DE LEON STREET IMPROVEMENTS - 09-0055-EN - ADMINISTRATIVE CHANGE ORDER # 1 & FINAL1 s
ADMINISTRATIVE CHANGE ORDER 1 & Final
PROJECT: De Leon Street Improvements
DATE: 4/19/201
PROJECT NUMBER: 09-0055-EN
PO REFERENCE NO.: ST107220
CONTRACTOR:
Steve's Excavating & Paving Inc.
PO Box 303
COUNCIL AWARD:
DATE OF CONTRACT: 3 0 2011
Dunedin, F134698
Code:0315-96124-563700-539-000-0000 A
0181-99628-563700-554-000-0000 B
0315-92273-563700-541-000-0000 C
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
To adjust quantities decrease unused, increase for overruns & add necessary items to close the contract.
See attached sheets for quantities and additional items.
ORIGINAL CONTRACT AMOUNT $ 77,285.18 ACCEPTED BY:
CO# 1 & Final- Admin - CM
NEW CONTRACT AMOUNT
($4,722.98)
$ 72,562.20
tyf
ATTEST:
Rosemarie Call, City Clerk
qr?R
Date:
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B
Manager
AS TO
Camilo Soto
Assistant City Manager
Steve's ing, ?tLE _ -
t
By. r ,Sealy;,
Cathy Sarnago, President
Date:
Witnesses:
?i?/.(arid wi'?S tj i
Sf-•e" 13r-f3A4 IaJ
Recommended By:
City of Clearwater
Steve Doherty
Project Manager
Michael D. Quillen, P.E.
City Engineer
i
Page 2 continued:
RE: Adm. CO# 1 & Final - Deleon Street Improvements
ITEM DESCRIPTION QUANTITY UNIT UNIT COST
Stormwater Code A:0315-96124-563700-539-000-0000
Decreases
11 10% Contingency 1 LS $3,628.50
Increases:
10 Sod 1,725 SF $0.70
Addition:
18 Remove galvanized 2" gas main 270 LF $3.50
19 Install extra pipe bedding 9 TN $40.00
Total Additions Code A:
TOTAL COST
($3,628.50)
$1,207.50
$945.00
$360.00
$1,305.00
Total Net (Decreases)/Increases/Additions Code A: ($1,116.00)
East Gate wa New Sidewalks Code B: 0181-99628-563700-554-000-0000
Decreases:
12 Construct 4" concrete sidewalk 343 SF $3.15
($1,080.45)
13 Remove & Replace 6" Concrete 107 SF $3.80 ($406.60)
Sidewalk and or Driveways (3,000
PSI w/Fiber Mesh Reinforcing and
6 / 6 x 10 / 10 welded wire mesh)
16 LF $5.00
($80.00)
15 Root Pruning
16 Install tactile warning surface 24 SF $85.00 ($2,040.00)
(truncated domes)
Total (Decreases) Code B:
($3,607.05)
Additions:
19 Sod 738.1428571420 SF $ 0.70
$516.70
Total Net (Decreases)/Additions Code B: ($3,090.35
New Sidewalks Code C: 0315-922711-563700-541----
Decreases:
17 10% Contingency 1 LS $3,397.43
($3,397.43)
Additions:
21 Install Asphalt on Site 6 TN $185.00 $1,148.30
22 Sod 2,475 SF $ 0.70 $1,732.50
Total Additions Code C: $2,880.80
Total Net (Decreases)/Additions Code C: ($516.63)
Total Net (Decreases)/Increases/Additions to Contract: ($4,722.98)