ENVIRONMENTAL AND STORMWATER MANAGEMENT FIVE YEAR CAPITAL WATER RESOURCE PROJECTS IMPROVEMENTS - SUMMARY FY 2002-2006 I I I I I I I I I I I I I I I I I I I CITY OF CLEARWATER ENGINEERING DEPARTMENT Environmental and Stormwater Management Five Year Capital Water Resource Projects Improvements SUMMARY FY 2002 - 2006 LL earwater o > ~ u I I I I I I I I I I I I I I I I I I I Table of Contents Introduction.................................................................................................................... ................................ i Structure Flooding Improvement Projects ....... .................. .......... ............ ................ .......... ....... .................... 3 Myrtle Avenue Drainage and Roadway Improvements Project ........................................................... 4 Kapok Flood Resolution Project ................................... .... ..... ....... ................ ........... .................. ..... ... ... 6 Town Pond ...................... ............... ............... ...... ...... ...... .... ......... ....... .... ....... ................ ................ ... .... 8 Sharkey Road Drainage Improvement Project............................... ..................................................... 10 Alligator Creek Drainage Improvements .................. ................ ............. ....... .................... .......... ........ 12 Stevenson Creek Implementation Phase I.......... .................. ....... ....... ........... ........................ .............. 14 Momingside - Meadows Drainage Improvements............................................................................. 16 Tropic Hills Drainage Improvements................................................................................................. 18 Allen's Creek Neighborhood Flooding.... .............. ...................... ............. ......... .......... ........... ............ 20 Street Flooding Projects....................................................................................................................... ....... 22 N. Greenwood Corridor Stormwater Enhancement Project................................................................ 23 Storm Pipe System Replacement Projects ............................................. .................. ........................... 25 North Beach Drainage Improvements... ..... .... ........ ...... .... ........ ................... ............................ ....... ..... 27 Regulatory Compliance Projects................................................................................................................ 29 FDEP Compliance...................................................................................................................... ........ 30 Bridge Flooding Projects .......... ......... .... ......... ......... ........ .................. ............... ....... .... ........ ....... ................ 32 Maj or Erosion Projects............................................................................................................................... 33 Allen's Creek Gabion Project............................................................................................................. 34 Water Quality and Environmental Projects................................................................................................ 36 Stevenson Creek Estuary Restoration................................................................................................. 37 Alligator Creek Implementation Projects .... ................... ................ .................. ........... ................. ...... 39 North Greenwood Stormwater Retrofit. ............ .............. ....... ........... ............ ............. ......................... 41 Other Projects...................................................................................................................... ....................... 43 Storm System Expansion Project. ...... ................ .... ...... ............... ......... ......... .... ............. ..................... 44 Appendix A.... .... ......................... .......... .................... .... .... ........... .... ............. ....... ................. ...................... 46 Review and Approval Process Appendix B ..................................................................................................................................... ............ 48 Strategic Objectives/Measuresffargets Appendix C .............................................................................................................................. ................... 50 Stormwater Utility Project List Appendix D.............................................................................................................................. ................... 54 Capital Improvements Program I I Introduction I The City of Clearwater implemented a Stormwater Utility Fee in FY 1991 to pay the cost of stormwater drainage facilities to be constructed City-Wide and to pay the cost of operation, monitoring, enforcement, administration and maintenance of the stormwater drainage facilities of the City. (Ord. No. 5058-90) The summary document is intended to be an annual review document for the Clearwater City Commission that describes studies or projects being considered or developed by the Engineering Department, in conjunction with Public Service, Drainage and Transportation. This summary document will not describe program funding related to operational costs, rather it will describe the planned projects as outlined in the City Capital Improvement Budget and planned Rate Study Bond Improvements commencing in FY 2002 through FY 2006, inclusive. I I I I I I The primary purpose for this document is to provide the Clearwater City Commission with a clear understanding of the purpose, justification, and scope of planned Capital Improvement Project (CIP) expenditures. It is also intended to provide the City Commission the opportunity to review and provide conceptual approval of those planned watershed studies and water resource projects being considered for development. City Staff regard City Commission acceptance of this document and any subsequent CIP budget and rate study projects approvals as direction to proceed to acquire grant funding for project development as may become available. The emphasis in describing planning and improvement projects in this document is on projects that City Staff are actively pursuing through the Stormwater Capital Projects Review and Approval Process (Appendix "A") and