WATER TREATMENT PLANTS 1 AND 3 WELLFIELD EXPANSION PHASE 1 - WELL INSTALLATION - PROJECT NO. 07-0037-UT - ADMINISTRATIVE CHANGE ORDER #1h 4 -11 ADMINISTRATIVE CHANGE ORDER 1
DATE: JUNE 29, 2010
PROJECT: WATER TREATMENT PLANTS 1 & 3 WELLFIELD EXPANSION PROJECT NUMBER: 07-0037-UT
PROJECT PHASE I - WELL INSTALLATION
CONTRACTOR:
SOUTHEAST DRILLING SERVICES, INC.
P.O. Box 2764
Lutz, Florida 33548
PO REFERENCE NO.: ST 105155
COUNCIL AWARD: JANUARY 15 2009
DATE OF CONTRACT: JUNE 15, 2009
CODE: 0376-96764563800-533-000-0000 A
0376-%763-563800-533-000-0000 B
0376-%764-563800-533-000-0000 C
0376-96764-563800-533-000-0000 D
0376-96763-563800-533-000-0000 E
0376-%763-563800-533-000-0000 F
0376-96764-563800-533-000-0000 G
0376-96763-563800-533-000-0000 H
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This Change Order is to delete Well 52 R and Well 69 Rehab, add new Well 69R, demolition and abandonment
of Well 69, upsizing pump and piping at Well 1-3, add 8" liner at Well 3-4, acidize Well 3-5, and add 59 days
to the contract. See attached sheets for quantities and additional items.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
PO ST105155
CO I - Admin - CM -
New PO Amount
PO ST105869
PO ST105868
New PO Amount
ORIGINAL CONTRACT AMOUNT
CO 1 - Admin - CM
NEW CONTRACT AMOUNT
PINEL S COUNTY, FLORIDA
William B. Horne, Il City Manager
APPROVED AS TO FORM:
+ r
Leslie Dougall-Sides Assistant City Attorney
$ 3,329,629.20
$ 145,263.33
$ 3,474,892.53
$ 152,499.20
$ 37,151.60
$ 189,650.80
$ 3,519,280.00
$ 145,263.33
$ 3,664,54333
By:
Job:
Datt
Witnesses:
Recommended By:
City of rwater
Lan-Anh Nguyen, PE Project Manager
Michael. D. Quillen, P.E.
City Engineer
CITY OF CLEARWATER, in
Page 2 of 3
RE: Administrative Change Order 1
ITEM DESCRIPTION
Code C:0376-96764-563800-533-000-0000
Decreases
52R: I Mobilization / Demobilization
52R: 2A Test / Production Well
52R: 2B Perform continuous split spoon, drill 24-inch
diameter boreholes, furnish and install 18-inch
diameter steel casing (0.25'), and furnish and
emplace cement grout around the perimeter of
the 18" casing
52R: 2C Drill 18-inch diameter borehole
52R: 2D Furnish and install 12-inch diameter Sch. 40
PVC casing, and furnish and emplace cement
grout to land surface around the perimeter of the
12" casing
52R: 2E Drill 12-inch diameter borehole
52R: 3 Site Work
52R: 4A Install Well Pump, Piping, Valve, Meter, and
Appurtenances
52R: 4B Vertical discharge Pipe
52R: 5 Production Well Pump and Motor (ODP)
52R: 6 Control Valve Actuator and Control Valve
(ODP)
52R: 7 Flow Meter (ODP)
Additions:
1-3 :8 Upsizing Pump and Piping
QUANTITY UNIT COST TOTAL COST
0.95 LS 9,500,00 (9,000.00)
1 LS 20,000,00 (20,000.00)
23 VF 200.00 (4,600.00)
15 VF 100.00 (1,50000)
39 VF 75.00 (2,925.00)
100 VF 30.00 (3.000,00)
1 LS 13,000.00 (1.3,000.00)
