SOUTH GULFVIEW BLVD RECONSTRUCTION - 07-0060-EN - ADMINISTRATIVE CHANGE ORDER # 2ADMINISTRATIVE CHANGE ORDER # 2
PROJECT: So. Gulfview Blvd. Reconstruction Project
CONTRACTOR: R.E. Purcell Construction Co., Inc.
1550 Starkey Road
Largo, Florida 33771
Date: September 18, 2009
PROJECT NUMBER: 07-0060-EN
PO REFERENCE NO.: ST 105546
COUNCIL AWARD: June 18, 2009
DATE OF CONTRACT: July 17, 2009 _
CODE-0315-92273-563700-541-000-0000 A
CODE: 0315-96170-563700-539-000-0000 B
CODE: 0376-96752-563800-533-000-0000 C
CODE: 0376-96665.563800-535-000-0000 D
CODE: 0315-96739-563800-533-000-0000 E
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
See attached sheet for additional i;tcros.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $1,109,657.62
Adm. CO # 1 - CM - 09/11/09 $4,623.76
Adm. CO # 2 - CM - $14,924.30
NEW CONTRACT AMOUNT $1,129,205.68
ATTEST:
Clthia E. Goudeau, Cho C%r
Date: I O Lo Zoo
CITY OF CLEARWATER, in ?l
PINELLAS COUNTY, FLORID
_.dl • w.,0
William B. Horne, II City Manager
ACCEPTED BY:
R.E. Purcell Co ruction Company, Inc.
By: (SEAL)
Scott Williams, Vice President
Date:
Witnesses:
';54Z4 ?&
41,
City of Clearwater
Gary W. Johnson, CGC
Public Services Director
Michael D. Quillen, P.E.
City Engineer
Page 2 of 2
Administrative Change Order # 2
Re: So. Gulfview Blvd. Reconstruction Project (07-0060-EN)
ITEM DESCRIPTION QUANTITY
CODE A - 0315-92273-563700-541-000-0000
Additional Items
2023 4" PVC Conduit (Traffic) Provide 1590
labor and equipment for the
installation of 4" PVC Conduit and
pullboxes; City of Clearwater to
provide all necessary materials
(conduit, sweeps, and pullboxes).
2024 2" PVC Conduit (Bright House) 175
Provide labor, equipment and
materials for the installation of 2"
PVC Schedule 40 Conduit
2025 3 - 2" PVC Conduit (Bright 180
House) Provide labor, equipment,
and materials for the installation of
3 Way 2" PVC Schedule 40
Conduit
UNIT UNIT COST TOTAL COST
LF $7.97 $ 12,672.30
LF $7.16 $_ .. _ 1,253.00
LF $5.55 $ 999.00
Total Additions to Contract $14,924.30