NE APCF IN-PLANT PUMP STATION REHAB - 07-0043-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINAL
l-...~
ADMINISTRATIVE CHANGE ORDER # 1 & FINAL
July 21, 2008
PROJECT: NE APCF In-Plant Pumo Station Rehab
PROJECT NUMBER: 07-0043-UT
PO REFERENCE NO.: ST 104449
CONTRACTOR:
TLC Diversified, Inc.
2719 17th Street East
Palmetto, FI 34221
DATE OF CONTRACT: June 10.2008
CODE: 0376-96664-563800-535-000-0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
To decrease contract by unused items - see attached sheet for details
STATEMENT OF CONTRACT AMOUNT
ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
Administrative Change Order # 1 & Final
NEW CONTRACT AMOUNT
$91,590.40
($10,734.40)
$80,856.00
TLC Diversified
~
~.-"'-iSEAL)
Thurston Lamberson, President
Date:
? /~IJJa R'
Date: ~uJ-&. GOosY
o /
CITY OF CLEARWATER, in
~~~
WIlliam B. Home, II City Manager
: City of Clearwater
)l..; ~
Page 2 of2
Administrative Change Order # 1 & Final
NE APCF In-Plant Pump Station Rehab
ITEM
DESCRIPTION
QUANTITY UNIT UNIT COST
TOTAL COST
Decreases for Code 0376-96664-563800-535-000-0000
5 Polymer Modified Mortar 14
6 Poly Injection 40
CF
Gal
$152.00
$7.00
($2,128.00)
($280.00)
10% Contingency
1 LS $8,326.40
TOTAL NET (Decreases):
($8,326.40)
($10,734.40)