CLEVELAND STREET STREETSCAPE 03-0093-ED CHANGE ORDER #3 ~ Clearwater u Interoffice Correspondence Sheet From: William B. Horne, II, City Manager Gary A. Johnson, CGC, Public Services Director To: CC: Tina G. Wilson, Budget Director; Anne Fogarty, Economic Development Program Coordinator; Paul Bertels, Traffic Operations Manager; Tara Kivett, Construction Project Coordinator; Andrea Beane, Senior AccountanU Public Services; Stephanie Sansom, Senior AccountanUPWA Engineering/ESM; Alice Eckman, Construction Office Specialist Date: August 2, 2007 Administrative Change Order No.3 - Cleveland Street Streetscape (03-0093-ED) RE: RECOMMENDED ACTION: Approve Administrative Change Order No.3 Gibbs & Register, Inc. of Winter Garden, FL for the Cleveland Street Streetscape Project (03-0093-ED) increasing the contract amount by $528,536.00 for a new contract total of $10,205,236.53. BACKGROUND: This contract was previously approved by the City Council April 20, 2006 for $11,275,561.88 and a deductive Change Order No. 1 was approved at this same meeting decreasing the contract amount by $2,325,456.09, for a new contract total of $8,950,105.79. Change order No. 1 was part of the value engineering process to reduce costs. Change Order No.2 in the amount of $726,594.74 was approved by the City Council July 19, 2007 for a new contract total of $9,676,700.53. Change Order No. 2 was needed to cover costs associated with field conditions, overrun of existing bid items, and design changes. Change Order No. 3 includes the addition of a new mast arm at the Drew and Osceola intersection and re-establishes the date palms that were deleted during the value engineering process. The palms will be planted at the quantity and unit price from the original March 2006 bid. The new mast arm at Drew and Osceola will improve the overall intersection operation with a more reliable signal support structure and improve the survivability of the signal during major storm events. Sufficient budget and revenue are available in the Capital Improvement Program project, 0315-92558 Intersection Improvements to fund for the new mast arm to be installed at Drew Street and Osceola Avenue in the amount of $206,536.00. OFFICE OF MANAGEMENT AND BUDGET DEPARTMENT REVIEW I recommend approval based on the administrative change order criteria: 1. Increases do not exceed 10% of the Council approved amount on a cumulative basis. 2. Change does not change the scope of the project. 3. Price increases do not require additional appropriation to the project. 4. Contract price decreases may be approved without limitation. 5. Completion date is not extended more than 60 days. Gin'; G. wifs~';, ?'\"'\~:Je Adm. CO#3 -Memo - Cleveland Streetscape Initial "~ ADMINISTRATIVE CHANGE ORDER #3 DATE: Iuly 27, 2007 ~" PROJECT: Cleveland Street Streetscape PROJECT NUMBER: 03-0093-ED PO REFERENCE NO.: ST 102232-2 CONTRACTOR: Gibbs & Register, Inc. 530 S. Main Street Winter Garden, FL 34787 DATE OF CONTRACT: 5/2/06 CODE: 0315-92269-563700-541-000-0000 Streets 0377-92269-563700-539-000-0000 Storm 0357-92269-563700-539-000-0000 Storm 0315-92269-563700-539-000-0000 Storm 0378-92269-563800-533-000-0000 Water 0315-92269-563800-535-000-0000 Sewer 0315-92269-563700-541-000-0000 Streets 0315-92558-563700-541-000-0000 Intersection SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT See attached sheet for additional items. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: Gibbs & Register, Inc. ORIGINAL CONTRACT AMOUNT CHANGE ORDER #1 CHANGE ORDER #2 CHANGE ORDER #3 NEW CONTRACT AMOUNT $11,275,561.88 ($2,325,-t56.09) $726,594.74 $528,536.00 $10,205,236.53 BY'uW' ~ .... Ted Ferguson, ice esident (SEAL) Date: g- /- 0 l --~./ Witnesses: Cr~O~ ~J#~ x~ [. 2a:?7 . ity of Clearwater Dol, ~ ~ CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA @df7~~~ William B. Home, II City Manager , Michael D. Quill City Engineer Page 2 of 2 Adm. CO#3 - Cleveland Street Streetscape (03-0093-ED) ITEM DESCRIYTION QUANTITY UNIT UNIT COST TOTAL General Fund Code: 0315-92269-563700-541-000-0000 Additions 178 Medjool Date Palms 46 EA $ 7,000.00 $322,000.00 Total Net {Decreases)jIncreasesfAdditions to General Fund $322,000.00 Intersection Improve Code: 0315-92558-563700-541-000-0000 Additions 210 Signalization@Drew/Osceola 1 LS $ 206,536.00 $206,536.00 Total Net (Decreases)jIncreasesfAdditions to Intersection Improvement $206,536.00 Total Net (Decreases)fIncreasesfAdditions $528,536.00