2010 STREET RESURFACING PROJECT - 10-0022-EN - ADMINISTRATIVE CHANGE ORDER # 2ADMINISTRATIVE CHANGE ORDER #2 PROJECT: 2010 Street Resurfacing Project CONTRACTOR: R.E. Purcell Construction Co., Inc. 1550 Starkey Road Largo, Florida 33771 Date: March 22, 2011 PROJECT NUMBER: 10-0022-EN PO REFERENCE NO.: ST 107138 COUNCIL AWARD: November 04 2010 DATE OF CONTRACT: November 30 2010 CODE: 031.5-92273-563700-541-000-0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT Approve a time extension of 59 days to complete additional work added to this contract at the following locations: Restoration of nine (9) CSX Railroad Crossings; Countryside Blvd. & Northside Dr.; Cleveland St. /Drew Street to Coachman Park; Water Systems Facility @ 2775 SR 580; Major restoration of right-of.--way @ Yacht Club. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: ORIGINAL CONTRACT AMOUNT $1,482,700.23 R.E. Purcell Construction Co., Inc. Adm. CO #1 (CM Approved 01/31/11) $147,387.50 Adm. CO 42 $0.00 NEW CONTRACT AMOUNT $1,630,087.73 "r By: (SEAL) . , Je cell, Asphalt Division Manager. ATTEST: OF Zmr ad.u Rosemarie Call, City C Date: O Date: 9 P?ofl Witnesses: CITY OF CLEARWATER, in PINELLAS COUNTY, FL ; h Y1'lc.; nn;g William B. Horne, lI City Manager Recommended By: City of Clearwater 3 ATTES Donald D. Melone Project Engineer T- ? F Camilo Soto, Assistant City Attorney Michael D. Quillen, P.E. Engineering Director LL } °_ Clearwater r U Interoffice Correspondence Sheet To: William B. Horne, II, City Manager ?D From: Michael D. Quillen, PE, Engineering Director`( CC: Tina G. Wilson, Budget Director; Donald D. Melone, Engineering Specialist I/Project Engineer; Stephanie Sansom, Senior Accountant/Engineering/Stormwater; Alice Eckman, Construction Specialist Date: March 24, 2011 RE: Administrative Change Order No. 2 2010 Street Resurfacing Contract (10-0022-EN) RECOMMENDED ACTION: Administrative Change Order No. 2 to R.E. Purcell Construction Co., Inc. of Largo, Florida, for the "2010 Street Resurfacing Contract (10-0022-EN)" is needed to approve a time extension to complete additional work added to the contract. There is no change to the contract amount. BACKGROUND: Approve a time extension of 59 days to complete work added to this contract at the following locations: ¦ Restoration of Nine (9) CSX Railroad Crossings ¦ Countryside Blvd. & Northside Dr. ¦ Cleveland St. / Drew St. to Coachman Park ¦ Water Systems Facility @ 2775 SR 580 ¦ Major restoration of right-of-way (Yacht Club) OFFICE OF MANAGEMENT AND BUDGET DEPARTMENT REVIEW I recommend approval based on the administrative change order criteria: 1. Increases do not exceed 10% of the Council approved amount on a cumulative basis. 2. Change does not change the scope of the project. 3. Price increases do not require additional appropriation to the project. 4. Contract price decreases may be approved without limitation. 5. Completion date is not extended more than 60 days. T'na G. Wilson Date Adm. CO#2 Memo - 2010 Street Resurfacing 03-14-11