MARSHALL STREET WRF RAPID SAND FILTER REHABILITATION - 09-0045-UT - ADMINISTRATIVE CHANGE ORDER #3 & FINAL�
Administrative Change Order 3& Final
PROJECT: Marshall Street WRF Rapid Sand
Filter Rehabiltation Project
CONTRACTOR: Wharton-Smith, Inc.
750 Monroe Road
Date: Mav 14, 2013
PROJECT NUMBER: 09-0045-UT
PO REFERENCE NO.: ST 107455
COUNCIL AWARD: 04/Q4/2011
DATE OF CONTRACT: OS/Q2/2011
Sanford, FL 32771 CODE: 0376-96664-563800-535-000-0000 "A"
CODE: 0315-96664-563800-535-000-000►0 "B"
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT ,
The change order Decreases Owner Direct Purchased items and Sales T� Savings and adjusts items according to field conditions -
see attached.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: Wharton-S 'th, Inc.
ORIGINAL CONTRACT AMOUNT $2,433,819.24
CO 1- CC - 1/12/2012 $ 455,222.52 By: Seal
CO 2- CC - 7/19/2012 $ - W' i ogan, roject Manager' ., �,
Admin CO 3& Final - CM
NEW CONTRACT AMOUNT
ATTEST:
� %�
Rosemarie Call,
C
William
� � �`�
��
:~ , '�
: .�+r � !
, ,� ,
.
� - �� .k� -+
� ! s t �'; �", �+�r;
i
.
� ��, w
:+ w
� ' � ,�
1 ' �'y.... . ,!
\����� , �.>.
� �r'��c��.�`'
�� �
1' 1�
�
($1,385,992.34) . . � � �
$1,503,049A2 Date: s'�� _ 4� _., ^
'� j� _r. .
. � � , 4,�
WITNESSES: " y`` �"' ` ' `'� ° °
, ,�, ,�� ►
`� .. ���,;.
��� ^,,;
� ��
Recommended By: City of Clearwater
�
�
City M ager ' ._
Tara Kivett, Eng. Construction Manager
Camilo Soto, Assistant City Attorney
� � .
Michael D. Quillen, PE, City Engineer
i
Page 2 of 2
Administrative Change Order 3& Final - MS WRF Rapid Sand Filter Rehabilitation
ITEM DESCRIPTION
Code B:
Decreases•
lb Sand Filter Rehab Equipment in accordance
to Section 01150, 3.OlA ODP Sales Tax
Savings retained by the City
2b
Additional New Underdrain Core Assemblies
in accordance with Section 01150, 3.O1B.-
ODP - Sales Tax Savings retained by the City
UNIT QUANTITY
1 LS
9 EA
�b Additional New Underdrain Care Assemblies 171
in accordance with Section 01150, 3.O1B.-
ODP - Sales Tax Savings retained by the City
Code A:
Decrease•
g 1 U% c:ontmgency
Additions
8 Furnish & Install Clips for Filters 5,6,7, 8, 11
9 Furnish & Install Clips for Filters #1,2,3,4,9,1�
10 Repair Leak in Filter #9
11 Mudwell Transmitter w/ Enclosure
12 Flowswitch for Eyewash
13 8" LP Air Shutdown
14 Add Chemical Pump HOA
15 Existing Coating Removal in Filter 1&2
16 Credit for Surveyed As-Builts
17 Additional Shop Drawing Review
Decreases for Owner Direct Purchases (ODP):
la Sand Filter Rehab Equipment in accordance
to Section 01150, 3.OlA (ODP amount paid
directly to Siemens by the City)
2a Furnish and deliver Additional New
Underdrain Core Assemblies in accordance
with Section 01150, 3.O1B.- (ODP amount
paid directly to Siemens by the City)
�a Furnish and deliver Additional New
Underdrain Core Assemblies in accordance
with Section 01150, 3.O1B.- (ODP amount
paid directly to Siemens by the City)
1
EA
EA
LS
LS
LS
LS
LS
LS
LS
EA
EA
UNIT COST
$50,210.00
$128.62
$112.12
TOTAL COST
�;$50,210.00)
($1,157.58)
{ $19,172.52)
Total (Decreases) Code B: ($70,540.10)
LS $212,892.66 (:6212,892.66)
Total (Decreases) Code A: (!�212,892.66)
5
7
1
1
1
1
1
1
1
8
$ 3,267.60 $16,338.00
$ 3,083.71 $21,585.97
$ 1,976.00 $1.976.00
$ 10,812.45 $10,812.45
$ 1,884.00 $1.884.00
$ 1,901.00 $1,901.00
$ 3,296.00 $3,296.00
$ 13,550.00 $13,550.00
($750.00) ($750.00)
($293.00) ($2,344.00)
Total Additions Code A: $68,249.42
Total Net (Decreases)/Additions Code A: (�144,643.24)
Total Net (Decreases)/Additions to PO: (5215,183.34)
1 LS
9 EA
171 EA
$836,000.00
$2,051.00
$1,850.00
($836,000.00)
($18,459.00)
($316,350.00)
Total (Decreases) ODP: ($1,170,809.00)
Total Net (Decreases)/Additions to the Contract: ($1,385,992.34)