that exceed a total project cost of $100,000. Operational projects of any amount (GIS Project) and projects less than $100,000, while listed on each chapter cover, are not specifically described in this document. I I I I I I I This document is intended to provide only brief project descriptions. Chapters are organized based on the Engineering Department's stormwater project "Problem Classification and Ranking Priority", depicted in Table 1. I I I Priorit I 2 3 4 5 6 Project and problem priorities are presented in the page header information for each project. The City Commission priority reflects the City Commission Strategic Objective "Key Intended Outcome" (KIO). The higher the KIO priority score the greater is the Commission priority. The KIO priority scores were established during development of the Stormwater Utility Enterprise Fund Business Plan in March 2001. The Commission priority score reflects those "Key Intended Outcome" factors that might be addressed by implementation of the project being considered. For example: The Town Pond project would certainly leverage private development funding through the City Commission approved "Regional Retention District" overlay, thereby satisfying that one City Commission KIO to meet the "Major Infrastructure Maintenance and Improvements" strategic objective. In that instance, the KIO would be given a score of one. The final KIO score is the summation of each KIO priority score for each Commission Strategic Objective KIO that the project is expected to satisfy. The maximum score that any project could possibly receive is twenty-three (23). A summary of the City Commission Strategic Objectives and corresponding KIO's is listed in Appendix "B". In conjunction with City Commission KIO's is included the problem classification and priority score, established by the Engineering Department, Capital Improvement Stormwater Management Steering Committee (CISM). That score not only establishes a rank based on the project classification, but also recommends the order for completion of projects based on project technical constraints. For example: using Table I above, a project to resolve structure flooding would receive a problem priority score of one point zero, zero (1.00). Project implementation would then follow in order with one point zero- one (1.01) being the first project through one point nine-nine (1.99) being the last project to be completed within that problem classification series. Technical project constraints are critical to the successful completion of infrastructure improvements for public safety reasons and therefore are considered and ranked in every project priority decision. General project descriptions and locations, with pictures or graphics, where appropriate, are provided. Each description provides a brief explanation of the project, the proposed project objectives, current project status, and brief fiscal information. In order to provide brief, yet informed descriptions, certain caveats are necessary: 1. This document reflects both Staff recommendations for project priority, as depicted in Table 1, and the Key Intended Outcome (KIO) ranking score defmed by the City Commission and interpreted by Staff as major priority areas for this fiscal year. The strategic objectives of the Commission include: (1) Public Safety; (2) Economic Development; (3) Quality of Life; (4) Infrastructure Maintenance; (5) Human Resources. Where differences between the two ranking priorities are apparent, City Commission priorities superpose the ranking of projects depicted in Table 1. 2. Descriptions are designed to be brief and objective. They are clearly not comprehensive evaluations. 3. The listing of proposed water resource projects reflect primarily structural solutions to address the documented "primary purpose". It is stressed that structural solutions currently being considered do not preclude changing to non-structural solutions at a later date, as circumstances and priorities may change. 4. The project status reflects either the actual project status or the anticipated next step of the process where that next step is imminent. 5. Fiscal summaries are to be considered project estimates only and are subject to change and City Commission approval through the budget and project review process. I 6. A summary of all stormwater problems throughout Clearwater is listed in APPENDIX "C". That list is complete as of FY'OI and includes projects to address water resource problems documented through either City watershed management plans, as required by the City Comprehensive Plan, or based on citizen expressed complaints. This doesn't preclude future changes to the list due to unplanned circumstances. 7. Secured funding represents a funding expectation that has been either approved by the City Commission or has a signed interagency agreement by the supporting agency, but not yet approved by City Commission. Un-secured cost share information reflects an expectation that while not specifically approved by City Commission or through interlocal agreement, is included for planning purposes in agency budgets or long range planning documents. Grants that have only been applied for and having no agency commitment have not been included in the fiscal summary of projects. 8. Where funding has been approved for cost share by others and the City of Clearwater is also the lead agency, the City is responsible for the initial payment of ALL project related costs, followed by subsequent participant reimbursement. 9. For each project, the "Needed to Complete" line item included in each project summary represents a line item project cost that has been modeled in the rate study. That table of all projects planned for and included in the rate study update is provided as APPENDIX "D". I I I I I I I I I I I 'I I I I I I 11 I Commission Project Cost Priority 13 $11,104,000 11 $16,688,000 11 $13,030,000 10 $900,000 9 $4,424,044 9 $6,090,500 9 $575,000 8 $550,000 8 $600,000 TOTAL: $53.961.544 I I I I I STRUCTURE FLOODING IMPROVEMENT PROJECTS I I I Project I I Myrtle Avenue Drainage and Roadway Improvements Project Kapok Flood Resolution Project I Town Pond I Sharkey Road Drainage Improvement Project Alligator Creek Drainage Improvements I Stevenson Creek Implementation Projects, Phase I I Morningside Meadows Drainage Improvement Project Tropic Hills Drainage Improvement Project I I Allens Creek Neighborhood Flooding Project I I I 3 Myrtle Ave. Drainage and Roadway Improvement Project Brian Barker City of Clearwater Coastal Zone 1 Commission (KIO) 13 Problem Priority 1.01 CIP - City, Project Development