ADMINISTRATIVE CHANGE ORDER #1 - US 19 WATER MAIN TIE-INS l' ADMINISTRATIVE CHANGE ORDER #1 PROJECT: US Hwy. 19 Water Main Tie-Ins as per JP A Agreement CONTRACTOR: Harvey-Taddeo, Inc. Attn: Mr. Richard Taddeo 305A Scarlet Blvd. Oldsmar, Florida 34677 DATE: October 11, 2004 PROJECT NUMBER: PO REFERENCE NO.: 99-0096-UT ST 100043 DATE OF PURCHASE ORDER 07/27/04 CODE: 315-96742-563800-533-000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT See attached sheet fQr~;additionalitefu.s'. STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT $45,000.00 ADM. CHANGE ORDER #1 $14.196.87 NEW CONTRACT AMOUNT $59,196.87 ~.., ATTES : . . . 'C ':., :J:t- . 00 "- Cynthia E. oudeau,.' City Clerk Date: IOllls,locr CITY OF CLEARWATER, in ~;;s COUNTY, FLORIDA ~A~~'dif: William B. Horne, II City Manager ACCEPTED BY: Harvey - Taddeo, Inc. Date: / {J-J! {l...j... I Witnesses: ~~~;~ f~~ ~ I t c (C. Ed< tn,QY) Gary, . Johnson, CGC Publi ervices Director ~~ Michael D. Quillen, P.E. City Engineer ~ .' , " Page 2 continued: Adm. CO#1 - US Hwy. 19 Water Main Tie-Ins as per JPA Agreement Summary of additional work reauested. Description Unit ~ Unit Price Total Item #1 - Pickup three (3) new 8" gate valves and install as requested. (No charge). LS $0.00 $0.00 Item #2 - Friday, August 20, 2004 - The City of Clearwater Water Division was unable to schedule this task, so Harvey-Taddeo, Inc. Excavated, and exposed the existing fire and domestic water services at Super 8 Motel. The FOOT drawings were incorrect. LS 1 $1,794.46 $1,794.46 Item #3 - Friday, August 27,2004 - Excavated, exposed and determine the 8" water service at Sta. 328+35 which was not installed per FOOT contract drawings. We were unable to make the connection, so we backfilled excavation. LS 1 $1,794.46 $1,794.46 Item #4 - Unable to proceed with waterline connections north of Sunset Point Road due to (Letter of Clearance) approximately 15 calendar days. (No charge). LS $0.00 $0.00 Item #5 - Thursday, September 16, 2004 - After completion of connection at Sta. 338+62 (Tropical West Breeze), were directed by City Water Department to disconnect the new connection and reconnect the existing. LS 1 $376.97 $376.97 Item #6 - Wednesday, September 22,2004- Had to re-excavate and again connect 8" to new water service at Sta. 338+62 (Tropical West Breeze) and start to backfill. LS 1 $1,794.46 $1,794.46 Item #7 - Thursday, September 23,2004- Completed backfilling at Sta. 338 + 62 (Tropical West Breeze). LS $565.45 $565.45 Item #8 - Thursday, September 29,2004 - Performed an additional connection required at Super 8 Motel and IHOP at Sta. 320 + 59, which was not included in the original proposal. LS $2,371.07 $2,371.07 Item #9 - Monday, October 04,2004 - Submitted proposal to locate, existing 12" ductile iron water line in order to restrain the existing joints. This work was performed east of the FOOT right of way just north of entrance to Parks ide Medical Facility Sta. 338+62. LS $5,500.00 $5.500.00 Total Additions $14,196.87