Loading...
MORNINGSIDE RECLAIMED WATER SYSTEM - 05-0022-UT - ADMINISTRATIVE CHANGE ORDER #2 & FINALAdministrative Change Order 2 & Final PROJECT: Morningside Reclaimed Water CONTRACTOR: Volt Information Sciences, Inc 12700 56th Street North Clearwater, Florida 33760 Date: April 22, 2011 PROJECT NUMBER: 05-0022-UT PO REFERENCE NO.: ST 105536 COUNCIL AWARD: June 1$ 2009 DATE OF CONTRACT: July 7, 2009 CODE: 0315-96739-563800-533-000-0000 A CODE: 0315-96739-563800-533-000-0000 B CODE: 0376-96739-5(3800-533-000-0000 C SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT ^ This change order is to decrease unused items, increase and add items for additional work and extend the contract by 4$ additonal calendar days. 3J• STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: ••• •..;_'JC? ',y, ??4 r ¦` r ORIGINAL CONTRACT AMOUNT $1,557,039.28 Volt Information Sciences, Inc. CO 1 - CC - 08/18/10 $234,165.96 CO 2 & Final - CM ,..? w ($163,870.83) `7' NEW CONTRACT AMOUNT $1,627,334.41 ??.,JJ ?-,/ "•" +?r? `??? By: IVMI CJ ??•G l Jill Gary Beilke Date: f.? 7 ATTEST: Witnesses: Rosemarie Ca _- SeCr??'y Dat .10 / / q ~~ ? , A+rre CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA 6 _ -i iam B. Horne, 11 City Manager APP OVED AS TO FORM: Leslie Dougall-Si es Assistant City Attorney Recommended By: City of Clearwater K lly J. 'Eden, Project Maiager Michael D. Quillen, P.E. City Engineer Page 2 of 3 Administrative Change Order 2 & Final Re: Morningside Reclaimed Water (05-0022-UT) ITEM DESCRIPTION Code B:0315-96739-563800-533-000-0000 Decreases: Transmission: A4 Tree Barricades A5 Root Pruning A7 10" PVC RJ A8 10" Compact ductile iron fittings A9 8" C-900 PVC Pipe (OC) All 8" PVC RJ A12 8" Compact Ductile Iron Fittings A13 8" Gate Valve and Box A14 Combination Air Relief Valve Assembly A16 Unsuitable Material Excavation A17 Select Backfill A18 Tree Removal A19 Progress Energy Allowance A21 10% Contingency Distribution: B6 3-inch ASTMN D2241 RJ PVC Pipe (HDD) B7 4" C-900 PVC Pipe (OC) B10 4" PVC RJ B11, 4" Compact Ductile Iron Fittings B12 4" Gate Valve and Box B14 2" Long Side Service B15 2" Short Side Service B17 1" Short Side Service B18 Concrete Driveway Replacement at Directed by Owner B19 Concrete Sidewalk Replacement at Directed by Owner B20 Concrete Curb Replacement as Directed by Owner B21a Asphaltic Concrete B21b Base Material B21c Sub-base Material B22 Asphaltic Overlay as Directed by Owner B26 Tree Removal B28 10 % Contingency B29 6" C-900 PVC (OC) B33 6" Compact Ductile Iron Fittings Willadel: B5 Root Pruning B31 8" x 6" Tapping Tee and Valve Increases: Transmission: A10 8" C-900 RJ PVC Pipe (HDD) UNIT QUANTITY UNIT COST TOTAL COST LS 1 $2,200.00 ($2,200.00) LF 607 $7.58 ($4,601.06) LF 22 $68.00 ($1,496.00) EA 10 $300.00 ($3,000.00) EA 584 $26.50 ($15,476.00) EA 65 $64.00 ($4,160.00) EA 13 $105.00 ($1,365.00) EA 6 $1,285.00 ($7,710.00) EA 7 $2,105.00 ($14,735.00) CY 100 $8.00 ($800.00) CY 100 $10.00 ($1,000.00) EA 1 $2,410.00 ($2,410.00) LS 1 $25,000.00 ($25,000.00) LS 1 64,410.30 ($64,410.30) LF 149 ($1,236.70) $8.30 LF 236 $22.50 ($5,310.00) EA 38 $38.00 ($1,444.00) EA 61 $55.00 ($3,355.00) EA 3 $855.00 ($2,565.00) EA 8 $800.00 ($6,400.00) EA 6 $710.00 ($4,260.00) EA 10 $425.00 ($4,250.00) SY 100 $58.50 ($5,850.00) SY 61 $56.50 ($3,446.50) T 100 $20.00 ($2,000.00) TN 15 $68.00 ($1,020.00) CY 25 $9.50 ($237.50) CY 35 $9.50 ($332.50) TN 15 $6.35 ($95.25) EA 2 $500.00 ($1,000.00) LS 1 $95,414.48 ($95,414.48) LF 150 $28.50 ($4,275.00) EA 9 $85.00 ($765.00) LF 214 $7.50 ($1,605.00) EA 1 $3,500.00 ($3,500.00) Total (Decreases): ($296,725.29) LF 814 $25.30 $20,594.20 Page 3 of 3 Administrative Change Order 2 & Final Re: Morningside Reclaimed Water (05-002 2-UT) ITEM DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST Increases continued: Distribution: B8 4" C-900 PVC Pipe (HDD) LF 4444 $15.23 $67,682.12 B9 6" HDPE Casing (HDD) EA 348 $26.50 $9,222.00 B13 Permanent Blowoff Assembly EA 3 $1,259.00 $3,777.00 B 16 1" Long Side Svc EA 10 $625.00 $6,250.00 Willadel: B30 6" C-900 PVC PVC (HD'D) LF 54 $26.50 $1,431.00 Clearwater Christian College: B8 4" C-900 PVC Pipe (HDD) LF 921 $15.23 $14,026.83 B13 Permanent Blowoff Assembly EA 2 $1,259.00 $2,518.00 Total Increases: $125,501.15 Additions: Transmission: A24 Downtime Belcher 8" Drill shot EA 1 $3,578.31 $3,578.31 A25 17'X14" Collars for Air Release EA 9 $150.00 $1,350.00 Clearwater Christian College: B36 Survey EA 1 $1,875.00 $1,875.00 B37 Video EA 1 $550.00 $550.00 Total Additions: $7,353.31 Total Net (Decreases)/Increaes/Additions to the Contract: ($163,870.83)