SKYCREST NEIGHBORHOOD TRAFFIC CALMING PROJECT - 03-0097-EN - ADMINISTRATIVE CHANGE ORDER # 2ADMINISTRATIVE CHANGE ORDER #2 & Final
PROJECT: Skycrest Neighborhood Traffic Calming Project (03-0097-EN)
Date: January 13, 2010
PROJECT NUMBER: 03-0097-EN
PO REFERENCE NO.: ST 104668
COUNCIL AWARD: August 21, 2008
CONTRACTOR: Semper Fi Services, LLC
1611 12th Street East, Unit B
Palmetto, FL 34221
DATE OF CONTRACT: August 26, 2008
CODE: 0315-92259-563700-541-000-0000-A
CODE: 0315-93286-563500-572-000-0000-B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
See attached sheet for additional items.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Adm. CO #1 - CM -
Adm. CO #2 - CM -
NEW CONTRACT AMOUNT
2,373,742.24
182,457.65
124,399.91
2,431,799.98
ACCEPTED BY:
i
By (SEAL)
Date: ?' IUD
Wit esses:
ft\k?J S 2010
By: City of
Perry M.
Michael D. Quillen, P.E.
City Engineer
CITY OF CLEARWATER, in
PINE AS COUNTY, FLORIDA
i am B. Horne, II City Manager
it
Page 2 of 2
Administrative Change Order #2
Re: Skycrest Neighborhood Traffic Calming Project
ITEM
QUANTITY UNIT UNIT COST TOTAL COST
Decreases Traffic Calmine Code A: 0315-92259-563700-541-000-0000
2 Traffic Control 0.005 LS 67,521.00 ($337.58)
3 Clearing & Grubbing, Erosion Control ar 0.005 LS 83,254.00 ($416.27)
18 8" crushed concrete base 1,377 SY 15.98 ($22,002.38)
22 Concrete sidewalk, 4" 175 SF 3.90 ($683.67)
23 Concrete sidewalk, 6" 171.3 SF 4.40 ($753.72)
26 Straight curb 150.6 LF 15.97 ($2,405.08)
31 Armor-Tile Truncated Dome 18.0 EA 365.00 ($6,570.00)
47 Adjust water valve box I EA 380.00 ($380.00)
56 6" Valve I EA 950.00 ($950.00)
58 6" DIP 4 LF 200.00 ($800.00)
64 Skip Traffic Stripe, (18"-18" Skip), Then 203 LF 3.35 ($680.05)
66 Solid Traffic Stripe, Thermoplastic (Whir 33.445 LF 2.27 ($75.92)
74 Yellow Flexible Delineator 13 EA 51.68 ($671.84)
75 Opti-Curb Reflective Pavement Marking 42 EA 40.36 ($1,695.12)
77 Sign Single Post (Fumish) 4 AS 64.80 ($259.20)
78 Sign Single Post (Install) 4 AS 129.60 ($518.40)
106 Irrigation & electrical sleeves (SCH 80 - 1,508 LF 5.25 ($7,917.00)
110 Contingency 1 LS 214,337.03 ($214,337.03)
113 Amour Tile Mats 18 EA 200.00 $3,600.00)
Total (Decreases) Code A: ($265,053.26)
Increases Traffic Calming Code A: 0315-92259-563700-541-000-0000
5 Concrete curb removal 664.0 LF 2.00 $1,328.00
21 Concrete brick pavers 43 SF 8.16 $353.57
24 Concrete sidewalk ramp 1,224 SF 4.40 $5,385.60
30 Sod 6,600 SF 0.31 $2,046.00
61 Retro-Reflective Pavement Markers 104 EA 8.10 $842.40
62 Skip Traffic Stripe, (2'-4' Skip), Thermox 14 LF 2.92 $40.88
63 Skip Traffic Stripe, (18"-18" Skip), Then 23 L.F 2.92 $67.16
65 Solid Traffic Stripe, Thermoplastic (Whit 92 LF 0.91 $83.72
66 Solid Traffic Stripe, Thermoplastic (Whit 282 LF 2.27 $640.14
68 Solid Traffic Stripe, Thermoplastic (Yell- 7,267 LF 0.91 $6,612.97
69 Solid Traffic Stripe, Thermoplastic (Yells 378 LF 192 $1,103.76
70 Patterned Textured Pavement (Asphalt) 4,183 SF 11.19 $46,807.77
71 Inlaid'rhermoplastic Pavemcnt Marking 114.2 SF 13.35 $1,524.57
73 Yellow Reflective Nose Paint 100 SF 2.70 $270.00
79 Remove Existing Pavement Marking 1,714.9 SF 16.48 $28,261.55
86 Arachis Glabrata'Ecoturf "Perennial Pea 4 EA 5.91 $23.64
92 Nandina Domestica'Harbor Dwarf "Dwf 33 EA 8.60 $283.80
93 Plumbago Auriculata "Plumbago" 8 EA 6.30 $50.40
107 Water meter assembly 2 EA 168.66 $337.32
111 Torpedo Bore under Driveways 95 LF 13.65 $1,296.75
Total Increases Code A. $97,360.00
Additions Traffic Calmin Code A: 0315-92259-563700-541-000-0000
129 Irrigation Revisions @ S Lake Dr 1 EA 1,168.00 $1,168.00
130 Demo & Replace Splitter Islands @ Aur( 1 EA 29,154.08 $29,154.08
131 Demo & Replace Bulb Out ! S Nimbus 1 EA 13,365.83 $13,365.83
132 Thermo Directional Arrows 16 EA 86.40 $1,382.40
Total Additions Code A: $45,070.31
Net Total (Decreases)/Increases/Additions Code A: ($122,622.95)
Decreases Parks Code B: 0315-93286-563500-572-00041000
1001 Pavement removal 95 SY 18.00 ($1,711.44)
1010 Sign Single Post 1 EA 64.44 ($64.44)
W
11 - loll Contingency
Increases Parks Code B:0315-93286-563500-572-000-0000
1002 12" Type .B stabilization
1003 8" crushed concrete base
1005 Concrete sidewalk, 4"
1006 Curb & gutter, Type 1
1 LS 1,457.72 - - ($1,457.72)
Total (Decreases) Code B: ($3,233.60)
19.2 SY $8.00 $153.60
66.2 SY $16.20 $1,072.44
22 SF $3.55 $78.10
10 LF $15.25 $152.50
Total Increases to Code B: $1,456.64
Total Net (Decreases)/Increases Code B: ($1,776.96)
Total Net (Decreases)/Increases/Additions to Contract: ($124,399.91)