DEL ORO ELEVATED STORAGE TANK DEMOLITION - 09-0043-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALADMINISTRATIVE CHANGE ORDER 1 & Final
PROJECT: Del Oro Elevated Storage Tank Demolition
DATE: 712/2010
PROJECT NUMBER: 09-0043-UT
PO REFERENCE NO.: ST106381
CONTRACTOR: JVS Contracting, Inc.
1608 North 43rd Street
Tampa, FL 33605
DATE OF CONTRACT: 4/5/2010
CODE: 0376-96760-563800-533-000-0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This CO adjusts quantities to what was actual used.
STATEMENT OF CONTRACT AMOUNT - ? ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
CO# 1- Admire - CM
NEW CONTRACT AMOUNT
ATTEST:
Cynthia E. udeau,
Date: -? )
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, II City Manager
Leslie Dougall- $ 37,950.00
APP OVED AS TO FORM:
UZ i stant City Attorney
($2,300.00)
$ 35,650.00
OF THE
city
B " (SEA!,_
Date:
Witnesses:
Recommended By:
City of Clearwater
/; ?-6- N 1A
Michael D. Quillen, P.E.
City Engineer
Page 2 of 2 r
Admu4iArative CO 1 & Final
ITEM DESCRIPTION
Decreases:
3 Contingency
Increases
2 Grout 16" water main
(QUANTITY[JNII UNIT COST
1 LS 3,450.00
230 LF 5.00
TOTAL COST
($3,450.00)
$1,150.00
Total Net (Decreases)/Increases/Additions to Contract ($2,300.00)