Structure Flooding, Street Flooding PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Description: The Myrtle Avenue Drainage and Roadway Improvement Project will consist of the reconstruction of approximately 2.4 miles of a major north/south roadway through downtown Clearwater between Lakeview Rd. to the south and Ft. Harrison Ave. to the north, including replacement of the substandard stormwater conveyance system. Myrtle Avenue is scheduled to be designated as Alt US 19 after a planned road exchange occurs with the FDOT. The Roadway improvement project must be completed before re-designation takes place. The proposed improvements will reduce flood hazard along the corridor, removing 18 properties from flooding in the 100 year storm event and flooding of 17 street locations during the 10 year event. Implementation will improve the viability for re-development. By improving the stormwater system through the proposed Myrtle A venue project and in concert with the planned Town Pond improvements, these vacant or under performing parcels will become attractive development/redevelopment sites for new businesses, bringing an increase in economic productivity to the Clearwater community. Objectives: 1. Reduce flood hazards along the Myrtle A venue corridor by replacing failing and undersized stormwater infrastructure. 2. Improve the viability of the Myrtle A venue corridor by becoming an attractive site for business re-development. 3. Bring Myrtle Avenue up to current FDOT specifications in order to exchange Myrtle Avenue for Fort Harrison Ave. FY 2001: The drainage plan for Myrtle A venue, Myrtle Avenue Stormwater Improvement Project, was completed in August 2001. The City is currently negotiating with CDM for design construction plan preparation. The City has applied for FDOT funding through the Transportation Outreach Program to fund $5.4 million of road improvements, leveraging stormwater revenues to obtain road improvement funding. STATUS FISCAL SUMMARY Project Cost Planning Design EngineeringlPermits Land Acquisition Construction TOTAL PROJECT COST Funding from Others Secured Unsecured Total Other Funding City Share Roadway Funding Stormwater Utility Total City Funding TOTAL PROJECT FUNDING Requirements Total Project Cost Less Roadway Funding Expended Through 09/30/00 Needed to Complete 4 I I I I I I I I $ 49,500 $1,255,000 I I $9.100.000 I $11.1 04.000 I 0% I $0 I 100% $ 1,049,500 $ 9.355.000 I $11,104,000 ,I $11.1 04.000 $11,104,000 $ 1,049,500 ~ $ 9.355.000 I I I I I Myrtle Avenue Roadway Improvement Project I I / .I ,:" ~( " ~.~\!~ Ii \:'( Y', I U S.R. 580 I t -, ii I> ,', 1[1 "...." ../ ,J:/,~~~ I , I 0 ~ o :=> N.T.S. I ~ 't-uIf 01 , I 'I') (\ , , 'y) 8 \ tD \ Z ~) ~ \ S SAFETY HARBOR / ~ l ~ ;/ MAIN T ~) .-,<1 Iv ,V,;/~ .,"/J _lJv-"'t ..:J-- (~r>. .-l,. (' 'I / ... ~ I l~i\, \ ,~~\ \:l!}~..':l .It(~~I\\l ! '- -~;-,> ,r;MJ ! L~ "'.:-? ,. ~(.,-..'-') '-'.~ ,. ~ ,~. " -- '. \>~.~.~:..=? '~-;,' " \ "-.'- (J~~/ ) . ! '( ( , I ~!' }("""- .~/ A (j) 6 &iJ . ti 1?G'? '. / BELLEAIR -J:. / ,..,t!) I >-' .---~)---" l..L ~ I I I !1I"'f I ".~~ I I I I I ~..,.:::.~,;-,~- I I I 5 PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Kapok Flood Resolution Project Terry Finch City of Clearwater Alligator Creek Commission (KIO) 11 Problem Priority 1.05 CIP - Joint, Interlocal Agreement Flood Control, Water Quality/Environmental Enhancement Description: The Friendly Village of Kapok is located in the Alligator Creek Basin and was identified and prioritized in the "Comprehensive Watershed Management Plan for the Alligator Creek Watershed" (June 1997). The project was developed cooperatively with the City of Clearwater, Pinellas County and the Southwest Florida Water Management District. Flooding of the Park is recognized for its severity, frequency, and number of affected residents. Removal of the Park will eliminate potential flooding for 200 mobile homes, 3 bridges and 497 properties upstream including, for example, College Hill Estates. The project would involve the purchase of the mobile home park and the relocation of the residents, allowing for floodplain restoration, wetland creation and habitat improvement, water quality improvement, and recreation and education facilities. The conceptual plan proposes the recreation of approximate I y 2.6 acres of wetland and would restore the area. Objectives: 1. Resolve property flooding. 2. Remove the existing Cliff Stephens Park control weir. 3. Reconstruct a longer weir to reduce the 10, 25 and 100 year flood elevations upstream. 4. Excavate the project site for wetland creation and also provide additional floodplain storage volume that will serve to attenuate the peak flow rate in the downstream channel, 5. Allow for the resolution of upstream flooding of approximately 497 structures. 6. Enhance the water quality treatment function of the existing and proposed stormwater facilities at Cliff Stephens Park and Moccasin Lake Park, thereby protecting Tampa Bay, an Estuary of National Significance, S.W.l.M. Waterbody, Outstanding Florida Water and Aquatic Preserve. STATUS I I I I I I FY 2001: Funding for the design and construction of the project has been approved in the SWFWMD Five Year Plan. Funding for $3.5 million for property acquisition has been applied for through Florida Forever; however, the status of this funding will not be known until January 2002. FISCAL SUMMARY Project Cost Plalming Design Engineering/Permits Acquisition Relocation & Mgt. Land Acquisition - Appraised Relocation Construction Reserve TOTAL PROJECT COST Funding from Others Secured SWFWMD (Contract Pending) U nseeured State Total Other Funding City Share Stormwater Utility Total City Funding TOTAL PROJECT FUNDING Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete 6 I I I $ 500,000 $ 2,688,000 $ 4,500,000 $ 2,500,000 $ 2,500,000 $ 4,000,000 I I $16.688.000 I 18% I $ 500,000 l,2,500,000 $ 3,000,000 I 82% $13,688,000 I $13,688,000 $16,688.000 I $16,688,000 $ 0 $16,688.000 I I I I I Kapok Flood Resolution Project I ,. ~. \ IS 1':,r",.'c,'1 If., ~ '( " . ! "- ~ s', ;"-"<i> >} ~ DUNEDIN <{ -0: (3 iE I- ;:: UNION ST. S.R. 580 \ \, I, I 'J'~ CIJRLEW RD N.T.a. ,- I :.] r';r-~ ii &-j (> 7." :::; . ~ ~~,~ J i.~' '" I f o --' w <Il vi ::J I '/j"'l 01 L{) L{) cr' <Ii /? ',.. ) I- a o CD z ':l ~ SAFElY HARBOR ::!' <> ::!' OINT RD. MAl -'I ..j .Jl...w. I " ,~ '\ , I -r~ ) ~= v'- ,i,_ (~~~~-' "r':':;,,~~" 'G" I r' )/'fj~ ,/ ,./ N ;// ~-j'/ j I "'n i ,I (j \, /~ ) (i; ,@~/ ; :&.: I ,e>. / BI:LLEAlR ;' ."