MARSHALL STREET INFLUENT PUMP STATION REHABILITATION - 07-0014-UT - CHANGE ORDER #1
I \.;
"f
CHANGE ORDER # 1
PROJECT: Marshall Street Influent Pump Station Rehabilitation
CONTRACTOR:
TLC Diversified, Inc.
2719 17th Street
Palmetto Fl. 34221
Date:
October 1. 2007
PROJECT NUMBER: 07-0014-UT
PO REFERENCE NO.: ST 103295
DATE OF CONTRACT: April 19. 2007
CODE: 0343-96664-563800-535-000-0000 A
0376-96664-563800-535-000-0000 B
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This Change Order adds additional work to this contract. Approve a time extension of 150 days.
STATEMENT OF CONTRACT AMOUNT
ACCEPTED BY:
ORIGINAL CONTRACT AMOUNT
CO#I
NEW CONTRACT AMOUNT
$680,680.00
$397,151.70
$1,077,831. 70
... .. ,.~.
"'........-/
-.'-
,.,. ~ ~ -
Date: /lJ - /;( :3-0' -
'"
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
~g~~-:IC.
William B. Horne, 11
City Manager
TLC Diversified, Inc.
r' \T.)
Thurston Lamberson, Presidt:nt.
Date: .b/~/t!J/, . .'
~:~
~ ~~
Gary A. Johnson, CGC
Public Services Director
~4~
Michael D. Quillen, P.E.
City Engineer
t
\
. .
Page 2 on
Change Order # 1
ITE DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Additions for Code 0376-96664-563800-535-000-0000 B
66 Force Main Repairs 1 LS $22,587.00 $22,587.00
67 Replace Sluice gates 1 LS $30,809.00 $30,809.00
68 Revamp 24" FM at Splitter Box 1 LS $20,026.00 $20,026.00
69 Repair Asphalt Drive (Allowance) 300 SY $79.00 $23,700.00
70 Line 12" FM at Splitter Box 1 LS $27,795.00 $27,795.00
71 Bypass Rental - Standby - Pumps 1.5 MO $36,574.00 $54,861.00
72 Bypass Rental- Standby - Tank 1.5 MO $3,570.00 $5,355.00
73 Reconfigure Bypass - Electrical for 2
Pumps, VFD LS $14,360.00 $14,360.00
74 Reconfigure Bypass - Electrical for
Transfer Switches LS $6,620.00 $6,620.00
75 Reconfigure Bypass - General Conditions LS $5,310.00 $5,310.00
76 Reconfigure Bypass - Freight in/out on
Components LS $11,290.00 $11,290.00
77 Reconfigure Bypass - InstallJRemove
Additional Rental Equipment 1 LS $16,980.00 $16,980.00
78 Reconfigure Bypass - Testing & Start-up 1 LS $4,100.00 $4,100.00
79 Additional Rental - Primary Bypass Pump 3 MO $7,315.00 $21,945.00
80 Diesel Fuel allowance 1008 HR $46.00 $46,368.00
81 Additional Rental- 12" High Head Diesel
with Piping, etc. 3 MO $10,875.00 $32,625.00
82 Accelerate Schedule 1 LS $8,640.00 $8,640.00
83 Inspector Overtime 64 HR $45.00 $2,880.00
84 Audible Alarm System at Diesel Pumps 2 EA $2,398.00 $4,796.00
85 10% Contingency Change Order # 1 1 LS $36,104.70 $36,104.70
Subtotal Additions to Code B $397,151.70
NET TOTAL: $397,151.70