614 S MISSOURI AVENUE STORM PIPE REPAIR - 09-0048-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINALADMINISTRATIVE CHANGE ORDER #1 & Final PROJECT: 614 So. Missouri Ave. Storm Pipe Replacement CONTRACTOR: Clark Hunt Construction, Inc. 2165 Logan Street Clearwater, Florida 337606 Date: June 22, 2011 PROJECT NUMBER: 09- 0048 -EN PO REFERENCE NO.: ST 107233 COUNCIL AWARD: January 13., 2011 DATE OF CONTRACT: February 09, 2011 CODE A: 0315 - 96124 - 563700 -539- 000 -0000 CODE B: 0376 - 96665 - 563800- 535 -000 -0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT Additional work to complete the storm pipe replacement. And approve a time extension of twenty -two days to complete this work. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: ORIGINAL CONTRACT AMOUNT Adm. CO #1 & Final NEW CONTRACT AMOUNT ATTEST: Rosemarie Call, $147,096.15 ($10,000.06) $137,096.09 CITY OF CLEARWATER, in PINELLAS COUNTY, FL Camilo Soto, Assistant City Attorney Clark Hunt Construction, ,1;4 -. -. - Warren C. Hunt, Presitleii "- .r" Date: June 30, 2011 Witnesses: Janet Chandler Ed Hnosko Recommended By: City of Clearwater 744,eL, chi_e_A4 Tara L. Kivett, Engineering Construction Manager Michael D. Quillen, P.E. Engineering Director Page 2 of 2 Administrative Change Order #1 & Final Re: 614 So. Missouri Storm Pipe Replacement (09- 0048 -EN) CODE A: 0315 - 96124 - 563700 -539- 000 -0000 ITEM DESCRIPTION UNIT OTY UNIT COST TOTAL COST Decreases: 4 Sand Cement Bag Headwall LF 55 $354.19 ($19,480.45) 8 12 Foot of New Chain Link Fence and Two LS 1 $1,452.00 ($1,452.00) (2) 6 Foot Chain Link Gates 10 6" Thick Concrete Slab with 6 x 6 #10 Wire SY 39 $36.68 ($1,430.52) Fabric 12 Bahia Sod SF 936 $0.24 ($224.64) 14 Sidewalk SF 45 $3.23 ($145.35) 16 Contingency LS 1 $10,031.09 ($10,031.09) Total (Decreases): ($32,764.05) Increases: 3 54" RCP LF 3 $147.22 $441.66 6 Asphalt (TYPE S -1) SY 328.00 $ 18.10 $5,936.80 Total Increases: $6,378.46 Additions: 22 Upsize collar - conflict to 54" DIP LS 1 $2,256.20 $2,256.20 23 Wall work LS 1 $9,715.57 $9,715.57 24 Flowable fill CY 6 $101.45 $608.70 25 Install Rip Rap LS 1 $1,870.67 $1,870.67 26 Revised Fence LS 1 $2,857.96 $2,857.96 Total Additions: $17,309.10 Total Net (Decreases) /Increases /Additions to Code A ($9,076.49) CODE B: 0376 - 96665 - 563800 -535- 000 -0000 Decreases: 21 Contingency LS 1 $1,484.92 ($1,484.92) Total (Decreases): ($1,484.92) Additions: 27 Extend lateral LS 1 $561.35 $561.35 Total Additions: $561.35 Total Net (Decreases) /Additions to Code B ($923.57) Total Net (Decreases)/Increases/Additions to Contract ($10,000.06)