CLEVELAND STREET STREETSCAPE 03-0093-ED CHANGE ORDER #2 CHANGE ORDER #2 DATE: Tune 21, 2007 <~ PROJECT: Cleveland Street Streetscape PROJECT NUMBER: 03-0093-ED PO REFERENCE NO.: ST 102232-2 CONTRACTOR: Gibbs & Register, Inc. 530 S. Main Street Winter Garden, FL 34787 DATE OF CONTRACT: 5/2/06 CODE: 0315-92269-563700-541-000-0000 Streets 0377-92269-563700-539-000-0000 Storm 0357-92269-563700-539-000-0000 Storm 0315-92269-563700-539-000-0000 Storm 0378-92269-563800-533-000-0000 Water 0315-92269-563800-535-000-0000 Sewer 0377-92269-563700-539-000-0000 Storm 0357-92269-563700-539-000-0000 Storm 0378-92269-563800-533-000-0000 Water SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT See attached sheet for additional items. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: Gibbs & Register, Inc. ORIGINAL CONTRACT AMOUNT CHANGE ORDER #1 CHANGE ORDER #2 NEW CONTRACT AMOUNT $11,275,561.88 ($2,325,456.09) $726,594.74 $9,676,700.53 SEAL) B T Date: /j-Z-;{7 Witnesses: ./) Date: CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA ~ B.~<I William B. Horne, II City Manager a . h . Pu lic Servic Director ~~ Michael D. Quillen, P.E. City Engineer Page 2 of 2 Change Order #2, Cleveland Street Streetscape (03-0093-ED) ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL Stormwater Code: 0377-92269-563700-539-000-0000 $212,002.52 0357-92269-563700-539-000-0000 $398,139.22 Additions 230 Additional drainage @ Opus * 1 LS $ 17,025.00 $17,025.00 231 Additional drainage @ sta sq (Biltmore) * 1 LS $ 6,925.00 $6,925.00 232 Additional drainage @ sta sq (city) 1 LS $ 8,225.00 $8,225.00 233 Revised drainage @ Osceola 1 LS $ 11,700.00 $11,700.00 234 Conflict str w / PE duct bank @ seawall 1 LS $ 36,420.00 $36,420.00 235 5eawallreplacement 1 LS $ 9,880.00 $9,880.00 236 Conflict structure 5-139C 1 LS $ 14,500.00 $14,500.00 237 Modify existing structures 9 EA $ 3,150.00 $28,350.00 238 Conflicts w / 54" RCP at Osceola 1 LS $ 69,000.00 $69,000.00 239 Conflicts @ Ft. Harrison 1 LS $ 68,995.00 $68,995.00 240 Conflicts Ft. Harrison to Garden 1 LS $ 110,785.42 $110,785.42 241 ERCP cleanup due to Water Main Break 1 LS $ 32,091.00 $32,091.00 242 PE/Verizon conflict structure @Garden 1 LS $ 44,135.00 $44,135.00 243 RFI 75 - mod 3 struct. due to PE, Garden 3 EA $ 3,150.00 $9,450.00 Ave. south side 244 RFI 79 - mod 3 struct. due to PE, Garden 3 EA $ 3,150.00 $9,450.00 Ave. north side 245 RFI 76 - 5-106 conflict w / Verizon 1 LS $ 2,347.22 $2,347.22 246 RFI75 - redesign 5-103 v inlet, matIs. 1 LS $ 595.10 $595.10 247 Roof Drain Installation 30 EA $ 350.00 $10,500.00 248 Relocate Verizon duct bank @5-302 1 LS $ 5,968.00 $5,968.00 249 Remove & replace unsuitable material 1 LS $ 94,000.00 $94,000.00 Total Additions to Stormwater $590,341.74 * These amounts were reimbursed to the City by the Developer Increases 85 RCP 36" 24 LF $ 150.00 $3,600.00 89 ERCP 14"x23" 62 LF $ 100.00 $6,200.00 98 Manhole J-7T 1 EA $ 10,000.00 $10,000.00 Total Increases to Stormwater $19,800.00 Total Net (Decreases)jIncreasesfAdditions to Storm Code $610,141.74 Water Code: 0378-92269-563800-533-000-0000 Additions 260 6" gate valve & box 1 LS $ 1,400.00 261 Lower jack & bore for casing 2 EA $ 13,500.00 262 Replace 6" water line @ Osceola 1 LS $ 24,000.00 263 Remove 24" steel casing on 12" water main at 5ta. 211 1 LS $ 2,347.00 264 Relocate 4 hydrants, remove one hydrant 1 LS $ 50,000.00 265 Remove old water main at Garden Ave. 1 LS $ 4,816.00 Total Additions to Water Increases 104 8" PVC Watermain 14 LF $ 55.00 106 12" PVC Watermain 14 LF $ 80.00 117 Wet-tap, 8"x8" w / tapping sleeve & valve 1 EA $ 5,000.00 Total Increases to Water $1,400.00 $27,000.00 $24,000.00 $2,347.00 $50,000.00 $4,816.00 $109,563.00 $770.00 $1,120.00 $5,000.00 $6,890.00 Total Net (Decreases)jIncreasesfAdditions to Water $116,453.00 Total Net (Decreases)jIncreasesfAdditions $726,594.74