~'{9'll) / '-------.) ./ I~J I I LARGO { o -" OU ~t 1r--7 ~"]~ '-~y__,LC -tll~~~'.....,......, 3l~ I I I I I I I I I 7 PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Town Pond Terry Finch City of Clearwater Coastal Zone 1 Commission (KIO) 11 Problem Priority 1.00 CIP - Joint, Design Water Quality Improvement, Flooding Description: The Town Pond project is an integral part of the plan to invigorate the downtown area and promote development. The downtown area was developed with little or no landscaping, with significant asphalt and impervious surfaces and no provision for flood protection or stormwater quality treatment. As a result the area is subject to frequent flooding and the exisitng two acre pond, which persists with nuisance vegetation, is aesthetically unpleasant and generally poor water quality. The project is for the constlUction of a 4 acre stormwater treatment pond and park amenity in downtown Clearwater to reduce existing flooding problems and provide stormwater treatment to protect the water quality of Clearwater Harbor, an Outstanding Florida Waterbody. During the development of the project and other downtown redevelopment it was determined that significant improvements to the storm system in Myrtle A venue would also be required to meet the desired level of service for flood protection not only in the vicinity of the Town Pond but also along Myrtle Avenue ConstlUction of this facility will also promote a 'stormwater buy-in district' within which development and, or redevelopment projects can make a payment in-lieu-of for City and State stormwater treatment requirements. The improved site will incorporate landscape architecture amenities to create a pleasant environmental setting in downtown ClearwateL Objectives: 1 Provide water quality treatment for the Downtown Stormwater Service District prior to discharge to Clearwater Harbor. 2. Reduce localized flooding. 3. Redevelopment incentive. STATUS I I I I I I FY 2001: 7/01 - Commission approved the Agreement with FDEP for funding through the Water Advisory Panel in the amount of $400,000. FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction Reserve TOTAL PROJECT COST Funding from Others Secured FDEP - Surface Water Grant State - SWFWMD Federal Appropriation I $ 20,000 $ 610,000 $ 2,700,000 $ 7,700,000 $ 2,000,000 I I $13.030,000 I 49% $ 400,000 $ 3,105,000 $ 1,295,000 I I Unsecured Economic Development Land Sale $ 600,000 "Buy-In" Storm $ 1,000,000 Total Other Funding $ 6,400,000 City Share Pem1Y for Pinellas Stormwater Utility Total City Funding TOTAL PROJECT FUNDING Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete 8 I 51% $ 1,500,000 $ 5.130,000 $ 6,630,000 I I $13.030.000 $13,030,000 $ 1,376,809 $11.653.191 I I I I I I I I I I I I I I I I I I I 1\ I I I Town Pond t 1 "'.. } "i; IU.S. ""4- 1/)1 ~I I, ~~, {,\ I 'ii' \' '. , i' i' ,I \ ,~ f << o '" f--- <( UNION 51.. ~ DUNEDIJI .At"'*"> LARGO RD,i en U ..J W en ui :::J S.R. 580 f- a a en 2 ':':i ::i 9Ai'ETY HARBOR ::E " :::!' MAIN ST._ I / ~L~J e-----', r;==;;-/ "r L, i) "1 ,1-.",L vi :B"'f 9 PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Sharkey Road Drainage Improvement Project Brian Barker City of Clearwater Alligator Creek Commission (KID) 10 Problem Priority 1.06 CIP - City, Design Structure Flooding, Bridge Flooding Description: The Sharkey Road Drainage Improvement Project will consist of the replacement of the undersized culvert crossing at the corner of Sharkey Road and Oberlin Drive and the reconstruction of the channel to the north of the culvert. This project is reconm1ended in the Alligator Creek Watershed Management Plan (June 1997). While this project will reduce the frequency of flooding, implementation of downstream improvements will still be required to meet drainage level of service in College Hill and Rolling Heights. Objectives: 1. To alleviate the flooding of houses along Oberlin Drive. 2. To eliminate the overtopping of Sharkey Road due to the existing undersized culverts. I I I I I STATUS FY 2001: The Sharkey Road Drainage Improvement Project is cunently under design. The next step is Commission approval to fund project construction.. I I FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction I $900,000 I TOTAL PROJECT COST $900.000 I Funding from Others Secured (0%) lJ nsecured I Total Other Funding $0 I I City Share Stormwater Utility (100%) $900,000 Total City Funding $900,000 TOTAL PROJECT FUNDING $900,000 I I Requirements Total Project Cost Expended Tlu'ough 09/30/00 Needed to Complete $900,000 $ 0 $900,000 I I I 10 I I I Sharkey Road Drainage Improvements I '&r4 ()I , I ~,~.) / /." I ~ I" \ \, ~ '.. 'r'.'.._,_ I r. ;" I J ~ I 1i'> s,. -- f >}.'il w J ~ IJ1Jl!ElllN <{ (3 iY t- ~ UNION ST. S.R. 580 I RD t ','\, I., ' I' .:;\'11:- i J } "\. ,fl~ '.~ r :::J' /-.' -..J " w I U -' w <0 ~ en ::i N.T.S. ,'l , u I I I ok. - I' ..~, I~_:J ~'-~~;> \- ,.~ '\'" "'.:;.~) 'If \', i ) !i ,/Yi~ ~ o o ro z w -' 5 SAFETY HARBOR ::z " ::l' ( I ,1' / I ..4t=i<>> MAIN ST, < ",J f' /'j Rf/ ,;1'1' !,;.A! ~.J' ) / '('-. .-:tt/C /' ( .,/ I I /f I: , i /J A'= (20/ , ;0 I ,Jx;o29 I '7--.) LARGO ( '/ ~ 0/& ~~. (r-7' ,'r' -:!/(, '~-----"\~"'-" $""1 x".,h". I, I I I I I I I I 11 PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Alligator Creek Drainage Improvements Terry Finch City of Clearwater Alligator Creek Commission (KID) 9,4 Priority 1.20, 1.22-1.26, 6.05 CIP - City, Project Development Structure Flooding Description: The next phase of improvements in Alligator Creek following the implementation of the Kapok project includes, clearing and snagging Chamlel A between Belcher Road and N.E. Coachman Road, and widening the channel between N.E. Coachman Road and, U.S. 19, the installation four parallel box culverts under U.S. 19, the installation of larger box culverts at the entrance road to the Solid Waste Transfer Station and the construction of an off-line treatment pond.. The Alligator Creek Watershed Management Plan includes the replacement of the Old Coachman Road and N.E. Coachman Road bridge spans, and the widening of Channel A between U.S. 19 and Cliff Stephens Park which would require coordination and participation by Pinellas County In order to fully implement improvements in this area. These improvements would assist in resolving flooding problems in the reach of Channel A from Belcher Road to U.S. 19; and in Channel] and H which are directly related to tail water conditions in Channel A. The problem is defined by a set of road crossings that fail to meet the 25- year flooding level of service, in addition to isolated instances of structural flooding during the 100- year design storm event. Objectives: Reduce flooding in this reach of Alligator Creek. I I I I STATUS I FY 2001 : I No Activity FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction I $ 663,607 I $3,760,437 TOTAL PROJECT COST $4.424.044 I Funding from Others Secured 0% I Unsecured Total Other Funding $0 I City Share Stormwater Utility 100% $4,424,044 I Total City Funding $4,424,044 TOTAL PROJECT FUNDING I $4,424.044 Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete I $4,424,044 $ 0 $4.424.044 I ,I I I 12 I I I Alligator Creek Drainage Improvements S.R, 580 I t I I , .a ( 'io.1 " ' I ~"" ." }~I,;,' J "~I, I" \:\ ;,", , u ,J .