 4" 1,204 SF $2.73 ($3,286.92)
16 ADA Sidewalk Ramp, 4" Concrete 1,170.5 SF $10.80 ($12,641.40)
FDOT Underdrain Inspection Box, Index
18 #245 3.0 EA $870.96 ($2,612.88)
19 6" Underdrain 4.0 LF $23.57 ($94.28)
22 8" Underdrain 2,486.5 LF $26.12 ($64,947.38)
26 Modified Curb (Remove & Replace) 163 LF $34.37 ($5.,602.31)
27 Valley Gutter Curb (Remove & Replace) 176 LF $44.57 ($7.,844.32)
28 Swale Curb, 4' Wide, (bid includes adjacent 14 LF $72.37 ($1[ 013.18)
asphalt)
35 10% Contingency 1 LS $48,910.26
($48,910.26)
Total (Decreases): ($156.,707.77)
Increases:
2 Maintenance of Traffic, Underdrain, 2 Lane, 2 5 EA $262.11 $1.,310.55
Way
4 Maintenance of Traffic - Kapok Park Trail 1 EA $115.40 $115.40
10 Remove Existing Underdrain 4,085 SF $2.53 $10,335.05
12 Remove Existing Concrete Sidewalk, 6" 9,884.78 SF $2.19 $21,647.67
13 Remove Existing Asphalt 175.24 SY $18.45 $3.233.18
14 Core Existing Storm Inlet 19 EA $375.50 $7.,134.50
15 Concrete Driveway, 6" 9,914.78 SF $4.07 $40,353.15
17 Concrete Sidewalk, 4" 24 SF $3.54 $85.67
23 8" Clean Out 24 LF $229.63 $5.,511.12
24 8" Solid PVC Storm Pipe 2,167 LF $12.45 $26.972.93
25 Type I Curb (remove and replace) 441 LF $26.37 $11.,629.17
30 Asphalt 1 -1/2" Thick PC III 49.07 SY $30.09 $1,476.52
31 10" Thick Crushed Concrete Road Base 56.18 SY $26.91 $1.,511.80
32 Sod Replacement (Bahia) 4,719 SF $0.58 $2.737.02
33 Sod Replacement (St. Augustine) 14,064 SF $0.71 $9.,985.44
34 Sod, Cynodon Dactylon (Bermuda 419- 1,040 SF $1.82 $1,892.80
Certified)
37 Install 8x8 tee 4 EA $138.00 $552.00
Total Increases: $146,483.96
Total Net (Decreases)/Increases: ($10.223.81)