MORNINGSIDE RECLAIMED WATER SYSTEM - 05-0022-UT - ADMINISTRATIVE CHANGE ORDER #2 & FINALAdministrative Change Order 2 & Final
PROJECT: Morningside Reclaimed Water
CONTRACTOR: Volt Information Sciences, Inc
12700 56th Street North
Clearwater, Florida 33760
Date: April 22, 2011
PROJECT NUMBER: 05-0022-UT
PO REFERENCE NO.: ST 105536
COUNCIL AWARD: June 1$ 2009
DATE OF CONTRACT: July 7, 2009
CODE: 0315-96739-563800-533-000-0000 A
CODE: 0315-96739-563800-533-000-0000 B
CODE: 0376-96739-5(3800-533-000-0000 C
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT ^
This change order is to decrease unused items, increase and add items for additional work and extend the contract
by 4$ additonal calendar days.
3J•
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: ••• •..;_'JC? ',y,
??4 r ¦` r
ORIGINAL CONTRACT AMOUNT $1,557,039.28 Volt Information Sciences, Inc.
CO 1 - CC - 08/18/10 $234,165.96
CO 2 & Final - CM ,..? w
($163,870.83) `7'
NEW CONTRACT AMOUNT $1,627,334.41 ??.,JJ ?-,/ "•" +?r? `???
By: IVMI CJ ??•G l
Jill
Gary Beilke
Date:
f.? 7
ATTEST: Witnesses:
Rosemarie Ca _- SeCr??'y
Dat .10 / / q ~~ ? ,
A+rre
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
6 _ -i iam B. Horne, 11 City Manager
APP OVED AS TO FORM:
Leslie Dougall-Si es Assistant City Attorney
Recommended By: City of Clearwater
K lly J. 'Eden,
Project Maiager
Michael D. Quillen, P.E.
City Engineer
Page 2 of 3
Administrative Change Order 2 & Final
Re: Morningside Reclaimed Water (05-0022-UT)
ITEM DESCRIPTION
Code B:0315-96739-563800-533-000-0000
Decreases:
Transmission:
A4 Tree Barricades
A5 Root Pruning
A7 10" PVC RJ
A8 10" Compact ductile iron fittings
A9 8" C-900 PVC Pipe (OC)
All 8" PVC RJ
A12 8" Compact Ductile Iron Fittings
A13 8" Gate Valve and Box
A14 Combination Air Relief Valve
Assembly
A16 Unsuitable Material Excavation
A17 Select Backfill
A18 Tree Removal
A19 Progress Energy Allowance
A21 10% Contingency
Distribution:
B6 3-inch ASTMN D2241 RJ PVC Pipe
(HDD)
B7 4" C-900 PVC Pipe (OC)
B10 4" PVC RJ
B11, 4" Compact Ductile Iron Fittings
B12 4" Gate Valve and Box
B14 2" Long Side Service
B15 2" Short Side Service
B17 1" Short Side Service
B18 Concrete Driveway Replacement at
Directed by Owner
B19 Concrete Sidewalk Replacement at
Directed by Owner
B20 Concrete Curb Replacement as
Directed by Owner
B21a Asphaltic Concrete
B21b Base Material
B21c Sub-base Material
B22 Asphaltic Overlay as Directed by
Owner
B26 Tree Removal
B28 10 % Contingency
B29 6" C-900 PVC (OC)
B33 6" Compact Ductile Iron Fittings
Willadel:
B5 Root Pruning
B31 8" x 6" Tapping Tee and Valve
Increases:
Transmission:
A10 8" C-900 RJ PVC Pipe (HDD)
UNIT QUANTITY UNIT COST TOTAL COST
LS 1 $2,200.00 ($2,200.00)
LF 607 $7.58 ($4,601.06)
LF 22 $68.00 ($1,496.00)
EA 10 $300.00 ($3,000.00)
EA 584 $26.50 ($15,476.00)
EA 65 $64.00 ($4,160.00)
EA 13 $105.00 ($1,365.00)
EA 6 $1,285.00 ($7,710.00)
EA 7 $2,105.00 ($14,735.00)
CY 100 $8.00 ($800.00)
CY 100 $10.00 ($1,000.00)
EA 1 $2,410.00 ($2,410.00)
LS 1 $25,000.00 ($25,000.00)
LS 1 64,410.30 ($64,410.30)
LF 149 ($1,236.70)
$8.30
LF 236 $22.50 ($5,310.00)
EA 38 $38.00 ($1,444.00)
EA 61 $55.00 ($3,355.00)
EA 3 $855.00 ($2,565.00)
EA 8 $800.00 ($6,400.00)
EA 6 $710.00 ($4,260.00)
EA 10 $425.00 ($4,250.00)
SY 100 $58.50 ($5,850.00)
SY 61 $56.50 ($3,446.50)
T 100 $20.00 ($2,000.00)
TN 15 $68.00 ($1,020.00)
CY 25 $9.50 ($237.50)
CY 35 $9.50 ($332.50)
TN 15 $6.35 ($95.25)
EA 2 $500.00 ($1,000.00)
LS 1 $95,414.48 ($95,414.48)
LF 150 $28.50 ($4,275.00)
EA 9 $85.00 ($765.00)
LF 214 $7.50 ($1,605.00)
EA 1 $3,500.00 ($3,500.00)
Total (Decreases): ($296,725.29)
LF 814
$25.30
$20,594.20
Page 3 of 3
Administrative Change Order 2 & Final
Re: Morningside Reclaimed Water (05-002 2-UT)
ITEM DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST
Increases continued:
Distribution:
B8 4" C-900 PVC Pipe (HDD) LF 4444 $15.23 $67,682.12
B9 6" HDPE Casing (HDD) EA 348 $26.50 $9,222.00
B13 Permanent Blowoff Assembly EA 3 $1,259.00 $3,777.00
B 16 1" Long Side Svc EA 10 $625.00 $6,250.00
Willadel:
B30 6" C-900 PVC PVC (HD'D) LF 54 $26.50 $1,431.00
Clearwater Christian College:
B8 4" C-900 PVC Pipe (HDD) LF 921 $15.23 $14,026.83
B13 Permanent Blowoff Assembly EA 2 $1,259.00 $2,518.00
Total Increases: $125,501.15
Additions:
Transmission:
A24 Downtime Belcher 8" Drill shot EA 1 $3,578.31 $3,578.31
A25 17'X14" Collars for Air Release EA 9 $150.00 $1,350.00
Clearwater Christian College:
B36 Survey EA 1 $1,875.00 $1,875.00
B37 Video EA 1 $550.00 $550.00
Total Additions: $7,353.31