} tli; ~ vi :::J I if.T,S, ~ F!: o o al Z ':l -' :::J SAFETY HARBOR :::> <) ~ 1< I '!fulf ml J I i I I If .<<~ I ~ I I I ! -I "~':"" I c~ ~,'(i :"-c, ~~.- ~. _;;, ,~~_~' b' I I I /?/ /i~ /tf! j gYB) ~-_J I MAIN S /) l,~V/' "'j'tr j,~~~J <<..{d.J ] ".Q> [,/""1~ i , ) " I S,R. I ) "J~~I ;I l(~ / /~,/) C./ '. I I I I I I I _i<;i;~" ~ _~~~~~1~-Y-; ~...':l.~ -~~'t':]lM"~.-;jt~ rs: '_ .- --'m:-m~'J I I 13 PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Stevenson Creek Implementation Phase I Elliot Shoberg City of Clearwater Stevenson Creek Commission (Kia) 9 Problem Priority 1.02, 1.08, 1.12 CIP - Joint, Project Development Structure Flooding, Water Quality/Environmental Description: The Stevenson Creek Watershed Management Plan (WMP) identifies causes and sources of problems such as flooding, water quality degradation, excessive channel erosion, and loss of habitat. Once problems are identified, recommendations are made to alleviate the problems. The WMP focused on floodplain Level of Service (FPLOS) deficiencies with water quality, habitat restoration and erosion protection incorporated where feasible. The recommendations include capital improvement projects, creation and restoration of habitat, maintenance and operational strategies and pollution reduction programs. These projects and programs reflect the goals of the City Comprehensive Plan. Full implementation of WMP projects will result in the removal of 243 of the identified 334 structures from the 100 year flood plain. Many (28) of the remaining deficiencies are located within the coastal high hazard area of Lower Stevenson Creek and will remain susceptible to flooding from storm surge. In addition the combined projects would remove FPLOS deficiencies at 33 locations on residential streets, 16 locations on collector roads, and on one arterial road. Objectives: 1. To resolve problems identified in the watershed management plan and provide flood protection, water quality improvement, environmental protection and enhanced maintenance and operational controls, I I I I I STATUS I FY 2001: The City approved interlocal agreements with SWFWMD and FDEP in June and July of 2001. The WMP was completed in August 2001. The City is proceeding to project implementation with the understanding that details of the specific projects would retum to the Commission before implementation begins. I I FISCAL SUMMARY (FY 2002) Project Cost Planning Design Engineering/Permits Land Acquisition Construction I $ 600,000 $ 700,000 $4,790,500 I TOTAL PROJECT COST $6.090.500 Funding from Others 55% Secured SWFWMD $ 970,000 FDEP ~ Water Resource Grant $ 1,500,00 Unsecured SWFWMD $ 925,000 Total Other Funding $3,395,000 City Share 45% Stormwater Utility $2,695,500 Total City Funding $2,695,500 TOTAL PROJECT FUNDING $6,090,500 I I I I I Req u i rements Total Project Cost Expended Tlu'ough 09/30/00 Needed to Complete I $ 6,090500 $ 155,878 $5,934,622 I I 14 I I I Stevenson Creek Implementation Phase 1 I ,l of 1 i S,R. :>aD '\ f'= o o OJ I N.I.S, I ~ : ~, !,~,!;. !! <, . "'1 I '&4 ) '~II i 'll i I vr I I I I ..Jl~ i) II :~ 17 1~. ~1!fi~ '" - . ... ~ :' I J .' / ;' " ~ if) if) r:' () as g SDR'I'Y EIARBOR ~ ". I I '" vi MAIN S I J!y/I ..: ~~;' ~,: I~f ./ .t'~-, .~. f't Y' , i I Ii 1/ IF' /[~/ -~-'~D / .C-.. :i"'f i / I ~i~ 'I~> , ' "',..,.........~~-II ~"'I'~" '~ t I I I I I I I I I 15 Description: The Morningside/Meadows Drainage Improvement Project will address home and street flooding in these two subdivisions. Houses of major concern are located on Flushing A venue, G lenmore Court, Charles Drive and Chinaberry Road, Summerlin Drive and Moreland Drive. The proposed project will include the extension of the stormwater collection system, removal and replacement of the existing stormwater system and the regrading of swales between homes. PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Objectives: 1 . Alleviate house and street flooding. Morningside - Meadows Drainage Improvements AI Carrier City of Clearwater Aligator Creek Commission (KIO) 9 Problem Priority 1.04 CIP - City, Project Development Structure Flooding, Street Flooding I I I I I STATUS FY 2001: I No Action FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction I $575,000 I I TOTAL PROJECT COST $575,000 Funding from Others Secured 0% I Unsecured Total Other Funding I $0 City Share Stormwater Utility 100% $575,000 I I I Total City Funding $575,000 TOTAL FUNDING BALANCE $575.000 Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete $575,000 $ 0 $575.000 I I I I 16 I I I N.T.S. Momingside-Meadows I' ~~, ,'I. ( 1~\i;\), I . . , I" i \, '.J I : I S.R. 580 I CURLEW RD. I t "" '" OJ W C vi c;:j :::> m I DUNEDm J: f- a o [!) <;; '&4 Of <l: [) iE t- ~ UNION ST. If) If) Ii vi z W -.J ::l SAFE.TI H.i.RBOR :2 " :2 ,1 " UNSET OINT RD. , {' _MAIN~'., ..~J I .Ai_ (J) 1 )~!?/ "",~(~'/f /' . (7-.........J,. ..-l..... /~..- ~?,/ i i -I: ~1, I I' i: a <( o "" <Ii ::i DREW STREET I , ) . I' (I i i Ii / ,I I ' / ...J '= /g.7/ 11''':;:>" h~~i'-'29 - ~ /) / i'fJ~i I 1(~ / '/7( Iv) J I A ,/ :BELLEAIR i o 2: <( -.J r S2 J: BELL / I ,L:::J (/)/.J. ~ -' 1I---7 -. ~ If"': - -'" l../<-J ~ ""..... ". ii<>r I LARGO -.J W IT) I I I I I I I I I 17 PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: I I Tropic Hills Drainage Improvements AI Carrier City of Clearwater Coastal Zone #2 Commission (KIO) 8 Problem Priority 1.03 CIP - City, Project Development Structure Flooding, Street Flooding Description: The Tropic Hills Drainage Improvements project is located south of Gulf to Bay Boulevard and to the west of U.S. 19 in the Tropic Hills residential neighborhood. The proposed project will include the extension of the stormwater collection system, removal and replacement of the existing stormwater system and the design of the outfall under U.S. 19. Objectives: I. Alleviate house flooding for homes on the south end of the subdivision. 