06/01/1998 (2)
'.'. '
" "
; '\ :,'
'I'
.. '
..
"'::,, ,'<
,,',
" ,
! '
, "
'I" '
; ,
, "
. "
-' '., ~ c ' C ,', c . '
i1t'.V'? :;"1;"(1;:'!~!;;V!'!\;;";;;"i ";"",...~;~: ,\,' :;,' .....'
, '
'Tl' .c
. ,
.. '
I,'
, . I . "
:', ll'. 'I
': ,;
:L
, .1,
" ','
, "
"
'.':, ,
, ,'.
"
WORKSESSION
" '
, ,
, "
City 'Commission Worksession Minutes
,l.' I
, ,
:rune.
,
I "'l 8
II
f, :
, "
,
'Date
, "
, "
)
, ,
'~'l",\.4_""\""""'.a,''''' '... '.",~,
:z1OfU.,.......T r' , . '"
qas
;' ~ > :- c. ' '
'(," , .
) .
,
'r.i:.!~'.t',,' ,'. .~
4, "
" ,
d
...
o
~
t','"
CITY COMMISSION WORK SESSION
CITY OF CLEARWATER
June 1, 1998
i
f
I:
I
i
!
I
Present:
Rita Garvey
Ed Hooper
J. B. Johnson
Robert Clark
Karen Seel
Michael J. Roberto
Richard L. Hedrick
Bob Keller
Pamela K. Akin
Cynthia E. Goudeau
Brenda Moses
Mayor/Commissioner
Vice-Mayor/Commissioner
Commissioner
Commissioner
Commissioner (arrived 9:03 a.m.)
City Manager
Deputy City Manager
Assistant City Manager
City Attorney
City Clerk
Board Reporter
The meeting was called to order at 9:00 a.m. at City Hall.
PRESENTATIONS
Downtown Pond Status (WSOJ
Public Works Administrator Rich Baier gave a status report on the downtown pond.
He reviewed the project benefits, identified existing flooding problems, proposed 3 design
alternatives, and explained how the project facilitates the Brownfields initiatives and
increases the City's competitive edge. The present pond is 1.8 acres, has inadequate
storage volume for runoff, has frequent and periodic flooding problems, is unsightly, and
smells badly. The pond will be expanded to the north to a total of just over 4 acres. Total
acreage required is 4.5 acres. Plans are to add more green space to the area surrounding
the pond for a more aesthetically pleasing environment. In response to a question, he said
the pond can be expanded in the future. Treatment of storm water will remove many of the
nutrients before the water goes out into Clearwater Bay. He said if the City decides not to
pursue expansion of the current pond, it must accept the current level of service and
pursue other development incentive strategies. Mr. Baier will supply the Commission with
storage and volume capacity of the expanded pond. In response to questions regarding
Option #2, he said the berm will be more of a land slope, not a concrete berm seen from
the street. The City Manager said plans are to incorporate the pond into an urban park
type setting, with the possibility of tying it into other nearby developments.
Assistant City Manager Bob Keller said by permitting private land owners to utilize
the new downtown pond, it will cost them 25 % less than providing retention on their own
land. The City will cover permits and maintenance. In response to a question, he said
private land owners may not be expected to pay for pipes to connect to the pond. The
City plans to use as much information as possible from the study done by Real Estate
Research consultants last year. Firm figures were requested regarding costs of buying into
the use of the pond. Mr. Baier will supply the Commission with the assessed value of the
property being purchased to expand the pond.
mws06a98
1
06/01/98
r', .
'< ' '
"
'"
C)
~
Deputy City Manager Rick Hedrick said $1.5 million of Penny for Pinellas funds,
$500,000 from the private sector, and adjustments from storm water fees and grants will
comprise the $10 million estimated cost for the pond. The estimate includes costs for the
remainder of the design, acquisition of property, Brownfields clean-up, and sidewalks. It
does not include structures. It was requested staff check with SWFMD (Southwest Florida
Water Management District) and SWIM for additional funding. Mr. Baier said SWIM and
SURF, water improvement grants, and a Preservation 2000 grant for $800,000 are
anticipated.
