MARSHALL STREET WRF RAPID SAND FILTER REHABILITATION - 09-0045-UT - CHANGE ORDER #1Change Order 1
PROJECT: Marshall Street WRF Rapid Sand Filter Rehabilitation
Project
CONTRACTOR: Wharton-Smith, Inc.
750 Monroe Road
Date: December 20, 2011
PROJECT NUMBER: 09-0045-UT
PO REFERENCE NO.: ST 107455
COUNCIL AWARD: 04/07/2011
DATE OF CONTRACT: OS/02/2011
Sanford, FL 32771 CODE: 0376-96664-563800-535-000-0000 "A"
CODE: 0315-96664-563800-535-000-0000 "B"
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order is to add items to accommodate field conditions.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
CO 1 - CC - 1/12/2012
NEW CONTRACT AMOUNT
� r
Frank Hibbard, Mayor
$2,433,819.24 Wharton-Smith, Inc.
$455,222.52
By: Seal
Willia Logan, P oject Manager
$2,889,041.76
Date: ��0 9 �/ Z, :�, ` ,
�.
.. . F' ....�:
WITNESSES: : �`�' �' �
'l—�� � �;
U�U�— r_ � a `y �
C ���— �
CITY OF CLEARWATER, in Recommended By: City of Clearwater
PINELLAS COUNTY, FLORIDA
Camilo Soto, Assistant City Attorney
t���''LI--P�
Tara Kivett, Eng. Construction Manager
► '^ =
C��
Michael D. Quillen, P.E.
City Engineer
' Page 2 of 2
Change Order 1- MS WRF Rapid Sand Filter Rehabilitation
ITEM DESCRIPTION UNIT OUANTITY
Code:0315-96664-563800-535-000-0000 "B"
Additions•
7a Furnish and deliver Additional New EA 171
Underdrain Core Assemblies in accordance
with Section 01150, 3.O1B.- (ODP amount
paid directly to Siemens by the City)
7b Sales Tax Savings EA 171
7c Install, Test and warranty additional EA 171
underdrain core assemblies in accordance to
Section 01150, 3.O1B
UNIT COST
$1,850.00
$112.12
$700.00
Total Additions:
TOTAL COST
$316,350.00
$19,172.52
$119,700.00
$455,222.52
Total Net Additions to the Contract: $455,222.52