BARRIER WALL INSTALLATION FOR S GULFIVEW BOULEVARD - CORONADO DRIVE INTERSECTION - 10-0001-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINAL4ft
ADMINISTRATIVE CHANGE ORDER #1 & FINAL Date: September 30, 2010
PROJECT: Barrier Wall Installation for So. Gulfview /
Coronado Dr. Intersection
CONTRACTOR: Castco Construction, Inc.
9001 126th Avenue No.
Largo, Florida 33773
PO REFERENCE NO.: ST 106511
PROJECT NUMBER: 10-0001-EN
DATE PO ISSUED: May 13, 2010
CODE: 0315-92558-563700-541-000-0000 A
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order is necessary to adjust quantities actually used in the field to close out contract.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT $56,300.40 Castco Construction, Inc. i 4
Adm. C0#1 & Final - ($806.90)
NEW CONTRA AM UNT $55,493.50
(('SEA)
Israel Castro, President
APPROV D AS TO FO `
Date: I - 09 - /C)
_
Date: it- /0 ~ /U
Camilo Soto,
ATTEST: „r'
n - C3
Rosemarie Call, City Clerk
'ArSk
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Home, 11 City Manager
Witnesses:
Recommended By: City of Clearwater
Michael D. Quillen, PE, Engineering Director
Construction Manager
AMM
Page 2 of 2
Administrative Change Order #1 & Final
Re: Barrier Wall Installation for So. Gulfview/ Coronado Intersection
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Code: 0315-92558-563700-541-000-0000 "A"
Decreases
102-14 Traffic Control Officer 100 MH $46.67 ($4,667.00)
475 10% Contingency
Additions:
500 Radius Wall in lieu of Straight
LS $5,118.21 $5,118.21
Total (Decreases): ($9,785.21)
LS $8,978.31
$8,978.31
Total Net (Decreases)/Additions: ($806.9
LL
}
Clearwater
Interoffice Correspondence Sheet
To: William B. Horne, II, City Manager
From: Michael D. Quillen, PE, City Enginee5l
CC: Tina G. Wilson, Budget Director; Stephanie Sansom, Senior Accountant/Engineering/
ESM; Alice Eckman, Construction Specialist
Date: November 10, 2010
RE: Administrative Change Order No. 1 & Final
Barrier Wall Installation for So. Gulfview ! Coronado Intersection (10-0001-EN)
RECOMMENDED ACTION: Approve Administrative Change Order No. 1 & Final to Castco
Construction, Inc. of Largo, Florida, for the "Barrier Wall Installation for So. Gulfview ! Coronado
Intersection (10-0001-EN)". This change order decreases the contract amount by ($806.90) for a
new contract total of $55,493.50.
BACKGROUND: This change order is needed to adjust quantities to those actually used in the field
and to close out this project.
OFFICE OF MANAGEMENT AND BUDGET DEPARTMENT REVIEW
I recommend approval based on the administrative change order criteria:
1. Increases do not exceed 10% of the Council approved amount on a cumulative basis.
2. Change does not change the scope of the project.
3. Price increases do not require additional appropriation to the project.
4. Contract price decreases may be approved without limitation.
5. Completion date is not extended more than 60 days.
kk la
Tina G. Wilson D to
Adm. C0#1 & Final Memo - Barrier Wall Installation 9-30-10