The Mayor said the public needs to be aware this proposed pond is a huge downsize
from the previous proposal in 1995 of 36 acres. In response to a question, Mr. Baier said
this pond will address all water retention issues should other businesses come into the
downtown area. He said anticipated costs for the first phase of the pond design is
$100,000. He noted this does not address problems with some of the property owners
that have a finished floor and parking elevation that is lower than the street.
Consensus was to go forward with the project. Mr. Baier said he will bring the
project back to the Commission for approval. ,
Mr. Keffer acknowledged Dan Mayer and Miles Ballog for their efforts on this
project.
PUR PURCHASING
Mueller Distribution Contractors. installation of polvethylene Qas mains & service lines
throughout gas system, extension, 6/30/98-9/30/98 (GAS)
Cushion Deck International, purchase & installation of cushion deck safety plav surface at
Cherry Harris Park, $43,505.25 (SW)
Ross SYstems. Inc.. financial system software licenses & maintenance, 6/30/98-6/29/99,
$53,000 (1M)
In response to a question, Purchasing Manager George McKibben said total costs for
the contract with Mueller Distribution Contractors for installation of polyethylene gas mains
and service lines throughout the gas system is $478,000. This is a request for a 3-month
extension.
Commissioner Clark said the correct name of the company under Item #2 is Cushion
Deck International of Clearwater. In response to a question, Mr. McKibben said this
request is for the purchase and installation of cushion deck safety play surface constructed
of recycled tires at Cherry Harris Park.
Regarding Ross Systems, Inc., the City Manager said the most recent set of
programs run for the financial system software licenses and maintenance for the contract
period June 30, 1998, through June 29, 1999, Is not as accurate as desired. Ross
mws06a98
2
06/01/98
", ' "
)).!
",
(.)
~
continues to assure the City problems will be fixed. The issue must be resolved in July,
1998. The Commission will be updated on Ross' progress. The City Attorney is
researching legal remedies to the problem.
TR TOURISM
Approve recommendations for S08c;al Events Grants Fundina oifot oronram, granting total
of $50,000 to 8 Clearwater non-profit organizations for new or expanded special events
At the request of the Commission, a Special Events Grant Funding pilot program
was developed to assist Clearwater non-profit organizations in creating new, or expanding
existing, special events. The pilot program provides a total of $50,000 for eligible
applicants in variable increments with a maximum of $10,000 per event. Funds are to be
awarded on a matching basis of 2 City to 1 Applicant, of which 50% of the applicant's
match must be in cash. If City services are requested, such services are included in the
request for grant funding. Funds are for events between June 15, 1998, and September
30, 1999. Sixty-six 166) applications were distributed to those that attended the pre-grant
workshop or to those that requested an application by mail as a result of newspaper
notices. Of the 12 qualifying applications that were received, eight are recommended for
funding. Funding is available in the General Fund Non-Departmental program for this
purpose.
,In response to questions, Director of Tourism Jean Sherry said the Military Order of
the World Wars award was reduced from $10,000 to $5,000 in order for the City to be
able to fund several other projects. Although The Florida Orchestra, Inc. has had a concert
in the park earlier this year, this event includes fireworks. The Sunsets at Pier 60 Society,
Inc. funding is receiving $8,000 in addition to the $10,000 previously awarded. Sunsets at
Pier 60 is held every night. The City will fund Saturday nights. The City Manager said the
purpose of this funding is to help various organization expand in order to stand alone as
they grow in the future. The goal is to sponsor special events versus ongoing
programming, without discouraging ongoing events that are very successful. It was
remarked that funds are not intended be used for grounds improvements to applicants.
In response to a question, Ms. Sherry said 1 2 of 66 applications distributed were
received because some applicants were not qualified, some did not have the organizational
,staff to complete the application, and some had no organized plan to bring the funding
request forward. It was suggested streamlining the application process and arranging
partnerships with various nonprofit organizations to assist one another in obtaining funding.
Organizations must provide proof of commitment or have matching funds available at the
time of application.
PW PUBLIC WORKS
Contract to purchase real propertv commonlv known as "Atrium Aoartments". 1 707 N. Ft.