2. Reduce street flooding throughout the subdivision. I I I STATUS FY 2001 : I I I I No Action FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction $550,000 TOTAL PROJECT COST $550.000 Funding from Others Secured 0% I I Unsecured Total Other Funding $0 City Share Stormwater Utility 100% $550,000 I I I Total City Funding $550,000 TOTAL PROJECT FUNDING $550.000 Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete $550,000 $ 0 $550.000 I I I I 18 I I I Tropic Hills I I S.R. 580 ~uIf (If .fL' ~\ ; !~5:j Ii ' I, I ---=r:-o I t ~ ~ N.T.S. u -' w <Il vi :;) ~ DlJIII:Dlli I ,'. ." I <( U 6" c- o<( UNION Sf. "" "" <>' vi 9 ::j SAP'ETY RiROOR ::> " :::> ~J w j> ,/ -< NSET OINT RD. I "u<<Cie<> I l ! --1~ I';:-=-, ~' ;==co. " '- ..., - -, 'I ~ , .b ',"" ':J o <( o a:: ~ vi ::i DREW STREET I , , ,/'/ .,/ ,/ "~ ,J,' , (i''5;1I / {~it~?i:~:i '~~ / j(~ '(I' ',' ,J .'ii<>y' I LARGO ,.._3 ~ (t ~~._----.... ~/' / '1 I I I I I I I I I 19 PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: I I Allen's Creek Neighborhood Flooding AI Carrier City of Clearwater Allen's Creek Commission (KIO) 8 Problem Priority 1.19 CIP - City, Project Development Structure Flooding, Street Flooding Description: The Allen's Creek Neighborhood Flooding project is the residential neighborhood located north of the Allen's Creek Rehabilitation Project and to the east of Hercules Avenue and includes Rebecca Drive, Sandra Drive, Lees Court, Burnice Drive and Canterbury Road. This project is intended to reduce house, street and yard flooding due to inadequate stormwater conveyance. The proposed project will include the extension of the stormwater collection system, removal and replacement of the existing stormwater system and the regrading of swales between homes. Objectives: 1. Alleviate house and street flooding. I I I STATUS FY 2001 : I No Action FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction I $600,000 I I TOTAL PROJECT COST $600,000 Funding from Others Secured 0% I I Unsecured Total Other Funding $0 City Share Stormwater Utility 100% $600,000 I I Total City Funding $600,000 TOTAL PROJECT FUNDING $600,000 Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete I $600,000 $ 0 $600.000 I I I I 20 I I I ABen's Creek Neighborhood I RD I t N.T.S. I ~!, :c, I ,~,' \ lf11~':.'",1'1 Ii . c, )>1 II I I I I I I '&4 01 I .M...-. I ~,i~-'-c'" ~&"~ ."", I I~~/ i J(~ / I /1 // /' / ,'-:~~~7' / ';~~7(/151 J 2:~-:-3-d' (.r l ,; I I I I I I I I I '1 ,FJf~:! :>; . ':, C ::, ~ ,':i' f I " <>\. i st ; '" S' ! "t-i:>1 DUlfEDIN si O{ ~ ~ UNION ST. ~ u G:I en I~ S.R. 580 't, i'= o o en z LU g SAFETY EiARBOR ::> u ::! ", "'1 "' '" a:: <Ii \ . .. ) NSET OINT RD. MAIN ST. -\ ~ <( 1~,17' .,~~~:t~</ ~ a "" o '" ui ::i DREW STR EET ~.~;/ , '. ' 1~/ [/iv / .! a:: 8ELLEAIR RD. LU ( I ;~ dJU ~, 'j-----::-" ""~"- ~ .1---------..., '\, :xl"'f LARGO -' 4J <D 21 I I I I I I I STREET FLOODING PROJECTS I I Project Commission Project Cost Priority 14 $2,315,001 8 $5,814,000 8 $470,000 TOTAL $8.599.001 'I I North Greenwood Corridor Enhancement Project Stormpipe System Replacement Projects North Beach Drainage Improvements I I I I I Project Commission Priority Project Cost City-Wide Aerial Photography* * No Description Provided for Projects Less Than $100,000 5 $22,000 I I I 22 N. Greenwood Corridor Stormwater Enhancement Project Bob Maran City of Clearwater Stevenson Creek Commission (KIO) 14 Problem Priority 2.02 CIP - Joint, Design Street Flooding PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Description: The City of Clearwater will begin improvements along North Greenwood A venue corridor from just south of Palmetto Street north to Fairmont Street. In conjunction with this project, the City intends to upgrade the main collector pipes running under North Greenwood A venue and relocate them from under the planned roundabout. This corridor project will be a timely opportunity to replace older pipes from under the proposed improvements to a more strategic location for future repair as may be needed. Objectives: 1. Improve the City storm system. 2. Protect the new streetscape from pipe collapse below proposed improvements 3. Alleviate street flooding with larger capacity drain pipes. I I STATUS I I I I I FY 2001: The North Greenwood Corridor Enhancement project is designed and' on schedule for construction in November. A change order in the amount of $225,000 for stormwater drainage improvements will require Commission approval. I I FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction $2.315.001 TOTAL PROJECT COST $2.315.001 Funding from Others (18%) Secured SWFWMD $ 425.000 Unsecured Total Other Funding $ 425,000 City Share (82%) Road Millage $ 240,000 Water/Sewer $ 425,000 Penny for Pinellas $1,000,001 Stormwater Utility $ 225.000 Total City Funding $1,890,001 TOTAL PROJECT FUNDING $2.315.001 Requirements Total Project Cost $2,315,001 Less Other City Funding $2,090,001 Expended Through 09/30/00 $ 0 Needed to Complete $ 225.000 23 I I I I I I I I I I I I North Greenwood Corridor Enhancements ,~ /;1 RD S_R_ 580 \ I t ;2: I IU.S. w [lJ vi :::i I DUN\lDlII o o <Xl I '&ulI 8)1 '" '" o! o ') )( u r5 --' :5 SAY1m' HARBOR ~ ~ RD_ I I I \ ! \ ) / I' // // // G II3fJ ::~~)fl ui ::J I \h.J fJU ~:~:;> -o' ~I../_~ "Tf'''''-..., :.e~ UROO I I "1~' .. 4" I I I I I I I 24 PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Storm Pipe System Replacement Projects Bob Maran City of Clearwater City-wide Commission (KID) 8 Problem Priority 2.00 CIP - City, Project Development Street Flooding Description: The Public Services Department compiles a list of temporary repairs made throughout the City-wide storm pipe system, providing this information to Engineering. The locations where temporary repairs were made are evaluated by Engineering and, where necessary, permanent upgrade and replacement locations are placed on the annual storm pipe replacement contract. All projects are reviewed by the Capital Improvement Stormwater Management Committee for consistency with appropriate watershed management plans and prioritized by the Conm1ittee. Emergency projects are given the highest priority. Objectives: 1. Either slip-line or replace corrugated metal pipe with reinforced concrete pIpe. ") .... Eliminate road base erosion and subsequent road subsidence. 3. Reduce sedimentation load to storm pipes and ultimate receiving waterbody. FY 2001: The City Commission approved the Ammal Stormpipe Replacement Project for FYOl in March 2001. Three of four contract areas have been completed. Replaced 132 ft. of 54-inch pipe along Druid Road west of Missouri Avenue. Also replaced 1900 ft. of up to 18-inch diameter pipe at Olenwood A venuelDruid Road and Powderhom Drive/Huntington Lane. An additional 600 ft. of 18-inch diameter pipe will begin in the fall at Pinebrook and Admiral Woodson Lane. STATUS FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction TOTAL PROJECT COST Funding from Others Secured Unsecured Total Other Funding City Share Stormwater Utility Payments in-Lieu-of Retention Total City Funding I I I I I I I I I I I $5,814,000 $5.814.000 I 0% I $0 I 100% $5,730,000 $ 84,000 I $5,814,000 I TOTAL PROJECT FUNDING $5,814.000 Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete 25 $5,814,000 $ 0 15-.