SKYCREST EXPANSION & CHAUTAUQUA LAKE ESTATES RCW PROJECT - 09-0044-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALG
�ADMINISTRATIVE CHANGE ORDER Change Order 1& Final
PROJECT: Skycrest Expansion & Chautauqua Lake Estates RCW
Project
CONTRACTOR:
Young's Communication
424 West Drive
Melbourne, F132904
DATE: August 31, 2012
PROJECT NUMBER: 09-0044-UT
PO REFERENCE NO: ST107604
COUNCIL AWARD: June 14. 2011
DATE OF CONTRACT: June 29 .2011
CODE: 0315-96739-563800-533-000-0000 A
CODE: 0315-96739-563800-533-000-0000 B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order adjusts quantities and adds new items according to fieid conditions and adds 59 calendar days to th�; ..
contract - see details attached . � ��,�
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin CO 1& Final - CM
NEW CONTRACT AMOUNT
ATTEST:
�°��.� �c.,
Rosemarie Call,
Date: �i �%���vilc
City Clerk
17� .:J—�%i�� �'=
CITY OF CLEARWATER, in
PINE�,.LAS COUNTY, FLORIDA
0
W111i8Iri
- ' 1/�l�" � � .
orng II ,�City Manager
Camilo Soto, Assistant City Attorney
$ 1,160,489.00
($149,016.35)
$ 1,011,472.65
TNE
�
�
,,
1. �
'��
, ` �: ++�:
� �:
ACCEPTED B .
Young's Co mm ' a1
B: �'�—
Date: � ' y' ��
Wimesses:
O
� � y�
i `'
� � �� :
}�> y,
y.l �,, .
,) ,
� �• � _
� ��
Recommended By: City of Cle ater
..__.. _........
��:;.
Lan—Anh Nguyen, Project Manager
t. �.
Michael D Quillen, PE, City Engineer
�
� Page 2 of 4 continued:
RE: Administrative Change Order 1& Final - Skycrest Expansion & Chautauqua Lake Estates RCW Project
ITEM DESCRIPTION UNIT QUANTITY UNIT COST
Skvcrest Exaansion Code: A 0315-96739-563800-533-000-0000
Decreases•
AS F&I 4" PVC Pipe by Open Cut LF 998 $12.00
A6 F&I 6" PVC Pipe by Open Cut LF 533 $18.00
A8 F&I 6" Resilient Wedge Gate Valve & EA 5 $790.00
Valve Box
A10 F&I 1" Short Side Service Assembly for EA 47 $450.00
Reclaimed Water System
Al l F&I Single 1" Long Side Service EA 14 $725.00
Assembly for Reclaimed Water System
(2" Casing)
Al2 F&I Single 2" Long Side Service Assemb EA 7 $1,110.00
A13 Root Pruning LF 986 $3.00
A18 Connect to Existing 6" RCW Main at LS 1 $1,475.00
Plaza Street and Pennsylvania Avenue
A19 Sod Restoration as Directed by the SY 400 $4.00
Owner or the Owner's Authorized
Project Representative
A24 Underdrain Restoration as Directed by LF 171 $ 9.00
the Owner or the Owner's Authorized
Project Representative
TOTAL COST
($11,976.00)
($9,594.00)
($3,950.00)
($21,150.00)
($10,150.00)
($7,770.00)
($2,958.00)
($1,475.00)
($1,600.00)
($1,539.00)
A25 10% Contingency LS 1 $80,723.50 ($80,723.50)
Total (Decreases) Code A: ($152,885.50)
Increases•
A1 Mobilization (3.5% Maximum)
A2 Maintenance of Traffic (1.5%
A3 F&I 4" PVC Pipe by Horizontal
Directional Drill
A4 F&I 6" PVC Pipe by Horizontal
Directional Drill
A7 F&I 4" Resilient Wedge Gate Valve &
Valve Box
A9 F&I 4" Blow-off Assembly, Reclaimed
Water System
A21 Concrete Sidewalk Restoration as
Directed by the Owner or the Owner's
Authorized Project Representative
Addirions•
A26 Video
A27 LayoudAs-builts
A28 Connect to Existing 4" RCW Main at
Palmetto St and Holt Ave.
A29 F&I 4" HDPE Pipe by Horizontal
Directional Drill
A30 Dewatering 100 Pierce St.