Harrison Ave.. Lesley's Sub., part of Lots 8 & 9 lying east of Ft. Harrison Ave. extended,
from Proactive Enterprises, Inc., $370,000; pay est. $21,500 for environmental audits,
$2,900 for boundary survey & closing costs, demolition expenses, excluding remediation of
mws06a98
3
06/01198
..-~
\:t:,,;j
The II Atrium Apartmentsll were constructed in 1927 at the apex of North Fort
Harrison and Myrtle Avenue. This aging structure dominates the Alternate US 19 northerly
entry into Clearwater. Further impetus for this purchase comes form areas residents and
the Old Clearwater Bay Neighborhood strongly supporting /lOne City. One Future. " goals to
beautify entryways into Clearwater. Among other conditions of the purchase, Seller is
required to deliver the property at closely completely vacated of any tenancies. At this
time, the extent of difficulties associated with pre~existing site conditions cannot be made
without performing a Phase I and limited Phase II audit of the property at a cost not to
exceed $21,500. The City will have 60 days following acceptance in which to conduct
this investigation and may withdraw from the contract if investigations reveal conditions
unsatisfactory to the City If it is determined the structure should be demolished following
its purchase, a demolition contractor has estimated the cost at approximately $56,085,
including a 10% contingency allowance, and subject to determination of the extent and
types of asbestos present in the building, which may increase demolition costs by an
amount unknown without completing an asbestos audit. Preliminary plans to create an
attractive passive park on the leveled site have been estimated at approximately $38,785,
exclusive of certain labor costs, which would be competitively bid. The park would provide
an attractive entry into Clearwater, as well as serving to partially satisfy a stated
Comprehensive Plan objective for one acre of park land in this planning district. City
Charter Section 2.01 (d) (4) Ox} requires 1 appraisal be performed for a property purchase
exceeding $250,000 but less than $500,000 in value. This property was previously
appraised for the City on January 3, 1996. The value was determined to be $3001000 at
that time. It is believed that valuation remains approximately relevant. In addition to this
purchase furthering 1I0ne City. One Future'; goals, it will also replace a neighborhood
feature perceived to be inimical to public safety and welfare with one which will be a major
enhancement. Funding in the amount of $416,000 will be provided from the undesignated
retained earnings of the Special Development Fund. The balance of $ 73, 270 will be
provided by a transfer of infrastructure funds from project 31 5~9331 6, Bayfront Park
Renovations. Mid~year budget amendments will address these amendments and establish a
project for this purchase.
:il
~
friable asbestos containing materials, est. $56,085, including 10% allowed for
contingencies; minimum park development costs est. $38,785 exclusive of certain labor
costs, for TOTAL acquisition costs est. $489,270 plus certain costs presently
undetermined
The City Manager said this property is at the northern entrance to the community.
Plans are to replace the structuro with a passive park. In response to a question, Mr. Baier
said a stipulation can be put in the contract the purchase is contingent on the
environmental report being favorable. In response to a question, the City Manager said the
property was not for sale at the time the City approached the owner. Staff and the owner
have negotiated on the purchase price. The system is geared toward protecting the
property owner.
In response to a question, Mr. Baier said a cursory audit has been done regarding
asbestos. On the surface it appears there is not an inordinate amount on the site. Atter
demolition of the structure, the Parks and Recreation Department will install an irrigation
y
mws06a98
4
06/01/98
~i '
~
!'~......
'" )
....
'~
system and provide other necessary services on the site for a passive park. Cost estimates
for these services have not been completed. It was questioned if the property is currently
to code. Mr. Baier said code violations have been corrected for the most part. The owner
has a responsibility to clean up the site until the sale is transacted. A comment was made
once the City demolishes the property, it may not be as lush and green as the public would
like. It was remarked that purchasing and cleaning this parcel of land will only improve one
portion of the area.
In response to a question, Mr. Baier said he will supply information regarding the
source of 'the Special Development Fund and the balance of the fund. The City is not using
the Major Intersection Improvement Fund for this project because of the current balance of
retained earnings in the fund. He said since December 1, 1996, 627 Police Department
service calls were received regarding problems at this site.
