GULF TO BAY / HIGHLAND AVENUE IMPROVEMENTS (GATEWAY) - 08-0051-EN - ADMINISTRATIVE CHANGE ORDER #1; w
ADMINISTRATIVE CHANGE ORDER 1
PROJECT: Gulf-to-Bay Blvd./Highland Ave. Improvements
Project
CONTRACTOR: Gibbs & Register, Inc.
232 S. Dillard Street
Winter Garden, FL 34787
Date: Julv 3, 2012
PROJECT NUMBER: 08-0051-EN
PO REFERENCE NO.: ST107810
AWARD DATE: September Ol, 2011
CONTRACT DATE: September 23, 2011
CODE: 0315-92270-563700-541-000-0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order adjusts and adds quantities used in the field and adds 30 days to the contract. See attached details.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
��� , ����� :.
ORIGINAL CONTRACT AMOUNT $340,265.20 Gibbs & Re ister, Inc. ,��
Admin CO 1 - $12,486.37 � �`��", � �E�� '�
<; °
;� � �_. � ,
NEW C RAC AMOUNT $352,751.57 ��` 1�,�, ,',
1 . � _ �, � , n�:. t�
Camilo Soto, Assistant City Attorney
Date:
Rosemarie Call,
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
. �
William B. Horne, II City Manager
Date:
,.��_.�,,, .
ison, resi ent ' u "°�
7�� ,, � � , �
l� � 2 °'
Witnesses:
� • �
.• -
Recommended By:
City of Clearwater
��'—�/1d.��
Tara L Kive�tt,Engineering Construction Manager
� G�
Michael D Quillen, PE , City Engineer
� T
Continued Page 2 of 2
Administrative Change Order 1- Gulf to Bay/Highland Ave Improvements Project 08-0051-EN
ITEM DESCRIPTION
Decreases•
2001 Asphalt Milling
2002 Removal of Asphalt & Base
2004 Removal of Concrete Walk
2006 Removal of Unsuitable Material
3001 Asphalt, Surface Course, Type S-3, 1"
4003 6" Double Yellow Paint Center Line
4005 24" White Paint Stop Bar
5004 Concrete Curb, FDOT Type D
6004 Blueberry Flax Lilly, 3 gal.
7002 Conduit 2" Hand Trenched
7004 Conduit 1" Hand Trenched
7006 Contingency
Increases•
2003 Removal of Concrete Curb
2005 Material from Planting Areas
4001 6" White Paint Lane Line
4002 6" Yellow Paint Edge Line
4004 12" White Painted Crosswalk
4006 FDOT Standard Arrows (Paint)
5003 24" Wide Concrete Flush Curb at
Crosswalks
5005 6" Concrete Sidewalk
6005 Coontie - 7 Gal.
7003 Conduit 2" Directional Bore
Additions•
2007 Demo Extra Depth Asphalt
3002 Asphalt Design Mix to 12.5
4007 Striping
4008 18" White at Gore
5008 Sidewalk & Resoration
7006 Repair Conduit
QUANTITY UNIT UNIT COST
734
99
109
20
734
112
21
165
172
833
25
0.676722744
SY $2.00
SY $14.00
SY $12.00
CY $76.00
SY $7.00
LF $1.50
LF $3.00
LF $18.00
EA $11.00
LF $5.00
LF $4.00
LS $30,933.20
Total (Decreases):
21 LF $8.00
130 CY $80.00
366 LF $1.00
159 LF $1.00
246 LF $2.00
3 EA $39.00
58 LF $45.00
67 SY $50.00
28 EA $38.00
706 LF $13.00
1
3664
1
48
1
1
Total Increases:
LS $4,610.00
SY $2.00
LS $2,431.58
LF $3.00
LS $9,440.00
LS $1,739.99
Total Additions:
TOTAL COST
($1,468.00)
($1,386.00)
($1,308.00)
($1,520.00)
($5,138.00)
($168.00)
($63.00)
($2,970.00)
($1,892.00)
($4,165.00)
($100.00)
($20,933.20)
($41,111.20)
$168.00
$10,400.00
$366.00
$159.00
$492.00
$117.00
$2,610.00
$3,350.00
$1,064.00
$9,178.00
$27,904.00
$4,610.00
$7,328.00
$2,431.58
$144.00
$9,440.00
$1,739.99
$25,693.57
Total Net (Decreases)/Increases/Additions to the Contract: $12,486.37