PUMP STATION #16 RELOCATION - 02-0002-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINAL
~.
ADMINISTRATIVE CHANGE ORDER # 1 & Final
.
PRoJECT: Pump Station # 16 Relocation
CONTRACTOR:
TLC Diversified, Inc.
2719 17th Street East
Palmetto, Florida 34221
Date: August 27,2008
PROJECT NUMBER: 02-0002-UT
PO REFERENCE NO.: ST 103714
DATE OF CONTRACT: October 23. 2007
CODE: 0376-96686-563800-535-000-0000 A
0315-96686-563800-535-000-0000B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
See attached sheet for additional/decrease items for this change order.
STATEMENT OF CONTRACT AMOUNT
ACCEPTED BY--=
ORIGINAL CONTRACT AMOUNT
Adm. CO # 1 & Final
NEW CONTRACT AMOUNT
52,025,994.50
(5204,208.20)
51,821,786.30
Date:
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
TLC Diversified, Inc.
~
~ ~AL)
Thurston Lamberson, President
Date:~ C~~
of Clearwater
Gary A. Jo on, GC
Public Services Director
7l i/pr
Michael D. Quillen, P. .
City Engineer
,,j
.
Page 2 of2
Administrative Change Order # 1 & Final
ITEM
DESCRIPTION
QUANTITY JNI1 UNIT COST
TOTAL COST
Decreases for Code 0376-96686-563800-535-000-0000 "A"
Agenda 09/20/07 overstated contract 1 LS $50.00
7 DIP Fittings 0.12 Ton $16,150.00
9 12" DR 18 Gravity 1 LF $340.00
10 10" DR 18 Force Main 55 LF $78.50
14 Unsuitable Material Removal 370 CY $18.00
15 Select Fill 334 CY $20.00
16 Miscellaneous Concrete 88.5 CY $301.00
18 10% Contingency 1 LS $163;449.50-
Subtotal Decreases to Code" A"
($50.00)
($1,938.00)
($340.00)
($4,317.50)
($6,660.00)
($6,680.00)
($26,638.50)
- ($163;449.50)-
($210,073.50)
Additions for Code 0376-96686-563800-535-000-0000 "A"
20 Additional Asphalt 285 SY $20.58
Subtotal Additions to Code "A"
$5,865.30
$5,865.30
Total Net Decreases and Additions Code A
($204,208.20)