In response to a question, the City Attorney said when the City buys and sells
property, it is a matter of negotiation as to who performs site clean-up. In response to a
question, Mr. Baier said capping storage tanks to reduce soil contamination helps control
rain surcharge that can cause contamination to migrate.,
Public Hearina - Declare surplus for purpose of arantina an exclusive and perpetual
inaress/earess easement to Information Manaaement Resources, Inc.. its successors &
assigns, all of Lots 9, 10 & 11 of Revised Map of The Original Lot 5, R. H. Padgett's Sub.,
subject to approval & execution of a development agreement regarding real property
commonly known as the "Annex Site" between the eRA and lMR (Information
Management Resources), and conveyance of real property interests as stipulated therein,
reserving to the City the remainder fee interests, including, but not limited to, all rights
necessary for the construction & maintenance of public utility facilities within the full
easement width
It is anticipated the development agreement being formalized between the CRA and
IMR will contain a provision that the subject property be made available to IMR for
ingress/egress purposes from the southerly boundary of the "Annex Site" to the public
right-of-way of Gould Street. A stormwater retention plan already approved by the parties,
and now in the permitting process, provides for installation of a reinforced concrete
stormwater pipe extending from the "Annex Site" through the center of the proposed
easement to a pond to be constructed on the south side of Gould Street. The City reserves
all other property rights not inconsistent with the ingress/egress easement being granted to
IMR. These rights will allow for construction and future maintenance of all public utilities
as may be necessary for development of the "Annex Site". This exclusive ingress/egress
easement is granted for the purpose of facilitating planned development of the site and is
specifically not for dedication of the premises as public right-of~way. The easement rights
to be granted shall become effective concurrently with the conveyance by the CRA of real
property interests to IMR, and only upon such conveyances.
In response to questions, Mr. Baier said the City will build a pond on Gould Street
and pay for the stormwater pipe. Should the City decide not to build the pond, lMR will
construct a temporary pond facility to accommodate their storm water runoff. Because the
mws06a98
5
06/01198
...".
~
~.,
':.,,,",)
:.;;
City does not own the adjacent property, a permanent easement makes good sense. The
City Attorney said the easement is contingent upon IMR purchasing the II Annex Site".
The meeting recessed from 1 0:36 to 1 0:49 a.m.
C.O.#2 to Island Estates Reclaimed Water Transmission and Distribution Svstem, Contract
No.1. Kimmins Contractinn Coro.. decreasing contract by $274,449.16 for new total of
$3,377,165.86; C.O.#1 to Island Estates Reclaimed Water System, Pumping Station and
Storage Tank, Contract No. 2, Wharton~Smith Inc., increasing contract by $87,049 for new
total of $2,499,049; and approve time extension of 34 calendar days (Consent)
Contract No.1, (97-10) Change Order No.2, Island Estates Reclaimed Water
Transmission arid Distribution System has been prepared to reduce portions of the contract
items to reflect the actual quantities used to complete the project. Construct No. 2 (97~
15), to construct the Island Estates Reclaimed Water Storage Tank and Pumping Stations
was awarded to Wharton~Smith, Inc. on April 17, 1997, by the City Commission for a total
contract price of $2,412,000. A Change Order is necessary to advance the construction
process. A brief description of the Change Order Work is detailed on the following page.
The Landscaping work is being deleted from the Contract and will be performed by the City
Parks Department. The revised Substantial Completion date for Contract No.2 will be
June 26, 1998, with a total completion date of August 3D, 1998. Construction cost
summary: 1) Contract No.1 (97-10): original bid amount - $3,658,295; Change Order No.
1 - ($6,679.98); Change Order No.2 - ($274,449.16); revised contract amount ~
$3,377,165.86; and 2) Contract No. 2 (97~15): original bid amount - $2,412,000; Change
Order No. 1 ~ $87,049; revised contract amount - $2,499,049. A net reduction of
combined contract numbers 1 and 2 is 1$194,080.14).
Contract No. 1 (97-101
Change Order No.2, provides a decrease in the contract amount due to the
balancing of the original bid items and previously approved Change Order No. 1 items to
, reflect the actual quantities used to complete the project.
