CLEARWATER BEACH BOAT RAMP - 06-0049-MA - RATIFY & CONFIRM CHANGE ORDER #2 & FINAL
RATIFY & CONFIRM CHANGE ORDER #2 & FINAL
PROJECT: Clearwater Beach Boat Ramp
Date: Februa 24 2011
PROJECT NUMBER: 06-0049-MA
PO REFERENCE NO.: ST 106588
COUNCIL AWARD: June 17, 2010
CONTRACTOR: Custom Built Marine Construction, Inc.
1321 SE Decker Avenue
Stewart, FL 34994
DATE OF CONTRACT: July 9, 2010
CODE: 0315-93408-563800-575-000-0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Additional work to maintain and repair the existing seawall during construction and extend contract 67 days.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
CO #1 - CM Approved 2/7/11
CO #2 - CC Approved 3/17/11
NEW CONTRACT AMOUNT
ACCEPTED BY:
$156,495.90 Custom Built Marine Construction, Inc.
$14,959.12 -
$19,615.35
$191,070.37
Y: (SEAL) ±
ve Carrigan Vice Preside
Dater// / / /
Mayor
CamiTo Soto, Assistant City Attorney
ATTEST: 4 a_ 1W'TNI
946.
0'zX Ifl<
Rosemarie Call, City V _low
Date: 4'1
NZATV
CITY OF CLEARWATER, in
LAS COUNTY, /FL
PIN _
/ DD/ 11 w w 6 /CL.R1.f w I
Witnesses:
IIo
I?
Q Recommended By: City of Clearwater
C
Tara L. Kivett, Project Manager
William B. Horne, H City Manager Michael D. Quillen, P.E. Engineering Director
Page 2 of 2
Ratify & Confirm Change Order #2 and Final
Re: Clearwater Reach Boat Ramp (06-0049-MA)
ITEM DESCRIP'T'ION QUANTITY UNIT UNIT COST
Decreases:
6 Place & Compact #57 - crushed 10.35 TN $135.00
concrete base and stabilize bedding
(truck measure)
1.4 Contingency 1.00 LS $14,226.90
Total (decreases):
Increases:
9 Pour-in-place 6" new concrete ramps, 0.4 CY $450.00
including 1/2: expansion joints,
thickened edges, and two concrete
closures
Additions:
19 South seawall tie-back, sidewalk and
cap
20 Railing
21 Seawall Maintenance
Total increases:
1 LS $16,179.50
TOTAL COST
($1,397.25)
($14,226.90)
($15,624.15)
$180.00
$180.00
$16,179.50
1 LS $1,380.00 $1,380.00
1 LS $17,500.00 $17,500.00
Total additions: $35,059.50
Total net (decreases)/increases/additions: $19,615.35