2011 SIDEWALK CONTRACT - 11-0012-EN - ADMINISTRATIVE CHANGE ORDER #2�
ADMINISTRATIVE CHANGE ORDER #2
� � PROJECT: 2011 Sidewalk Contract
CONTRACTOR:
Central Florida Contractors, Inc.
P.O. Box 3987
Seminole, Florida 33775
Date: March 12. 2012
PROJECT NUMBER: 11-0012-EN
PO REFERENCE NO.: ST 108005
CONTRACT AWARD: November 03. 2011
CONTRACT DATE: December 13, 2011
CODE: 0315-92339-563700-541-000-0000 A
CODE: 0315-92273-563700-541-000-0000 B
SCOPE OF CI3ANGE: ' THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT `
This change order is necessary to adjust quantities used in the field. '
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
Adm. CO#1 - CM Approved 2/15/12
Adm. CO#2
NEW CONTRACT AMOUNT
Camilo Soto, Assistant City Attorney
Date:
ATTEST:
' /l_ �e Be�/.�11
Rosemarie Call, City Clerk �n,. -_— �
'�t9.
�
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
�C��w �'�-' . /N-a-c.u�-�
William B. Horne, II City Manager
$568,337.00
$56,832.00
$a.00
$625,169.00
r�
�,�
' r o� �,`.� !'�
Central Florida Contractors, I1�c z�',f ; .
x
. ,..
�,
.. �:
, . .:_
By: (�EAL}
George no , President
Date: �v1-
Witnesses:
, 1 ��-
�� Hob Divi
�1 ��°
� �.��Q. ��1 cl..►ee
� Alice Eckman •
Recommended By: City of Clearwater
�L� �• _
Tara L. Kivett
Engineering Construction Manager
� � �^ ,
�
Michael D. Quillen, PE
City Engineer
<.
. • Page 2 of 2
Administrative Change Order #2
Re: 2011 Sidewalk Contract
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Remove & Renlace Sidewalks Code: 0315-92273-563700-541-000-0000 "B"
Decreases•
19 Constuct 5 Ft. wide ADA Ramp 20 EA $1,050.00
20 Constuct 4 Ft. wide ADA Ramp 56 EA $1,050.00 �$21,000.00)
($58,800.00)
Total Decreases: ($79,800.00)
Increases•
21 Sod 20400 SF $0.45 $9,180.00
24 Gravity Wall (Max Height 24") 1350 LF $50.00 $67,500.00
27 Removal of 4" only 1560 SY $2.00 $3,120.00
TotalIncreases: $79,800.00
Total Net (Decreases)/Increases/Additions to the Contract $0.00