>SI4,000 I I I I I Storm Pipe System Replacement I ~,: (',~ .1;\ " , ,1 "," . I': . \-- 1\ \ 'I : 'I I ! I I Jl...- I'", i ~' I ) --/._' ~~5~~) \', ..i:l \" :.. ,I ;i/.)'fj~j I" /" ji ~, 'I' ,~)) ( I') ~~t ~'~~0 .:::;-.:..:-, S.R. 580 I t -".1"-. CURLEW RD. I Ol RT.S. .f "" 0:: W I U --' W OJ vi => I ';!,4 0/ H"l lD '" vi " _I( I;' iE o o m z ~ :5 SAFETY HARBOR ":!' <> ~ I N '3) C" j' I I I LARGO ! ,I ~ lJU r;-.lo.{ (,::->, ,r~"'l:- " \/'~ "', " !.B"'j- I I I I I I I I I 26 PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: North Beach Drainage Improvements AI Carrier City of Clearwater Clearwater Beach Island Commission (KIO) 8 Problem Priority 2.10 CIP - City, Design Street Flooding Description: The North Beach Drainge Improvements Project will provide improvements at various locations in the north end of the island. The work will include the installation of storm grate inlets and removal and repair of the existing collection and outfall system. Objectives: 1. Alleviate street flooding standing water in street. 2. Repair the eXlstmg stormwater collection system. 3. Repair street end outfalls. I I I I I STATUS FY 2001: In-house survey has been completed and project design has begun. Estimated construction to commence prior to January 2002. I I FISCAL SUMMARY Project Cost Planning Design Engineering/Permits Land Acquisition Construction I I $470,000 TOTAL PROJECT COST I I $470,000 Funding from Others Secured 0% Unsecured Total Other Funding I I I I $0 City Share Stormwater Utility 100% $470,000 Total City Funding $470,000 TOTAL PROJECT FUNDING $470,000 Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete $470,000 $ 0 $470,000 I I I 27 I I I North Beach Drainage S.R. 580 l, I t ). ri' II ~" }'. /i):,:::~ .U .'.f\~. I I I . ~~. ,\ i-Z~ '. :) 1"" \ ~~ \) \1." 1(' ,', 1\, '';) I . , JJ=.~ .]- "i; :r: () -' W m ~ vi :::J N.T.S. "" ~ I '&"'1 OJ 31. () o ~ "( ~ SAFETY HARBOR ~ ~/' :;;; II c. o <( o '" 2: uj ::J DREW STREET I .J , ,.'-~~j QJ?/ 1 /'" 'I /;', I .5 ,.,,-".1 ~J \ /"7~, /I "'\-~7'/" ,{~ I PROJECT LOCA TIONS .. I <:l) I " ''\ I' vf '\.'1 ( ;::" 'i"k J:>! MAIN ST I I CI z 5 SS :r: a:: BEUEAIR RD.W / ,/ 1 Ikd fJU C;-~f u7 I .,' ':v~lf1FJ'~'-'"", "'. ~"f I I LARGO -' w !1J I I I I I ~r ~ ;,-- ~ I I I 28 I I I I I I I I I I I I I I I I I I I REGULATORY COMPLIANCE PROJECTS Project Commission Priority Project Cost FDEP Compliance Project 5 $1,008,000 TOTAL: $1.008.000 Project Commission Priority Project Cost NPDES* 5 $44,000 * No Description Provided for Projects Less Than $100,000 29 PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: STATUS I I I I I I I I I I I I I I I I I I I FDEP Compliance Terry Finch City of Clearwater Not Specific Commission (KIO) 5 Problem Priority 3.00 P&S - City, Plan Conception Regulatory Compliance, Water Quality Improvement Description: This project provides for the funding of water quality enhancement projects as required to satisfy a consent order with the Florida Department of Environmental Protection. The City has currently paid $20,000 to FDEP for costs and expenses toward satisfying the consent order. Several projects have been considered for implementation and submitted to FDEP for review in 1999. To date, however, FDEP has not responded to the submittal. While the original settlement "projects" required the expenditure of $900,000, the actual cost of implementing projects under consideration would be somewhat higher; therefore, total funding in the amount of $1,028,000 is being requested. Objectives: 1. Satisfy FDEP Consent Order. 2. Provide water quality benefits to Clearwater Harbor and Tampa Bay. FY 2001 : No action has been undertaken this year. FISCAL SUMMARY Project Cost Planning $ Design Engineering/Perrnits $ 151,200 Land Acquisition Construction $ 856.800 TOTAL PROJECT COST $1.008.000 Funding from Others 0% Secured Unsecured Total Other Funding $0 City Share 100% Stormwater Utility $ 1.008.000 Total City Funding $1,008,000 TOTAL PROJECT FUNDING $1.008.000 Requirements Total Project Cost $1,008,000 Expended Through 09/30/00 $ 0 Needed to Complete $1.008.000 30 I I I I I I I ~. I I I I I I I I I I I I FDEP Compliance ~~...,~ (.~ . .." .-. -., O.""'~t"'::"':'U ..~..- .,*, <~~.,.... ~: ~~!r- 31 32 I I I I I I I I I I I I I I I I I I I BRIDGE FLOODING PROJECTS Project Commission Project Cost Priority None I I I I I I I I I I I I I I I I I I I MAJOR EROSION PROJECTS Project Commission Priority Allen's Creek Gabion Project 9 TOTAL: 33 Project Cost $681,779 $681.779 PRO.lECT NAME: PRO.lECT MANAGER: LEAD AGENCY: BASI N: PRO.lECT PRIORITY: PRO.lECT STATUS: PRO.lECT PURPOSE: STATUS I I I I I I I I I I I I I I I I I I I Allen's Creek Gabion Project AI Carrier City of Clearwater Allen's Creek Commission (KIO) 9 Problem Priority 5.00 CIP - City, Construction Major Erosion, Bridge Flooding Description: The ongoing Allen's Creek Gabion project is located north of Gulf to Bay Blvd. and south of Cleveland St. at Rainbow Dr. This project is necessitated by increased flow rates in the Allen's Creek channel caused by expansion of the stormwater system on Cleveland St. The project consists of channel realignment and sidebank stabilization utilizing the construction of gab ion baskets and gabion mattresses. The project also includes the replacement of an existing 72 inch corrugated metal pipe with a 7 foot by 20 foot ConSpan bridge structure at Rainbow Dr. Due to the nature of the project x homes will be removed from the 100 year floodplain. Objectives: 1. To eliminate the ongoing erosion that has caused portions of the creek owned by the City from encroaching into private property. 2. To alleviate roadway overtopping at Rainbow Dr. FY 2001 : The Commission approved award of construction in May 2001. Construction is presently underway. FISCAL SUMMARY Project Cost Planning Design EngineeringlPerrnits Land Acquisition Construction $ 16,550 $ 665.229 TOTAL PROJECT COST $ 681.779 Funding from Others Secured 0% Unsecured Total Other Funding $0 City Share Stormwater Utility 100% $ 681.779 Total City Funding $ 681,779 TOTAL FUNDING BALANCE $ 681.779 Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete $ 681,779 $ 14.950 $ 666.829 34 I I I I I I I I I I I I I I I I I I I ------------- AUens Creek Gabion Proj ect RD t j/"'f ~ () --' w !Xl iii ::J N. T.S. ~" '" I ' \ :1"'1 ,:,", 'I ~~ '; """. S.R. '580 s" ~"'" . -,I, I'!d DUNEDIN <( -<: l5 g: ;i Ur-.ION ST. I f- o o rn .z w -J :j SME'IT HARl30R tj ~ ~ "' LI) ri vi '&ulI OJ ~ NSET OINT RD. IAAIN .I" ,c.