RESERVOIR NO. 2 - TEST PRODUCTION AND MONITOR WELL PROJECT - 06-0055-UT - ADMINISTRATIVE CHANGER ORDER # 2 & FINAL ADMINISTRATIVE CHANGE ORDER # 2 & FINAL PROJECT: Reservoir No. 2 - Test Production & Monitoring Well Project CONTRACTOR: Thompson Well & Pump, Inc. 700A West New York Ave. DeLand, FI 32720 August 27, 2009 PROJECT NUMBER: 06-0055-IJT PO REFERENCE NO.: ST 104808 DATE OF CONTRACT: September 18, 2008 CODE: 0376-96767-563800-533-000-0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE, CONTRACT To decrease contract by unused items and increase contract by overrun items - see attached sheet for details. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: ORIGINAL CONTRACT AMOUNT 5790,526.31 Thompson Well & Pump, Inc. Administrative Change Order # 1 (dated 4/28/09) $68,420.50 Administrative Change Order # 2 ($71,285.28) NEW CONTRACT AMOUNT $787,661.53 By: (SEAL) r. Jerry Thompson, President Date: 9J-z1 ATTEST: Cyntl E. Goudeau, City Clerk ?+ t 4 Date: VV CSC( ZC" pFt?E11l1 ?0? CIT F CLEARWAT.ER, in P E ,L COUNT ', FLQ1tIDA >M ??? William B. Horne, II City Manager C9?AKn%M 11 Witnesses: Zavj_'?P 1-I&x4A-) City of Clearwater Maue, P.E. MaWger Michael D. Quillen, City Engineer Page 1 of 3 Page 2 of 3 Administrative Change Order 2 and Final Reservoir No. 2 - Test Production & Monitoring Well Project Decreases Code 0376-96767-563800-533-000-0000: ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST 5, MWb - Production Zone B Monitor Wells McMullen Tennis Complex MWb-I 1 Furnish and emplace cement grout from 8 FT' $45.97 ($367.76) -625 to -500 feet bls MWb-12 Ream pilot borehole to 12-in diameter 27 FT $25.04 ($676.08) from -60 ft to -425 ft bls using reverse air method MWb-13 Furnish and install 6-inch ID 15 FT $11.67 ($175.05) (minimum) Certa-L&I-m PVC from land surface to -425 feet bls MWb-15 Furnish and emplace cement grout from 33 FT3 $27.86 ($919.38) -425 feet bls to land surface MWb-16 Drill out cement plug and clean out 2 FT $22.99 ($45.98) borehole from -425 feet bls to ?=500 feet bls using reverse air method Sub-total (decreases) 5. MWb-Production Zone B Monitor Wells McMullen Tennis Complex (52,184.25) Ed Wright Park MWb-16 Drill out cement plug and clean out 40 FT $22.99 ($919.60) borehole from -425 feet bls to -500 feet bls using reverse air method Sub-total decreases 5. MWb - Production Zone B Monitor Wells Ed Wright Park ($919.60) Total (decreases) 5. MWb - Production Zone B Monitor Wells - ?? S3,1? 03.85) 9. Production Zone A Production Wells McMullen Tennis Complex PW-12 Daily rate for continuation of aquifer 1 DAY $1,609.20 ($1,609.20) pump test beyond initial 7-day period not to exceed 14-days. PW-17 Furnish and emplace cement grout from 14 FT3 $56.70 ($793.$0) 175' bls to land surface Sub-total (decreases) 9. Producrion Zone A Production WellsMcMullen Tennis Complex ($2,403.00) Ed Wright Park PW-10 Conduct 6-hour step-drawdown test at 3 HOUR $136.02 ($408.06) rates of 100, 200, and 300 gpm PW-12 Daily rate for continuation of aquifer 1 DAY $1,609.20 ($1760920) pump test beyond initial 7-day period not to exceed 14-days. Sub-total (decreases) 9. Production Zone A Production Wells Ed Wright Park ($2,017.26) Total (decreases) 9. Production Zone A Production Wells (54,420.26) Owners 10% Contingency 1 LS $71,838.76 ($71,838.76) Total (decreases) to the contract (579,362.87) Increases Code 0376-96767-563800-533-000-0000: 5. MWb- Production Zone B Monitor Wells McMullen Tennis Complex MWb-9 Furnish and emplace cement grout from 21 FT3 $17433 $3,660.93 bottom to -625 feet bis Sub-total increases 5. MWb-Production Zone B Monitor Wells McMullen Tennis Complex $3,660.93 Total increases 5. MWb- Production Zone B Monitor Wells $3,660.93 9. Production Zone A Production Wells McMullen Tennis Complex PW-6 Drill using reverse-air method nominal 6 FT .$34.00 $204.00 18-inch diameter borehole to 200 feet bls using reverse air method PW-7 Develop open borehole between X80 feet I 14OUR $59.77 $59.77 bls and -200 feet bls with double tube air lift Page 2 of 3 Sub-total increases 9. Producrion Zone A Production WellsMcMullen Tennis Complex $263.77 Page 3 of 3 Administrative Change Order 2 and Final Reservoir No. 2 - Test Production & Monitoring Well Project Increases Code 0376-96767-5_63800-533-000-0000 (continued) ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST Ed Wright Park PW-7 Develop open borehole between ±80 feet 14 HOUR $59.77 $836.78 bls and ±200 feet bls with double tube air lift PW-8 Conduct downhole geophysical surveys for the following parameters between f80 feet bls and 1200 feet bls: a) Static Conditions: temperature, caliper, gamma, short and long normal resistivity, fluid conductivity, and fluid velocity b) Pumping Conditions: temperature, 0.42439 EACH $4,712.64 $2,000.00 fluid conductivity, and fluid velocity PW-9 Furnish and install 300 gpm (minimum.) 0.29702 EACH $4,431.03 $1,316.11 test pump and discharge line to required drainage feature Sub-total increases 9. Production Zone A Production Wells Ed Wright Park $4,152.89 Total Increases 9. Production Zone A Production Wells $4,416.66 Total Increases $8,077.59 Total net (decreases)/increases to the contract ($71,285,28) Page 3 of 3