1 LS 93,000.00 (93,000,00)
46 VF 90.00 (4,140-00)
1 LS 9,000.00 (9,00(1,00)
1 LS 12,500.00 (12,500.00)
1 LS 3,000.00 (3.000-00)
Total (Decreases) Code C: ($175,665.00)
I LS 68,489.44 68,489.44
Total Net (Decreases)/Additions Code C: ($107,175.56)
Code E: 0376-96763-563800-533-000-0000
Decreases:
69:1 Mobilization /Demobilization 1 LS 5,000.00 (5,000.00)
69:13 Rehabilitate Well 1 LS 15,000.00 (15,000.00)
69:3 Site Work I LS 13,000.00 (13.000-00)
69:4A. Install Well Pump, Piping, Valve, .Meter, and 0.99 LS 30,000.00 (29,760.00)
Appurtenances
69: 4B Vertical discharge Pipe 113 VF 90.00 (10, 1 70.00)
69:5 Production Well Pump and Motor (ODP) 1 LS 9,000.00 (9,000.00)
69:6 Control Valve Actuator and Control Valve 0.2468744 I'S 12,500.00 (3,085.93)
(ODP)
69:7 Flow Meter (ODP) 023009 LS 3,000.00 (690-27)
Total (Decr eases) Code E: (85,706.20)
Additions:
3-4: 8 Installation of Liner 1 LS 26,126.61 26,126.61
3-5: 8 Acidizeation of Well 1 LS 19,130.00 19,130.00
69R: 1 Mobilization / Demobilization 1 LS 9,500.00 9,500.00
69R: 2A Test / Production Well 1 LS 20,000.00 20,000.00
69R: 2141 Continuous Split Spoons 96 VF 20.00 1,920.00
69R:2B2 Drill 24-inch diameter boreholes, furnish and 85 VF 180.00 15,300.00
install 18-inch diameter steel casing (0.25'), and
furnish and emplace cement grout around the
perimeter of the 18" casing
69R: 2C Drill 18-inch diameter borehole 20 VF 100.00 2,000.00
69R: 2D Furnish and install 12-inch diameter Sch. 40
PVC casing, and furnish and emplace cement
grout to land surface around the perimeter of the
12" casing
69R: 2E Drill 12-inch diameter borehole
69R. 3 Site Work
69R: 4A Install Well Pump, Piping, Valve, Meter, and
Appurtenances
69R: 4B Vertical discharge Pipe
Page 2 of 3
RE: Administrative Change Order 1
ITEM DESCRIPTION
69R: 5 Production Well Pump and Motor (ODP)
69R: 6 Control Valve Actuator and Control Valve
(ODP)
69R: 7 Flow Meter (ODP)
Abandonment of Well 69
69A: 1 Mobilization, SWFWMD Well Abandonment
Permit
69A: 2 Remove Existing Concrete Pad, Piping and
Appurtenances (Above and Below Ground),
Antenna, Fence, Electrical Panels and Conduits
69A: 3 Well Abandonment per SWFWMD
69A: 4 Site Restoration
69A: 5 Miscellaneous pipe fittings & valves
69A: 6 Well and Pump Panels
69A: 7 SED Services
69A:8 Electrical
105 VF 75.00 7,875.00
145 VF 30.00 4,350.00
1 LS 13,000.00 13,000.00
1 LS 113,774.75 113,774.75
100 VF 90.00 9,000.00
QUANTITY UNIT COST TOTAL COST
1 LS 9,000.00 9,000.00
1 LS 12,500.00 12,500.00
1 LS 3,000.00 3,000.00
1 LS 5,000.00 5,000.00
1 LS 5,402.70 5,402.70
1 LS 6,189.62 6,189.62
1 LS 13,000.00 13,000.00
1 LS 5,114.05 5,114.05
I LS 27,03145 27,033.45
1 LS 1,704.00 1,704.00
1 LS 8,224.91 8,224.91
Total Additions Code E: $338,145.09
Total Net (Decreases)/Additions Code E: $252,438.89
Total Net (Decreases)/Additions to PO: $145,263.33