LAKE BELLEVUE BRANCH 6A STORMWATER MANAGEMENT PROJECT - 03-0030-EN - ADMINISTRATIVE CHANGE ORDER #4
ADMINISTRATIVE CHANGE ORDER # 4
PROJECT: Lake Bellevue Branch 6A Stormwater Treatment
Project
Date: June 25, 2010
PROJECT NUMBER: 03-0030-EN
PO REFERENCE NO.: ST 105380
CONTRACTOR: Caladesi Construction Company
1390 Donegan Rd.
Largo, Florida 33771
COUNCIL AWARD: April_ 15, 2009
DATE OF CONTRACT:May 1, 2009
CODE: 0315-96152-563700-539-000-0000 A
CODE: 0315-92273-563700-541-000-0000 B
CODE: 0376-96742-563800-533-000-0000 C
CODE: 0376-96634-563800-535-000-0000 D
.
SCOPROFCHANGE:?-- THIS CH- GE.ORDER ACCEPTSREVISIONS TO THE. CONTRACT
This-chan'ge order is todecrease unu sedit nd increase items for additional
ems,a drainage and road work.
See.attached sheet for:detail. .... .
STATEMENT OF CONTRACT AMOUNT
ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT $1,662,525.45
Adm. CO # 1 - CM - 08/14/09 $14,375.00
Adm. CO # 2 - CM - 11/04/09 $5,260.00
Adm. CO # 3 - CM - 3/4/10 $40,040.00
Adm. CO # 4 - CM - ($12,201.64)
NEW CONTRACT AMOUNT $1,709,998.81
4hi ST:
ka E. to
Date: lu old
CITY OF CLEARWATER, in
PIN AS COUNTY, FLORIDA
William B. om f II
APPR ED AS T(
City ? Cler? 4 S ./,?F N
?yr
City Manager
Ca la esi Constru=Company
B) : (SEAL)
Donald J. Hi ichs, President'
Date: r - Perry M. Lopez
Construction Manager
r",
Camilo Soto Assistant City Attorney Michael D. Quillen, E.
City Engineer
-i Recommended By: City of Clearwater
Page 2 of 3
Administrative Change Order # 4
Re: Lake Bellevue Stormwater Management Project (03-0080-EN)
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Stormwater Code A: 0315-96152-539-000-0000
Decreases
I110 Remove existing Manhole and 2 EA $750.00 ($1,500.00)
fill
1111 Remove existing Inlet and fill 3 EA $750.00 ($2,250,00)
1116 Brick and Morter Plug 1 EA $1,200.00 ($1,200.00)
1214 Install Storm Sewer 15" RCP 36.5 LF $32.20 ($1,175.30)
1217 Install Storm Sewer 30" RCP 5.5 LF $64.19 ($353.02)
1218 Install Storm Sewer 29"x45" 12 LF $115.00 ($1,380.00)
ERCP
1219 Install Storm Sewer 36" RCP 30 LF $78.00 ('$2,340.00)
1220 Connect to Existing Storm 4 EA $350.00 ($1,400.00)
Structure or Pipe
Total (Decreases) Code A: ($11,598.32)
Increases
1210 Install FDOT Junction Box 1 EA $3,385.00 $3,385.00
(Type J-Alt B)
Total Net (Decreases)/] ncreases Code A: ($821.3.32)
Roads Code B: 0315-92273-541-000-0000
Decreases
2002 Install Type I Curb Index 101 127 LF $17.4486 ($2,215,97)
2008 Prepare Subgrade 759.31 SY $2.4919 ($1,892.12)
2011 Embankment Roadway 120.52 CY $14.51 _($1,748.75)
Total (Decreases) Code B: ($5,856.84)
Increases
2001 Standard Milling 521 SY $4.25 $2,214.25
2005 Surface Course - Asphalt Conc. 154.3 TONS $110.00 $16,973.00
Type III
2007 Install 8" Crushed Conc. Base 360.1 SY $10.00 $3,601.00
Total In creases Code B: $22,788.25
Total Net (Decreases)/Increases Code B. $16,931.41
Water Code C:0376-96742-563800-533-000-0000
Decreases
3001 Install Water Main 8" (PVC) 17.85 LF $14.00 ($249.90)
3002 Install Water Main 8" (DIP) 1.5 LF $34.00 ($51.00)
3005 Install Gate Valve (8") 2 EA $1,200.00 ($2,400.00)
3006 Tapping Sleeve and Valve (8"x8 I EA $3,400.00 ($3,400.00)
3008 Vertical Offset 12" Water 1 EA $1,800.00 ($1,800.00)
3011 Utilities Relocation (Vertical 1 EA $525.00 ($525.00)
and/or Horizontal Offsets)
3012 Install Gate Valve (12") 1 EA $1,700.00 ($1,700.00)
3013 Utility Pipe to be Removed </= 333 LF $6.10 ($2,031.30)
10" Dia.
Total (Decreases) Code C: _ ($12,157.20)
Page 3 of 3
Administrative Change Order # 4
Re: Lake Bellevue Stormwater Management Project (03-0080-EN)
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Sewer Code D: 0376-96634-563800-535-000-0000
Decreases
3101 Remove and Replace Sanitary - 66.5 LF $44.85 ($2,982,53)
8"
3102 Remove and Replace Sanitary - 20 LF $70.00 ('$1,400,00)
12"
3103 Remove and Replace Sanitary 3 EA $1,060.00 ($3.180.00)
Sewer Laterals (Contingency)
3104 Adjust Manholes 2 EA $600.00 ($1,200.00)
Total (Decreases) Code D: ($8,762.53
Total Net (Decreases)/Increases to Contract: ($12,201.64)
Total Net (Decreases)/Increases Stormwater Code A: 0315-96152-563700-539-000-001 ($8,213.32)
Total Net (Decreases)/Increases Roads Code B: 0315-92273-563700-541-000-0000 $16,931.41
Total Net (Decreases)/Increases Water Code C: 0376-96742-563800-533-000-0000 ($12,157.20)
Total Net (Decreases)/Increases Sewer Code D: 0376-96634-563800-535-000-0000 ($8,762.53)
($12,201.64)