Loading...
CLEARWATER BEACH WEST BRIDGE SPUR CONNECTOR - 99-0081-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINAL ADMINISTRATIVE CHANGE ORDER #1 & FINAL PROJECT: Clearwater Beach West Spur Connector CONTRACTOR American Bridge Company 5430 West Tyson Avenue Tampa, FL 337611 DATE: October 6, 2008 PROJECT NUMBER: 99-0081-EN PO REFERENCE NO.: ST 103431 DATE OF CONTRACT: Tune 7, 2007 CODE: 0315-92340-563800-541-000-0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT See attached sheet for Decreases/Increases/Additions. - STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: American Brid q Company ORIGINAL CONTRACT AMOUNT ADMINISTRATIVE CHANGE ORDER #1 & FINAL NEW CONTRACT AMOUNT $2,481,673.25 ($62,325.82) $2,419,347.43 BY: / Senior Vice Date: Qcr. G., 2GC18 EST: +Cyna Goudeau, City Clerk Date: L/ CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA William B. Horne, H City Manager Witn ses ` Ronald HendersJ O('4"' K. bV? Andrew Spangler Reco ended ity of Clearwater Gary A. Johnson, CGC Public Services Director Michael D. Qu' en, P.E. City Engineer 4 ? r Page 2 of 2 Administrative Change Order #1 & Final Clearwater BeachWest Spur Connector 99-0081-EN Code-0315-92340-563800-541-000-0000 ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL Additions 40 Project Signs 1 IS $1,200.89 $1,200.89 41 Temporary Mooring Barge 1 LS $12,500.00 $12,500.00 42 Barge Stanchions 1 LS $4,124.80 $4,124.80 43 Standby Time 1 LS $1,70240 $1,702.40 44 End Bent 1 1 LS $19,001.01 $19,001.01 45 Bright House Standby 1 IS $1,748.34 $1,748.34 46 Flowable Fill in Abandonded Manholes 1 IS $5,499.45 $5,499.45 47 Crack Injection 1 IS $3,001.89 $3,001.89 48 Vertical Crack, Sidewalk & Cap Repair 1 LS $20,109.61 $20,109.61 49 Remove & Replace Parking Lot Sidewalk 1 IS $2,033.13 $2,033.13 50 Add Fiber to Pavement 135 CY $7.62 $1,028.70 51 Concrete Removal in Parking Lot 1 LS $7,280.66 $7,280.66 52 Asphalt Patching in Parking Lot 1 IS $2,755.28 $2,755.28 53 6" Concrete Replacement, East Approach 1 LS $3,039.83 $3,039.83 54 Relocate Bollard 1 LS $1,499.85 $1,499.85 55 Extend Sidewalk, West Side 1 IS $503.57 $503.57 56 Thermo in Lieu of Paint 1 IS $1,507.49 $1,507.49 57 Add Grab Rail at West End 1 IS $888.80 $888.80 Total Additions to Code 031 5-92340-563800-541-000-0000 $89,425.70 Increases 3 Double Stake Silt fence (Type 111) 92 LF $8.00 $736.00 18 Tree Barricades 31 LF $12.00 $372.00 21 Class I Concrete (Retaining Wall) 4.8 CY $712.00 $3,417.60 22 Concrete Class IV (Superstructure) 21 CY $3,110.00 $65,310.00 26 Reinforcing Steel (Approach Slab) 0.3913 LB $1.38 $0.54 30 Prestressed Piles (24") 37 LF $700.00 $25,900.00 Total Increases to Code 0315-92340-563800-541-000-0000 $95,736.14 (Decreases) 5 Field Office (600 S.F.) 413 DA $10.00 ($4,130.00) 7 Embankment 214.5 CY $30.00 ($6,435.00) 8 6" Unreinforced Concrete Pavement 40 SY $72.00 ($200.00) 20 Polished Aluminum Railing System (54" HGT) 45 LF $114.00 ($5,130.00) 34 Dolphin Concrete 5.8 CY $570.00 ($3,306.00) 38 Contingency 1 IS $225,606.66 ($225,606.66) Total Decreases to Code 0315-92340-563800-541-000-0000 ($247,487.66) Net Total Decrease To Contract ($62,325.82)