MARSHALL STREET INFLUENT PUMP STATION REHABILITATION - 07-0014-UT - CHANGE ORDER #1 I \.; "f CHANGE ORDER # 1 PROJECT: Marshall Street Influent Pump Station Rehabilitation CONTRACTOR: TLC Diversified, Inc. 2719 17th Street Palmetto Fl. 34221 Date: October 1. 2007 PROJECT NUMBER: 07-0014-UT PO REFERENCE NO.: ST 103295 DATE OF CONTRACT: April 19. 2007 CODE: 0343-96664-563800-535-000-0000 A 0376-96664-563800-535-000-0000 B SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT This Change Order adds additional work to this contract. Approve a time extension of 150 days. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: ORIGINAL CONTRACT AMOUNT CO#I NEW CONTRACT AMOUNT $680,680.00 $397,151.70 $1,077,831. 70 ... .. ,.~. "'........-/ -.'- ,.,. ~ ~ - Date: /lJ - /;( :3-0' - '" CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA ~g~~-:IC. William B. Horne, 11 City Manager TLC Diversified, Inc. r' \T.) Thurston Lamberson, Presidt:nt. Date: .b/~/t!J/, . .' ~:~ ~ ~~ Gary A. Johnson, CGC Public Services Director ~4~ Michael D. Quillen, P.E. City Engineer t \ . . Page 2 on Change Order # 1 ITE DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST Additions for Code 0376-96664-563800-535-000-0000 B 66 Force Main Repairs 1 LS $22,587.00 $22,587.00 67 Replace Sluice gates 1 LS $30,809.00 $30,809.00 68 Revamp 24" FM at Splitter Box 1 LS $20,026.00 $20,026.00 69 Repair Asphalt Drive (Allowance) 300 SY $79.00 $23,700.00 70 Line 12" FM at Splitter Box 1 LS $27,795.00 $27,795.00 71 Bypass Rental - Standby - Pumps 1.5 MO $36,574.00 $54,861.00 72 Bypass Rental- Standby - Tank 1.5 MO $3,570.00 $5,355.00 73 Reconfigure Bypass - Electrical for 2 Pumps, VFD LS $14,360.00 $14,360.00 74 Reconfigure Bypass - Electrical for Transfer Switches LS $6,620.00 $6,620.00 75 Reconfigure Bypass - General Conditions LS $5,310.00 $5,310.00 76 Reconfigure Bypass - Freight in/out on Components LS $11,290.00 $11,290.00 77 Reconfigure Bypass - InstallJRemove Additional Rental Equipment 1 LS $16,980.00 $16,980.00 78 Reconfigure Bypass - Testing & Start-up 1 LS $4,100.00 $4,100.00 79 Additional Rental - Primary Bypass Pump 3 MO $7,315.00 $21,945.00 80 Diesel Fuel allowance 1008 HR $46.00 $46,368.00 81 Additional Rental- 12" High Head Diesel with Piping, etc. 3 MO $10,875.00 $32,625.00 82 Accelerate Schedule 1 LS $8,640.00 $8,640.00 83 Inspector Overtime 64 HR $45.00 $2,880.00 84 Audible Alarm System at Diesel Pumps 2 EA $2,398.00 $4,796.00 85 10% Contingency Change Order # 1 1 LS $36,104.70 $36,104.70 Subtotal Additions to Code B $397,151.70 NET TOTAL: $397,151.70