PSP93-10 (2)RECEIVED
N 0 `J 0 5 1993
CITY OF CLEARWATER
Interdepartment Correspondence
CITY CLERK DEPT.
TO: Cyndie Goudeau, City Clerk
FROM: Louis R. Hilton, Development Planner II
SUBJECT: Certified Site Plan for St. Cecelia School (PSP 93-10)
COPIES: See List Below
DATE: October 20, 1993
The Development Review Committee at its meeting of September 23, 1993, approved the above described amendment
subject to the following conditions:
1. Signs and fencing/walls are subject to separate review and permitting processes.
2. The requisite building permits must be procured within one (1) year from the date of certification of the final site
plan and all requisites certificates of occupancy must be obtained within three (3) years of the date of certification
of the site plan.
3. Prior to certification the preferred site data table shall be located on the site plan, which shall include parking.
4. Prior to certification the dumpster(s) shall be fenced and landscaped according to code requirements.
5. Prior to certification, the Dumpster Requirement Form must be completed and returned to the City Sanitation
Department.
6. Prior to the issuance of a certificate of occupancy, the dumpster/compactor must be visually screened, and gates
must be provided with a minimum 12-foot clear opening to the front for access by Sanitation trucks.
7. Prior to certification, a copy of the SWFWMD permit application is to be provided to Engineering Site Plan
Review.
8. Prior to the issuance of a building permit, a copy of the approved SWFWMD permit is to be provided to
Engineering Site Plan Review.
9. Prior to certification, the final site plan must be signed and sealed by a Professional Engineer
registered in the State of Florida.
10. Handicap spaces must be adjusted to meet government standards.
11. Dimensions to be shown on the plan to demote measurements for aisles, parking stalls, entrances, etc.
12. Prior to the issuance of a building permit, applicant shall acquire a clearing and grubbing permit and a tree
removal permit (or a no tree verification form) from Environmental Management.
13. Prior to issuance of a building permit, applicant shall provide to Environmental Management and Engineering
an approved copy of all necessary local, state and federal permits that may be required.
As conditions #3,4,5,7,8,9,10, and 11 have been met, please certify the attached plans subject to conditions #1,2,6,12, and
13 listed above and distribute.
LRH/lrh
cc: Scott Shuford, Director of Central Permitting .
William C. Baker, Director of Public Works/Engineering
Chuck Warrington, Gas Department
Tom Miller, Environmental
Ream Wilson, Parks & Recreation Director
Don Meerians, Traffic Engineer
Victor Chodora, Building Official
Cyndie Goudeau, City Clerk
Steve Doherty, Zoning Section Supervisor V
Developer/Project Sponsor (3) - Mr. Timothy J. Bauer, P.E.
Tampa Bay Engineering, Inc.
18167 U.S. 19 North
Suite: 550
Clearwater, Florida 34624