PUMP STATION 19 REPLACEMENT - 06-0010-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALADMINISTRATIVE CHANGE ORDER # 1 & Final
PROJECT: Pump Station # 19 Replacement
Date: July 7, 2009
PROJECT NUMBER: 06-0010-UT
PO REFERENCE NO.: ST 104663
CONTRACTOR: Clark Hunt Construction, Inc.
2165 Logan Street
Clearwater, Florida 33765
DATE OF CONTRACT: Sept. 18,2008
CODE: 0376-96686-563800-535-000-0000 A
0315-96686-563800-535-000-0000 B
0315-96124-563700-539-000-0000 C
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This Change Order decreases and adds new items. It results in an overall decrease to the Contract Amount.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT $630,165.25 Clark Hunt Construction, InF:'
Adm. CO # 1& Final ($42,518.00) °°yJ µ w
NEW CONTRACT AMOUNT $587,647.25 =+ -
By: SEA°
W
Warren C. Hunt, Preside
Date: ????d g
W'tnesses:
?.. Janet Chandler
ATTEST: 1
Vol
C ta E. Goudeau, City
Date: I, (I. IQ.
Zda9
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
Ed Hnosko
Reco end : City of Clearwater
ti
Gary A. Johnson, CGC
Public Services Director
9
William B. Horne, H City Manager
Michael D. Quillen, P.E.
City Engineer
Page 2 of 2
Administrative Change Order # 1 & Final
Re: Pump Station #19 Relocation
ITEM DESCRIPTION QUANTITY UNIT UNIT COST
Decreases for Code A 0315-96686-563800-535.000-0000
5 10" DIP Force Main 4 LF $205.00
6 10" DR 18 Gravity Sewer Pipe 1 LF $101.00
7 18" DR 18 Gravity Sewer Pipe 4 LF $125.00
11 DIP Fittings and Restraints 0.25 Ton $6,465.00
12 Unsuitable Material Removal 90 CY $23.00
13 Additional Select Fill 40 CY $26.00
14 Miscellaneous Concrete 50 CY $277.20
15 10% Contingency 1 LS $57,287.75
Total (Decreases) to Code A
TOTAL COST
($820.00)
($101.00)
($500.00)
($1,616.25)
($2,070.00)
($1,040.00)
($13,860.00)
($57,287.75)
($77,295.00)
Additions for Code A 0315-96686-563800-535-00040000
16 Adjust New Force main Alignment 1
17 Bollards 3
18 45 Degree Bends 1
19 6" 90 Degree Bends 1
20 Electrical Concrete Panel 1
21 Survey 1
22 By-Pass Port Modifications 1
23 Stainless Steel 90 Degree Bends 2
24 Bypass Pumping 1
LS $1,683.00 $1,683.00
EA $450.00 $1,350.00
LS $1,155.00 $1,155.00
LS $770.00 $770.00
LS $1,014.00 $1,014.00
LS $550.00 $550.00
LS $5,545.00 $5,545.00
EA $440.00 $880.00
LS $19,012.00 $19,012.00
Total Additions to Code A $31,959.00
Total net (decreases)/additions Code A ($45,336.00)
Additions for Code C 0315-96124-563700-539-000-0000
24 Curb & Gutter removal & replacem 1 LS $2,818.00 $2,818.00
Total Additions to Code C $2,818.00
Total net (decreases)/additions to Contract ($42,518.00)