Contract No.2 (97-15)
Due to the large quantity of debris under the proposed parking areas and the new
roadway, the contractor had to remove the debris, install a Mirafi 500X geotextile fabric
with an 18" thickness of compacted Iimerock base in order to stabilize the enter pavement
limits at a cost of $56,944. During the relocation of the existing 54" RCP storm sewer
around the east side of the new reclaimed water storage tank, the contractor had to treat
and remove contaminated soil and unsuitable materials. This cost includes the installation
of an air stripping tower, temporary diesel generator, and importing clean fill materials at a
cost of $79,428. During the construction of the 30" ductile iron pipeline that passes
through the new screen wall, the contractor had to purchase and install a 36" galvanized
steel sleeve at a cost of $677. A time extension of 34 calendar days is required for the
additional work added by the Change Order No.1. The revised substantial completion date
is June 26, 1998, and the total completion date is August 30, 1998. The City has decided
mws06a98
6
06/01/98
~ . '. - :".~'-1~'."'\""~.~' '"
~
r')
\"J"
\.)
to complete the landscaping at the site. This includes preparation of the landscaping areas,
all landscaping materials, including tress, shrubs, mulch beds, aluminum edging, weed '
barrier fabric, sod, and seed, Including sand grown sod in the stormwater retention pond.
Credit and/or decrease to the City is ($50,000). Capital Improvements Project 97-10 and
97-15, IS 120795, Island Estates reclaimed water transmission and distribution, and the
storage tank and pump stations have available funding for the decreased amount of
($187,400.16).
In response to a question, Mr. Baier said the Parks and Recreation Department felt it
best to install landscaping since they will be maintaining the property. Purchasing the
materials without paying sales tax will provide additional funds for additional landscaping
plants. There are dollars in other areas of the project to provide for additional landscaping
materials if needed.
In response to a question, Mr. Baier said it is difficult for the contractor to know
what type of debris, if any, is under the pavement, prompting the Change Order.
Generally, it is the responsibility of the owner to provide information regarding underground
materials. He feels the City has an excellent policy in place to accept bids according to
known factors, then addressing unexpected issues as they arise.
Aporove Consultant Selection Committee's recommendation to retain Camo Dresser &
McKee. lnc.. King Engineering Associates, Inc., Parsons Engineering Science, Inc., Tampa
Bay Engineering, Inc., and Wade Trim, Inc., as additional City Engineers of Record
The City currently has one Engineer of Record, Post Buckley Schuh & Jernigan, Inc.
This contract extends until May, 2000. Due to the diversity of anticipated upcoming
project types requires to implement One City. One Future., staff determined that an
additional Engineer{s) of Record is necessary to make the best expertise and talent
available for City use. Typical projects will require architectural, landscape, storm water,
utility, structural, and grant writing areas of expertise, among others. The Selection
Committee "short-listed" the five recommended firms, each of which then made oral
presentations to the committee. The committee consisted of representatives from the City
manger's office, Public Works Administration, Finance, and Park and Recreation. Rating
factors included the approach to project services, staffing plan, sub-consultants, quality
assurance, and prior experience. the Ranking was as follows: 1) Tampa Bay Engineering;
2) Parsons; 3) King Engineering; 4) Wade Trim; and 5) Camp Dresser & McKee. It is the
committee's recommendation, based on the oral presentations, that all five firms be
retained as Engineers of Record. Upon the City Commission's approval of the committee's
recommendation, contracts will be negotiated with each firm and brought forward for
Commission approval.
Mr. Baier said partnering with firms in Clearwater, allows the City to funnel Penny
for Pinellas dollars back into the area. In response to a question, he said Camp Dresser &,
McKee's specialty is in the area of environmental and wastewater. This proposal will
afford the City a total of six Engineers of Record, with each firm offering their own area of
expertise. Of nineteen applicants, only King Engineering is located in Clearwater. Ranking
was based on the lowest possible score.
