Loading...
ADMINISTRATIVE CHANGE ORDER - FINAL - COC-97075010 ADMINISTRATIVE CHANGE ORDER - Final PROJECT: Clearwater Main Library CONTRACTOR: Turner Construction Company 800 N. Magnolia Avenue Suite #500 Orlando, Florida 32803 DATE: June 29, 2005 PROJECT NUMBER: COC-97075010 PO REFERENCE NO.: 699 31584 DATE OF CONTRACT: June 08, 2001 CODE: 0315-93523-563600-571-000-0000 THIS CHANGI: ORDI:R ACCEPTS REVISIONS TO "HI: CON I RAe.. STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT Deductive CO-ODPOs CC 6/19/03 Deductive CO-ODPOs CC 1/15/04 Credit to Turner re ODPO reductions Adm. CO - Final NEW CONTRACT AMOUNT '. . ..../,1 , . -'~' Date:-H 7/ ~- CITY OF CLEARWATER, in PI~=z;.::A':-JL William B. Home, II City Manager $14,532,915.00 -$2,008,255.00 -$912,446.00 $259,494.87 $55,589.42 $11,927,298.29 ACCEPTED BY: Turner Construction Company -:::: _ _~, B.dL tL~ ~~ (SEAL) ~ Tom Lall, Project Executive Date: '/30/05 ;rt Gary . J oRnson, CGC Public Services Director -~~ Kathy Dort Interim Library Director Page 2 of2 Administrative Change Order - Final Clearwater Main Library ITEM DESCRIPTION QUANTITY UNIT COST TOTAL COST Increases 39 Add west terrace drainage 1 is $8,864.95 $8,864.95 40 Drip edge cutting of Keystone 1 is $3,575.50 $3,575.50 41 Millwork changes 1 is $5,798.51 $5,798.51 42 Revised tile height and floor 1 is $18,177.57 $18,177.57 tile choices 43 East draiange revisions and 1 is $6,823.64 $6,823.64 landscape 44 Add Board Room Terrace 1 LS $4,121.95 $4,121.95 Drains 45 Add seven (7) windows - 1 LS $4,721.14 $4,721.14 Third Floor 46 Stair B rated enclosures 1 is $14,378.18 $14,378.18 47 Add steel lintel for Keystone 1 is $5,515.47 $5,515.47 support 48 Revised soffit - Level 3, south 1 is $3,989.08 $3,989.08 end 49 Plywood support for top of 1 LS $4,406.37 $4,406.37 cantilver 50 Accoustical ceiling - gallery 1 LS $3,825.42 $3,825.42 51 Add to contract - tax savings 1 LS $22,396.00 $22,396.00 shortfall SUBTOTAL (Increases): $106,593.781 Decreases 52 Adjust Contract Amount 53 CR for West Terrace Drains 54 Delete mulch from contract 60 Security System SUBTOTAL (Decreases): 1 1 1 1 LS LS LS LS -$2,265.55 -$6,488.81 -$2,250.00 -$40,000.00 I ($2,265.55) ($6,488.81) ($2,250.00) ($40,000.00) ($51,004.36)1 $55,589.42 NET TOTAL (this Change Order) Previous Deductive COs - CC Al!enda Items 6/19/2003 HV AC, Demo, Signage, Material Testing 6/19/2003 Owner Direct pas - total $ 1/15/2004 Owner Direct pas - total $ Actual ODPO $ expended Credit back to Turner -$197,502.00 -$1,810,753.00 -$912,446.00 $2,463,704.13 $259,494.87