MORNINGSIDE NEIGHBORHOOD TRAFFIC CALMING - 07-0038-EN - RATIFY & CONFIRM CHANGE ORDER # 2Ratify & Confirm Change Order # 2
PROJECT: Morningside Traffic Calming
DATE: February 14, 2011
PROJECT NUMBER: 07-0038-EN
PO REFERENCE NO.: ST106342
CONTRACTOR:
R.A.M Excavating, Inc.
569 Hammock Drive
Palm Harbor, FL 34683
COUNCIL AWARD: 3/18/2010
DATE OF CONTRACT: 4/2/2010
CODE: 0315-92259-563700-541-000-0000 A
0315-%124-563700-539-000-0000 B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Due to unanticipated utility conflicts (mostly buried) - replacement of water main facilities at two mini roundabouts, discovery of
three different under-drain systems at Harn and Claiborne, replacement of 500 linear feet of water main at Harn and Stewart,
and addition of reclaimed water irrigation for landscaping - a time extension of 125 calendar days is necessary for the
_.?._...?.?_?_?-..-
construction contract.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL, CONTRACT AMOUNT
CO# 1- Admin - 12/22/2010
CO #2-Ratify & Confirm - CC - 3/17/2011
NEW CONTRACT AMOUNT
ACCEPTED BY:
R.A.M. Excavating, Inc.
$ 1,399,790.70
$ 95,128.54 By: i Seal
$0.00 Richard Slack
S 1,494,919.24
Frank Hibbard, Mayor
ATTEST:
Rosemarie Call,
rye
??\f/?
far,
r-
Ci f
Date:
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B.Ko ne, II City Manager
AS
Assistant City Attorney
Date: February 24, 2011
G
Witnesses:
i
Melinda Slack
Recommended By:
City of Clearwater
Paul Bertels,
Pro'ect Minager
Michael D. Quillen, P.E.
City Engineer