mws06a98
7
06/01/98
. ~ '.' ,
..' J
,-,
C)
, ":-:')
~
CP CENTRAL PERMITTING
Public Hearin~ First Readina Ords. #6284-98. #6285-98 & #6286~98 - Annexation, MPD
Zoning & land Use Plan Amendment to Residential Medium for property located 1,000 feet
east of US19N and north of Allen Creek, Sec. 29-29~16, M&B 22.01 & 22.02 and Sec. 20-
29~ 16, M&B 33.07 (Allen Creek Properties, Inc. I Harbourside Realty Holding Co., A9S-16,
LUP98-06)
This application involves the annexation of 62.11 acres of vacant property which
includes 19.57 wetland areas in order to obtain sanitary sewer and water services from the
City. 80th sewer and water lines are available in front of the property rights-ot-way to
provide the needed services. Assessed value of the property is $966,900. The applicant
proposes to construct 644 apartment units at the subject site after the annexation. The
Planning and Zoning Board held a public hearing on this application on May 19, 1998, after
which they unanimously endorsed the proposed annexation and zoning atlas amendment to
Master Planned development (MPD) and land use plan amendment to Residential Medium.
In response to a question, Director of Development Services Lorenzo Aghemo said
he will supply the Commission with information regarding the number of units currently
permitted under current zoning. He said one of the conditions of the study is that a traffic
impact study be done. It is anticipated the development will generate $800,000 in taxes
for the City. In response to a question, Mr. Baier said he will verify if property is in a
coastal hazardous zone.
Res. #98-21 - Reauestino the FOOT to convev title of the property located at 1400 Youno
Avenue, Clearwater, Florida, to the City of Clearwater, or otherwise grant permission to the
City to allow placement of additional antennas on the existing tower located on said
property
City staff desires to allow placement of additional antennas on the City~owned
tower located at 1400 Young Avenue, Clearwater. In particular, City staff desires to allow
BellSouth Mobility, Inc., to locate antennas on the tower in order in order to avoid
construction of a new 1 20-100t high tower proposed on the north side of Belleair Road,
approximately 200 feet west of Highland Avenue. The land upon which the City-owned
tower is located is leased from the Florida Department of Transportation (FOOT).
Placement of additional antennas on the City-owned tower requires either a lease
amendment or conveying title of the property to the City. IN order for the FOOT to
consider amending the lease or conveying title of the land, the FOOT requires the City
Commissions pass a resolution requesting same.
In response to a question, Mr. Aghemo said the City is not paying for the property
conveyance.
mws06a98
8
06/01/98
J'
., ' ' '. ~
, ,
. ,~
CM ADMINISTRATION
Brownfields Advisorv Board - 9 aooointments
Ordinance No. 6204-97 was adopted as required by Florida Statute 376.80(4) to
establish the Clearwater Brownfields Advisory Board. The purpose of the board is to,
improve public participation and receive public comments on: rehabilitation and
redevelopment of the Brownfields area, future land use, local employment opportunities,
community safety, and environmental justice. Advisory board members must review and
provide recommendations to the City Commissions regarding proposed site rehabilitation
agreements. The board shall consist of 9 members. Three shall be residents within or
adjacent to the Brownfields area, three shall be owners of businesses operating within the
proposed area and need not be residents of the City, and three shall be representatives of
Federal or State agencies or local governments involved in the Brownfields remediation
process within Pinel1as County and need not be residents of the City.
Economic Development (title) Miles Ballogg said staggered terms of 2, 3, and 4
years are required for these positions. It was noted Deborah Turner requested if other
, qualified candidates are available, she prefers her name be eliminated for consideration. It
was remarked the Commission recognizes many names on the candidate list and that Dr.
Noble would bring a unique perspective to this board.
CA LEGAL DEPARTMENT
Ir""\
......,~
Second Reading Ordinances
Ord. #6301-98 ~ Relatinq to Skateboards. Roller Skates, and In-Line Skates; amending Art.
I of Ch. 28, creating Sec. 28.11 to prohibit a person from using skateboards, roller skates,
and in-line skates in specified locations
The City Attorney said the Parks and Recreation Department has indicated one of
the few ways to traverse Clearwater Beach is by skating in parking lots due to the
narrowness of streets and sidewalks. They suggested an amendment to this ordinance to
eliminate the restriction of skating in parking lots. She suggested allowing skating in
parking lots, not in parking garages. The City can post those parking lots where it feels
skating activities should be restricted.
It was questioned if the City could adopt an ordinance similar to a City of New York
ordinance that prohibits the reckless operation of roller skates, in-line skates, and
skateboards on public streets. In response to a question, the City Manager said a
recommendation regarding a skateboard park will be presented to the Commission at the
July meeting.
