EAST AVENUE TRAIL CONNECTOR - FROM TURNER STREET TO DREW STREET - 09-0023-EN - RATIFY & CONFIRM CHANGE ORDER #4RECEIVED
JAN 1 8 2011
RATIFY & CONFIRM CHANGE ORDER #4
PROJECT: East Avenue Trail Connector - Turner St. to Drew St:
CONTRACTOR: APAC, Southeast, Inc.
4636 Scarborough Drive
Lutz, FL 33559
r1o
CODE: 315-92343-563700-541-000-0000 A
CODE: 315-92273-563700-541-000-0000 B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Restore the East Avenue corridor due to CSX rail and tie replacement work, replace handicap curb ramps on East Avenue to meet
current ADA standards, remove the southbound turn on Cleveland/East due to converting southbound East Avenue to a bicycle trail
,
and modify signage and extend contract by 342 calendar days due to CSX Railroad tie replacement.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
$289,029.25 APAC, Soothe c.
Change Order #1 - CM Approved 3/11/10
$420
00
.
? T f • ! v rt
Change Order #2 - CC Approved 5/20/10 $85
44 >
481 `• `?' '
w
,
.
Change Order #3 - CC Approved 8/18/10 $38
463
30
,
.
Change Order #4 - CC 2/3/11 $361
672.77 BY: '"
,
e-i
NEW CONTRACT AMOUNT
$775,066.76
?? .. ? -••
}
?d
a 4
,
P
,
?,•
. .. ,, r?
?
?`?? y
y ?
J v'77C?I'1 Cry
Date:
Frank
(-I I' ftfA "
Assistant City Attorney
ATTEST:
Rosemarie Call,
Date:
City Clerk
DATE: Janus 12 2011
PROJECT NUMBER: 09-0023-EN
PO REFERENCE NO.: ST 105759
COUNCIL AWARDED: Se tember 3 2009
DATE OF CONTRACT: September 4, 2009
Witnesses:
Recommended By: City of Clearwater
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
c•?-??...,,?- G?o??t??
Wi liam S. Horne, II City Manager
Tara Kivett, Project Manager
Michael D. Quillen, PE
City Engineer
Page 2 of 2
Ratify & Confirm Change Order #4
Re: East Avenue Trail Connector - Turner St. to Drew St.
Item Description 2Y Units Unit Price
C de :031 -92343-563700-541-000-0000
Increases.
29 Restore Drew Street Crossing 13.36 TN $ 180.00
32 Restore Laura to Park & Pierce Street 20.01 TN $ 215.00
Crossing
Additions:
37 Restore Turner Street Crossing and East
Avenue Corridore
38 Excavate and Grade East Avenue
Corridore
39 Restore Druid Street Crossing
40 Remove Debris at Druid St Crossing
41 Replace ADA Ramps
42 Remove Cleveland Street Turn Lane and
Widen Median
43 705-10-1, Object Marker, Type 1
44 711-11-111, 6" Solid Traffic Stripe (White)
45 711-11-123,12" Solid Traffic Stripe (White)
46 711-11-231, 4" (3/9) Skip Traffic Stripe
(Yellow)
47 Restore Golf Cart Crossings
48 Remove & Replace Type F Curb
49 Relocate Sign Post
50 Replace Stop Sign
51 Replace One-Way Sign
52 Replace All-Way Sign
53 Install 18"x24" One-Way Sign & Post
Contract Price
$2,404.80
$4,302.15
Total Increases: $6,706.95
2016.31 TN $ 105.55 $212,821.52
1.00 LS $ 38,862.00 $38,862.00
57.44 TN $ 215.00 $12,349.60
1.00 LS $ 11500.00 $1,500.00
1.00 LS $ 58,000.00 $58,000.00
1.00 LS $ 12,630.00 $12,630.00
2 EA $ 134.00 $268.00
0.4323 NM $ 4,028.00 $1,741.30
784 LF $ 2.25 $1,764.00
43 LF $ 0.80 $34.40
1 LS $ 9,700.00 $9,700.00
120 LF $ 36.00 $4,320.00
5 EA $ 80.00 $400.00
3 EA $ 45.00 $135.00
2 EA $ 35.00 $70.00
2 EA $ 10.00 $20.00
2 EA $ 175.00 $350.00
Total Additions: $354,965.82