Loading...
MARSHALL STREET APCF GENERATOR UPGRADES, PHASE 2 - 07-0032-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINAL• A Administrative Change Order 1 & Final PROJECT: Marshall Street APCF Generator Upgrades, Phase 2 CONTRACTOR: Brandes Design-Build, Inc. 2151 NE Coachman Road Clearwater, Fl 33765 Date: June 14, 2011 PROJECT NUMBER: 07-0032-UT PO REFERENCE NO.: ST106095 COUNCIL AWARD: December 17, 2009 DATE OF CONTRACT: January 8, 2010 CODE:0376-96619-563800-535-000-0000A CODE:0315-96619-563800-535-000-0000B g: IRISVIlaNtgg ER ACCEPTS REVT*04,T 131- 1■1112 tfrizOlksAtitemS, atld'items &Le to vitbrseen conditions, decrease'OWnerIfiteaPtlit0001 4 P 9,1r#ct• STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT CO 1- Admin - NEW CONTRACT AMOUNT ATTEST: $1,104,220.82 ($289,981.06) $814,239.76 ACCEPTED B i.!t rZ Aq 9 c2,1 Brandes Di ui5Io. L cv •C;.)/ aus, President -it-Rov By: Key' Date: Rosemarie Call, CITY OF CLEARWATER, in PINE AS COUNTY, FLORIDA William B. Horne, II City Manager APPROVED AS TO FORM: ded y: City of Clearwater £4Lc Leslie K. Dougall-Sides, Assistant City Attorney bert Mane, PE, 23,1, Project Manage] Michael D. Quillen, PE, City Engineer a r. P- age 2 of 3 . " 'Administrative Change Order 1 & Final Re: Marshall Street APCF Generator Upgrades, Phase 2 ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST Sales Tax Savings Code B: 0315- 96619 - 563800 -533 -000 -0000 Decreases: 3a DEWATERING BUILDING 1 LS $8,377.61 ($8,377.61) GENERATOR (ODP SALES TAX 4a DEWATERING BUILDING STS 1 LS $914.00 ($914.00) (ODP SALES TAX SAVINGS) 7a BLOWER MCC BUILDING ATS 1 LS $2,642.00 ($2,642.00) (ODP SALES TAX SAVINGS) Code A: 0376-96619-563800-533-000-0000 Decreases: 8 PROGRAMMING SERVICES 1 LS $ 64.00 ($64.00) ALLOWANCE 9 10% CONTINGENCY 1 LS $ 100,382.71 ($100,382.71) American Recovery And Reinvestment Act Funding Administration: 10 ARRA FUNDING 1 LS $10.00 ($10.00) ADMINISTRATION 11 10% CONTINGENCY 1 LS $1.00 ($1.00) Total (decreases) Code A: ($100,457.71) Total (decreases) Code B: ($11,933.61) Additions: 12 TWO NEW BREAKERS FOR 1 LS $ 6,893.59 $6,893.59 INFLUENT PUMP STATION 13 RELOCATING EXISTING AC 1 LS $ 1,537.42 $1,537.42 COMPRESSOR UNIT 14 6 -INCH FIRE HYDRANT 1 LS $ 660.53 $660.53 EXTENSION 15 MARSHALL STREET WWTP 1 LS $ (3,926.62) ($3,926.62) TANK CLOSURE FEE 16 ADDITIONAL CONCRETE SLAB 1 LS $ 750.00 $750.00 FOR FUEL LINE 17 5 -FOOT - 2 SECTION HAND RAIL 1 LS $ 670.10 $670.10 FOR FUEL LINE PROTECTION 18 NEW PRIMARY ELECTRICAL 1 LS $ 5,621.63 $5,621.63 SERVICE WIRING FROM ATS 3A TO PE TRANSFORMER 19 RE- FEEDING DIGESTER PANEL I LS $ 6,597.11 $6,597.11 TO RELOCATED ATS -1 IN INFLUENT BUILDING Total additions: $18,803.76 Total net (decreases) /additions Code A: ($81,653.95) Total net (decreases) /additions to PO: ($93,587.56) Owner Direct Purchases (ODP): Decreases: 3 DEWATERING BUILDING 1 LS 138,793.50 ($138,793.50) GENERATOR (ODP) 4 DEWATERING BUILDING ATS 1 LS 14,400.00 ($14,400.00) (ODP) 7 BLOWER MCC BUILDING ATS 1 LS 43,200.00 ($43,200.00) (ODP) Total (decreases) ODP: Total net (decreases) /additions to the contract: ($196,393.50) ($289,981.06)