FIRE TRAINING FACILITIES AT FIRE STATION #48 - 05-0002-FD - ADMINISTRATIVE CHANGE ORDER #1 & FINALr^.
ADMINISTRATIVE CHANGE ORDER # 1 & Final
PROJECT: Fire Training Facilities @ Fire Station # 48
CONTRACTOR:
Bandes Construction Company, Inc.
1368 Spaulding Road
Suite "C"
Dunedin, FL 34698-5039
Date: February 1.9, 2009
PROJECT NUMBER: 05-0002-FD
PO REFERENCE NO.: ST 103555
DATE OF CONTRACT: August 17, 2007
CODE: 0315-91242-563600-522-000-0000 2
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This Change Order decreases items, increases items, and adds new items. It also resolves ODP items and results in a
overall decrease to the Contract: Amount.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $4,451,404.10
Adm. CO # 1 & Final Total ($$57,900.54)
NEW CONTRACT AMOUNT $3,593,503.56
ATTEST:
Cynt E. Goudeau, City Clerk
Date:
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA VIP
? ?. qua Fro ?.
William B. Horne 11 City Manager
ACCEPTED BY:
Bandes Construction Company, Inc.
i
By: (SEAL)
Robert Bandes, President
Date: 3
Witne es:
Recq 4mend0Q): City of Clearwater
Gary A. Johnson, CGC
Public Services Director
Michael D. Quillen, P.E.
City Engineer
...
'k:
Page 2 of 2
Administrative Change Order # 1 & Final
RE: Fire Station Training Facilities @ Fire Station #48
ITEM DESCRIPTION QUANTITY UNIT UNIT COST
Decreases for PO Code 0315-91.242-563600-522-000-0000 A
Decreases to Line Items
Decrease Due to Sales Tax Savings
Decrease 10% Contingency
0.5859481640 LS $404,673.10
Total Decreases to PO Code A
Decrease Contract Due To Owner Direct Purchases
TOTAL COST
($6,275.00)
($39,164.08)
($237,117.46)
($282,556.54)
($575,344.00)
NET TOTAL DECREASES TO CONTRACT: ($857,900.54)