LS
LS
LF
LF
EA
EA
SY
LS
LS
LS
LF
LS
0.54195 $20,000.00
0.763333333 $1,500.00
1359 $15.50
329 $23.00
5 $665.00
1 $1,100.00
18 $45.00
Total Increases Code A:
1 $ 2,825.00
1 $ 9,889.50
1 $1,500.00
1,430 $ 17.00
1 $1,852.00
$10,839.00
$1,145.00
$21,064.50
$7,567.00
$3,325.00
$1,100.00
$810.00
$45,850.50
$2,825.00
$9,889.50
$1,500.00
$24,310.00
$1,852.00
,
Page 3 of 4 continued:
RE: Administrative Change Order 1& Final - Skycrest Expansion & Chautauqua Lake Estates RCW Project
ITEM DESCRIPTION UNIT OUANTITY UNIT COST TOTAL COST
A31 Restoration 100 Pierce St. LS 1 $570.00 $570.00
A32 Remove Existing BlowoffAssembly EA 1 $563.00 $563.00
Catalina Dr.
A33 Remove Existing 4" Tee Maple St. EA 1 $775.00 $775.00
A34 Remove Existing 90deg bend Maple St EA 1 $800.00 $800.00
A35 Relocate Blowoff Assemblly Catalina EA 1 $715.00 $715.00
A36 16"X4" Tapping Sleeve EA 1 $3,688.00 $3,688.00
A37 Druid St. & Hercules Skycrest LS 1 $2,133.40 $2,133.40
A38 6" Tee & 6X4 Reducer Maple St. EA 1 $1,000.00 $1,000.00
A39 4" MJ Cross EA 1 $1,500.00 $1,500.00
A40 4" 22deg Fitting Glen Oaks Park EA 1 $241.00 $241.00
A41 4" 45deg bend Maple St. EA 2 $241.00 $482.00
A42 4" 90deg Fitting Glen Oaks Park EA 1 $241.00 $241.00
Total Additions Code A: $53,084.90
Total Net (Decreases)/Increases/Additions Code A: ($53,950.10)
Chautauaua Lake Estates RCW Code B: 0315-96739-563800-533-000-0000
Decreases•
B3 F&I 4" PVC Pipe by Horizontal Directior LF 121 $15.75 ($1,905.75)
B4 F&I 6" PVC Pipe by Horizontal Directior LF 98 $23.00 ($2,254.00)
BS F&I 4" HDPE Pipe by Horizontal LF 446 $17.00 ($7,582.00)
Directional Drill
B6 F&I 4" PVC Pipe by Open Cut LF 533 $14.00 ($7,462.00)
B7 F&16" PVC Pipe by Open Cut LF 104 $16.75 ($1,742.00)
B8 F&I 4" HDPE Pipe byOpen Cut LF 400 $19.00 ($7,600.00)
B10 F&I 6" Resilient Wedge Gate Valve & EA 1 $790.00 ($790.00)
Valve Box
B 11 F&I 4" Blow-off Assembly, Reclaimed EA 1 $1,100.00 ($1,100.00)
Water System
B 12 F&I 1" Short Side Service Assembly for EA 20 $450.00 ($9,000.00)
Reclaimed Water System
B13 F&I Single 1" Long Side Service EA 1 $725.00 ($725.00)
Assembly for Reclaimed Water System
(2" Casing)
B 14 F&I Single 2" Long Side Service EA 1 $1,110.00 ($1,110.00)
Assembly for Reclaimed Water System
(4" Casing)
B15 Root Pruning LF 295 $3.00 ($885.00)
B18 Sod Restoration as D'uected by the SY 200 $4.00 ($800.00)
Owner or the Owner's Authorized
Project Representative
B19 Concrete Driveway Restoration as SY 100 $55.00 ($5,500.00)
Directed by the Owner or the Owner's
Authorized Project Representative
B20 Concrete Sidewalk Restoration as SY 100 $45.00 ($4,500.00)
Directed by the Owner or the Owner's
Authorized Project Representative
B21 Concrete Curb Restoration as Directed LF 100 $45.00 ($4,500.00)
by the Owner or the Owner's Authorized
Project Representative
.�
� Page 4 of 4 continued:
RE: Administrative Change Order 1& Final - Skycrest Expansion & Chautauqua Lake Estates RCW Project
ITEM DESCRIPTION
B22 Asphalt Paving Restoration as Directed
by the Owner or the Owner's Authorized
Project Representative
B23 Underdrain Restoration as Directed by
the Owner or the Owner's Authorized
Project Representative
B24 Owner's Contingency
Increases•
„
UNIT
SY
LF
LS
OUANTITY UNIT COST
200 $45.00
500 $9.00
TOTAL COST
($9,000.00)
($4,500.00)
1 $24,775.50 ($24,775.50)
Total (Decreases) Code B: ($95,731.25)
B9 F&I 4 Resihent Wedge Gate Valve & V� EA 1 $ 665.00 $665.00
Total IncreasesCode B: $665.00
Total Net (Decreases)/Increases CodeB: ($95,066.25)
Total Net (Decreases)/Increases/Additions to Contract: ($149,016.35)