CLEARWATER BAYFRONT PROMENADE - ADMINISTRATIVE CHANGE ORDER #1 & FINAL - 05-0008-MAADMINISTRATIVE CHANGE ORDER # 1 & Final
PROJECT: Cleawater Bayfront Promenade
Date: April 8, 2009
PROJECT NUMBER: 05-0008-MA
PO REFERENCE NO.: ST 104603
CONTRACTOR:
Misener Marine Construction, Inc.
5600 West Commerce Street
Tampa, FLorida 33616
DATE OF CONTRACT: August 8, 2008
CODE: 0315-93402-563800-575-000-0000 A
0315-93405-563800-575-000-0000 B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This Change Order decreases items and increases the Contract Time by 31 days.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $1,480,139.28
CO # 1& Final ($75,349.55)
NEW CONTRACT AMOUNT $1,404,789.73
ACCEPTED BY:
Misener Marine Construction, Inc.
By: (SEAL)
John . Whalen Vice President
Date: 4-09-09
Witnesses:
-/
VYY"
ATTEST:
Cyn a E. Goudeau, City Cler
Gel
Date:
"
r
CITY OF CLEARWATER, in?
PINELLAS COUNTY, FLORIDA
ICC
®1
Recom4ded By/- of Clearwater
Gary A. Johnson, CGC
Public Services Director
Michael D. Quillen; P.E.
City Engineer
William B. Home, 11 City Manager
A
Page 2 of 2
Clearwater Bayfront Promenade
Administrative Change Order # 1 & Final
ITEM DESCRIPTION QUANTITY UNIT UNIT COST
Decreases for Code A 0315-93402-563800-575-000-0000
Decreases to Line Items
46 Decrease 10% Contingency 0.330184051 LS $102,751.45
Subtotal Decreases to Code A
Decreases for Code B 0315-93405-563800-575-000-0000
TOTAL COST
($24,241.59)
($33,926.89)
($58,168.48)
Decreases to Line Items ($5,085.49)
72 Decrease to 10% Contingency 0.380284387 LS $31,806.67 ($12,095.58)
Subtotal Decreases to Code B ($17,181.07)
NET TOTAL,: ($75,349.55)