ALLIGATOR LAKE WETLAND CREATION AND STORMWATER TREATMENT PROJECT - 99-0020-EN - CHANGE ORDER #2
CHANGE ORDER # 2
Date: December 22, 2008
PROJECT: Alligator Lake Wetland Creation & Stormwater Project Number: 99-0020-EN
Treatment Project
PO REFERENCE NO.: ST104566
CONTRACTOR: Ripa & Associates, Inc. DATE OF CONTRACT: September 03, 2008
1409 Tech Blvd., Suite #1
Tampa, FL 33619 - 7843 CODE: 0315-96137-563500-537-000-0000 (AA
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
See attached sheet for increases to contract, and approve a time extension of ten (10) days.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Adm. C0#1 (CM Approved 12/09/08)
CO#2
NEW CONTRACT AMOUNT
Prank Hi
Camilo Soto,-Xssistant City Marmgtar
$471,033.90
$28,703.15
$177,800.40
$677,537.45
ATTEST: r
nn
y yhia E. Goudeau, ?K
Date: O t 2-3 2.00
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, 11 City Manager
ACCEPTED BY:
Ripa & Associates, Inc.
By: (SEAL)
_L?L z -/-. . -
Christopher M. Estep, Project Manager
Date: l2 -23 -69
Witnesses:
n
ended By: City of Clearwater
Michael D. Quillen, P.E.
City Engineer
? (,0.?-y ,?o?Ir?Spr?
Gary . Johns ,
Public Services Director
Page 2 of 2
Change Order #2
ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Increases for Code "0315-96137-563500-537-000-0000"
2.4 Unsuitable Material Removal 5,868 CY $30.30 $177,800.40
Net Total Increase to Code "0315-96137-563500-537-000-0000": $177,800.40