2009 SIDEWALK PROJECT - 09-0039-EN - CHANGE ORDER #1CHANGE ORDER # 1
PROJECT: 2009 Sidewalk Project
Date: March 15, 2010
PROJECT NUMBER: 09-0039-EN
PO REFERENCE NO.: ST 106115
COUNCIL AWARD: 12/17/2009
CONTRACTOR: Kilgore Construction, LLC
11697 Walsingham Rd
Largo, Fl 33778
CODE: 0181-99628-590200-554-000-0000 A
CODE: 0315-92273-563700-541-000-0000 B
CODE: 0315-92339-563700-541-000-0000 C
SCOPE <OF.CHANGE: THIS CHANGE ORDER. ACCEPTS REVISIONS TO THE CONTRACT
CO.,#.1 is. to :provide A:DA compliance and add sidewalks in the East Gateway District where many streets lack sidewalks while
B1ock..Grant funding is available See below for detail.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
Council CO #1 -CC - 4/15/2010
NEW CONTRACT AMOUNT
$293,503.93
$119,715.75
$413,219.6$ (?
By. -? SEAL)..
61
Harold Kilgore, President mv"4 - iyiiy?•w:
Date: `ally "/d
ATTEST:
Cyn" E. Goudeau,
Date: v? Q, 0. . 2,01 D
CITY OF CLEARWATER, in
PINELLAkS COUNTY, FLORIDA
City Cler
OLA
William
AS
City Manager
Camilo Soto Assistant City Attorney
Witnesses:
Recommended By: City of Clearwater
P-tAA,u 7 XUn_t,, ,,-
Perry M.?pez U
Construe n Mana er
Michael D. Quillen, E.
City Engineer
Page 2 of 2
Change Order # 1
ITEM
DESCRIPTION QUANTITY UNIT UNIT COST
Increase New Sidewalks Code A: 0181-99628-590200-554-000-0000
1 Construct 4" concrete sidewalk 22,332 SF $2.75
(3,000 PSI w. fiber Mesh
Reinforcing)
2 Construct 6" concrete sidewalk 6,400 SF $3.55
(3,000 PSI w/Fiber Mesh
Reinforcing and 6/6 x 10/10
welded wire mesh)
3 Root Pruning 700 LF $11.00
Install tactile warning surface 325 SF $20.00
(trucated domes)
7 10% CONTINGENCY 1 LS $9,833.30
Total Increases Code A:
Increases Sidewalk R&R Code B: 0315-92273-563700-541-000-0000
11 Install tactile warning surface 275 SF $20.00
(truncated domes)
16 10% Contingency I LS $550.00
TOTAL COST
$61,413.00
$22,720.00
$7,700.00
$6,500.00
$9,833.30
$108,166.30
$5,500.00
$550.00
Total Increases Code B: $6,050.00
Total Increases: $114,216.30
Addition New Sidewalk Code C: 0315-92339-563700-541-000-0000
17 Construct 4" concrete sidewalk 1,818 SF $2.75 $4,999.50
(3,000 PSI w. fiber Mesh
Reinforcing)
18 10% Contingency 1 LS $499.95 $499.95
Total Additions Code C: $5,499.45
Total Increases $119,715.75