2011 SIDEWALK CONTRACT - 11-0012-EN - ADMINISTRATIVE CHANGE ORDER #4,- °
CHANGE ORDER 4
PROJECT: 2011 Sidewalk Contract
CONTRACTOR:
Central Florida Contractors, Inc.
PO Boz 3987
Date: August 17, 2012
PROJECT NUMBER: 11-0012-EN
PO REFERENCE NO: ST108005
CONTRACT AWARD: November 03, 2011
CONTRACT DATE: December 13. 2011
Seminole, Florida 33775 CODE: 0315-92339-563700-541-000-0000 A
CODE: 0315-92273-563700-541-000-0000 B
SCOPE OF CHANGE: TffiS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
E�ctends the contract for 180 days and increases the funding on a unit price basis only for a not to exceed amount, with all
other terms and conditions remairung the same, see attached for details.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY•
ORIGINAL CONTRACT AMOUNT
Admin CO 1- CM - 2/15/2012
Admin CO 2- CM - 3/20/2012
Admin CO 3- CM - 4/25/2012
C04-CC-09/0� 12
NEW CONTR�CT WMnillv
AS TO
Camilo Sd Ass' fiy ,
— G��r�t'�C't��
George N. Cretekos, Mayor
ATTEST:
�-�- �`�
Rosemarie Call, City Clerk ��
v
Date: y�{,�a-�"n G�-t�i ���� - �
$
$
568,337.00
56,832.00
$ 400,000.00
$ 1,025,169.00
SHE C`����\�
j ��
�
�� �
CITY OF CLEARWATER, in �
PINELLAS COUNTY, FLORIDA
�_ �
Witliam B. Horne, II City Manager
-�; U� _
, .,
` � ' �,
Central Flori ntractors, �c,;; :.� � � �":
.' t ?
g�i ,�_. �' «�
By: �� (��" � q :
George Gom , Presiden� `.-, � ``��'".� �r � =�
� '� �,
��'�i . � � �v
.
, f .^
Date: S 3/ /� °.f�1,,j;.,
Witnesses:
�I � 9
�j�
Recommended By: City of Clearwater
Tara L Kivett, Eng Construction Manager
�� �
Michael D Quillen, PE, City Engineer
Page 2 of 3
Change Order #4 - 2011 Sidewalk Contract
ITEM DESCRIPTION Estimated
uanti
New Sidewalks Code A: 0315-92339-563700-541-000-0000
Addition•
28 Construct New 4" Concrete 6000
Sidewalk (3000 PSI w/Fiber
Mesh)
29 Construct New 6" Concrete 2000
Sidewalk (3000 PSI w/Fiber Mesh
and 6"x6" /# 10 x# 10 Welded
Wire Mesh)
30 Root Pruning 230
31 Install Detectable Warning Mat on 163
Existing Sidewalk
32 Preparation, installation and 1
maintenance of Project Sign
UNIT UNIT COST
SF $2.45
SF $3.80
LF $3.00
EA $250.00
EA $500.00
TOTAL COST
$14,700.00
$7,600.00
$690.00
$40,750.00
$500.00
33 Construct 4 ft. Wide ADA Ramp 7 EA $500.00 $3,500.00
34 Construct 5 ft Wide ADA Ramp 7 EA $500.00 $3,500.00
35 Upgrade 4 ft. wide ADA Ramp 16 EA $1,050.00 $16,800.00
36 Upgrade 5 ft. wide ADA Ramp 16 EA $1,050.00 $16,800.00
37 Remove Concrete Dumpster Pad 1 EA $500.00 $500.00
38 Adjust Sanitary Sewer Manhole 2 EA $500.00 $1,000.00
39 Contingency 1 LS $3,561.46 $3,561.46
Total Net Increases Code A: $109,901.46
Remove and Renlace Sidewalks Code B: 0315-92273-563700-541-000-0000
Additions
40 Install Detectable Warning Mat on 1 EA
Existing Sidewalk
41 Preparation, installation and 1 EA
maintenance of Project Sign
42 Remove & Replace 4" Concrete 27775 SF
Sidewalk (3000 PSI w/Fiber Mesh
Reinforcing)
43 Remove & Replace 6" Concrete 700 SF
Sidewalk (3000 PSI w/Fiber Mesh
Reinforcing)
44 Remove & Replace Valley Gutter 312.5 LF
Curb
45 Remove & Replace Type I Curb 20 LF
46 Remove & Replace Modified 20 LF
47 Remove & Replace Straight Curb 50 LF
48 Construct 4 ft. wide ADA Ramp 59 EA
49 Construct 5 ft. wide ADA Ramp 59 EA
50 Sod 30000 SF
51 Adjust Sanitary Sewer Manhole 5 EA
52 Root Pruning 500 LF
53 Install Gravity Wall (Maximum 5 LF
Height 24 Inches)
54 Install Straight Curb 137.5 LF
$250.00
$500.00
$3.20
$3.80
$16.00
$16.00
$16.00
$16.00
$1,050.00
$1,050.00
$0.45
$500.00
$3.00
$50.00
$16.00
$250.00
$500.00
$88,880.00
$2,660.00
$5,000.00
$320.00
$320.00
$800.00
$61,950.00
$61,950.00
$13, 500.00
$2,500.00
$1,500.00
$250.00
$2,200.00
. .r . .
54 Install Straight Curb 137.5 LF $16.00 $2,200.00
Page 2 of 3
Change Order #4 - 2011 Sidewalk Contract
55 Removal of 4" sidewalk 100 LF $2.00 $200.00
56 Grinding (across the sidewalk) 108 LF $10.00 $1,080.00
57 Clearing & Grubbing 1 LS $5,007.00 $5,007.00
58 6-18" Wall 100 LF $30.00 $3,000.00
59 19 - 30" Wall 100 LF $55.00 $5,500.00
60 Contingency 1 LS $32,731.54 $32,731.54
Total Net Increases Code B: $290,098.54