~
mws06a98
9
06/01/98
~.. .1
'("\.
.'.
"
Ci?,\
~.~?;1~'
~
"
OTHER CITY ATTORNEY ITEMS
Discussion - Solicitation on Public Streets
Assistant City Attorney Rob Surette said since 1988, the City has had an ordinance
that prohibits persons from soliciting donations from the occupant of any motor vehicle
being operated on a public street within Clearwater. The ordinance is intended to prevent
the impediment to traffic flow that solicitation causes on frequently congested streets, and
to eliminate the danger that soliciting creates for solicitors and the occupants of vehicles
traveling those streets. A State Statute makes this activity a misdemeanor. Hillsborough
and Pinellas Counties also prohibit this activity. Pasco County's ordinance provides
specific criteria be met and an application be submitted.
Consensus was this type of activity is too dangerous on public rights-of-way. It
was questionect if "car wash" or "work for food" signs are permitted. Mr. Surrette said he
will supply the Commission with information regarding those activities not permitted in
medians, but that are acceptable on sidewalks.
, City Manager Verbal Reports
The City Manager said he will be unable to attend the June 4 Commission meeting
due to a Transforming Local Government Conference. He said the City is addressing how
to fund future projects in the City. They will involve public and private partnerships. As
each step of redevelopment progresses, it will be more obvious what is reasonable and
how the City can accomplish short and long term goals. He requested the Commission's
direction regarding how far, how soon, to progress over the next 10 years in order to meet
the public purpose and market viability. Once priorities are determined, cost estimates can
be done. At the June 1 5 Worksession, staff will bring forward Gulf-to-Bay Boulevard
redevelopment proposals. The Land Development Code revision is being finalized, master
development plans for downtown and the beach are forthcoming, and issues regarding
North Greenwood are being addressed. Staff's goals are to how to attain the City's Vision
and fund it, providing various options regarding each project, while refocusing the
organization to provide the information in the format the Commission wants.
It was remarked that some people are misinformed that the City has the money to
go forward with all these projects. Change takes time.
Other Commission Action
Commissioner Clark said he will be attending his son' 5 graduation Thursday and will
miss the next Commission meeting.
Commissioner Hooper said the new mast arms and street signs at SUnset Point
Road and Highland and Greenlee and Highland Avenues are impressive.
Commissioner Hooner said today is day 1 of hurricane season. He encouraged
everyone to take the time to prepare now.
mws06a98
10
06/01/98
~;:-'Ji,:":'/.;::":'<> ',:, ;',.:,.'
" . ~ t~ :: :
,: ' .
',', '
:',~ '
. ~"/>', ' " ,
,~
, . ,
Mavor Garvev said the Tampa Tribune published an article stating many mobile
homes are unsafe. She suggested a public campaign to encourage mobile home safety.
Commissioner Johnson questIoned when the ordinance to settle the Eller billboard
case will come forward. The City Attorney said it will be presented at the meeting in July.
Commissioner Johnson asked everyone to consider the ordinance very seriously before
passage. He has counted 36 signs with 18 supports on Gulf-to-Bay Boulevard, 9 of which
are Eller's. In response to a question, the City Attorney said removal of those signs is
pending resolution of the pending litigation. Eller Media has signs that are not on Gulf-to-
Bay Boulevard. PST A has an agreement with Eller Media for transit shelter advertising; the
other companies do not.
Commissioner Seel reported there will be a FEMA (Florida Emergency Management
Agency) workshop on June 8 at 9:30 a.m. in the auditorium of the St. Petersburg Junior
College Tarpon Springs Campus.
Commissioner Seel requested the construction status of the Sunshine Mall project.
Mavor Garvev said Chief Klein has indicated a sobriety checkpoint is scheduled for
June 6 from 9:30 p.m. to 3:30 a.m. at the Home Depot Plaza, US19 and Drew Street.
o
Mavor Garvev said children and teens, ages 8 to 18, can learn how they and their
families can best prepare for hurricane season by visiting the FEMA for Kids web site at
www.fema.gov/kids. '
')
Adjourn
The meeting adjourned at 11 :48 a.m.
f
. '''''<')
, ......,
mws06a98 '
11
06/01/98