-j ;:' .l:~~f d-"' .I ~f-- _. , , i t-,-' ~~', \;-" ~"----' " - ... vi ::i DREW STREET Q <( o fr: / r~ ~~'" ~/ i/'P',," / /r ,II ,," / I .l.~, 1<'-- /~~0~J) )'1S~j p' Xcn-6- 1/1) { (J/d. LARGO 35 Commission Project Cost Priority 12 $7,000,000 12 $2,216,000 7 $330,779 TOTAL: $9.546.779 I I I I I I I I I I I I I I I I I I I WATER QUALITY & ENVIRONMENTAL PROJECTS Project Stevenson Creek Estuary Restoration Project Alligator Creek Implementation Projects North Greenwood Stormwater Retrofit Project Project Commission Priority Coopers Point Restoration & Management Project* 7 * No Description Provided for Projects Less Than $100,000 36 Project Cost $92,000 PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: I I Stevenson Creek Estuary Restoration Elliot Shoberg United States Army Corp of Engineers Stevenson Creek Commission (KIO) 12 Problem Priority 6.00 P&S - Joint, Scope and Participation Criteria Water Qualityl Estuary Restoration Description: The Stevenson Creek Estuary discharges to Clearwater Harbor at the intersection of Ft. Harrison Street and Sunset Point Road. The Estuary Restoration Project was prompted by response to community concerns to reclaimed water expansion in the North Greenwood community. Through the Brownfields Environmental Justice plan, the community requested this project to have primary importance. The dredging will focus on accumulations of material and restoration of the estuary. Approximately 80,000 cubic yards of muck deposits, primarily located between the Fort Harrison Avenue Bridge and the Pinellas Trail Bridge, will be dredged to help improve water clarity and improve the habitat. 10,000 cubic yards of material will be dredged to open up restricted tidal flows at the Fort Harrison A venue Bridge. Without the project, the Stevenson Creek designated Outstanding Florida Waters (Chapter 17-3.041, F.A.C.) and Class III waters would probably continue to degrade in environmental quality. Odors from the area would continue to be baneful and aesthetics could decrease. Objectives: 1. Reduce odors associated with the organic muck, improve area aesthetics, restore dissolved oxygen levels and help reestablish the estuary tidal flow 2. Preserve the natural estuary. 3. Sea grass and mangroves will be planted in the Estuary. 4. The USACOE Environmental Restoration Report to demonstrate Federal Project Justification. Without Federal Justification, this project is underfunded by $4,550,000. STATUS I I I I I I FY 2001: The USACOE completed the Preliminary Restoration Plan (PRP) in October 2001. The USACOE is conducting a feasability study for the Stevenson Creek Estuary Restoration with an expected completion date of April 2002. The next step will be to bring a Project Cooperative Agreement (PCA) between the USACOE and the City of Clearwater to the Commission for approval. The City has applied for federal funding support to the United States Congress for $4,550,000 in FFY02. FISCAL SUMMARY Project Cost Planning Design Engineering/Perrnits Land Acquisition Construction TOTAL PROJECT COST Funding from Others Secured Unsecured USACOE Total Other Funding City Share Stormwater Utility Total City Funding TOTAL PROJECT FUNDING Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete 37 $ 552,118 $ 646,208 $ 1,270,000 $ 4,531.674 I I I $7.000.000 I I I I I I I I 29% $2,000,000 $2,000,000 71% $5,000,000 $5,000,000 $7.000.000 $7,000,000 $ 0 $7.000000 I I Stevenson Creek Estuary Restoration I I / 3(~ / c~.( UI ,; ) IJEIJEAIR ( [, I.' /~J (./ I t ,1\., 'j / ,;~,\II N,T,B, '~j I '&uIf (JI ~ ~I (~~,.~, "\ 11\' ';'. ,II, 'I,) '[1, I, '"j I ! I i , ~ :1 ~l -u ~~~.~ ) , I I J I ~ I SAl'ETY HARBOR , ) I I MAIN ST. .( /J' f \,,}~~; ",l~,':i) ... - (J ( '-F" i .f c'" i~:i/ If.?) I // /1 I' ! J IE' ,(2:2/ /,1;{Ciccl ....---.-' o ::J RD. \b.J. Ok/. ~ L~ ,{ ..:;~ ~,r-' ~ "" ~"Y I I I I ~~---:~~~:~-~~~-:.::':;:"--:'~~+-;=- -:~~~ -' ; - f I I I I I 38 PLAN NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: Alligator Creek Implementation Projects Terry Finch City of Clearwater Alligator Creek Commission (KIO) 12 Problem Priority 6.04 CIP - Joint, Construction Water Quality Improvement Description: This project IS for the construction of three projects that were recommended for implementation in the Alligator Creek Watershed Management Plan that was developed in cooperation with the Southwest Florida Water Management District, Pinellas County, Safety Harbor and the City of Clearwater. The projects are: 1 . Stabilization of Channel B between SR 590 and Moccasin Lake Park using gabions; 2. Moccasin Lake Park Sediment Sump and Rehydration which includes the construction of a pond and in-line sediment sump to catch sediment and trash and treat stormwater before it discharges into the park. 3. Cliff Stephens Park Dredging and Sediment Sump which includes dredging of the westernmost pond in Cliff Stephens Park and the construction of a sediment sump to catch sediments before they reach the lake proper. The projects are cooperatively funded by Clearwater, Pinellas County, the Southwest Florida Water Management District, Florida Department of Environmental Protection and the Tampa Bay Estuary Program Objectives: Eliminate erosion in Charmel B upstream of Moccasin Lake Park; catch sediments for removal before entering the park and rehydrate the park by restoring flow to historic channels; capture sediment from upstream for removal in an area of Cliff Stephens Park that is accessible and can be maintained regularly. STATUS I I I I I I FY 2001: In May 2001 the Commission approved a second amendment with the SWFWMD and others for implementation of the watershed management plan for Alligator Creek Watershed, providing for a time extension to July 2002 and reallocating funding. FISCAL SUMMARY Project Cost Plalming Design Engineering/Permits Land Acquisition Construction TOTAL PROJECT COST Funding from Others Secured State (SWFWMD) County Safety Harbor FDEP TBEP Unsecured Total Other Funding City Share Stormwater Utility Total City Funding TOTAL PROJECT FUNDING Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete 39 I I $ 456,500 $ 254,500 I $1,505,000 I $2.216.000 52% I $ 596,158 $ 255,196 $ 10,675 $ 242,000 $ 37,500 I $1 141.529 I I 48% $1,074,471 $1.074.471 $2.216.000 I $2,216,000 $ 662,637 $1 553.363 I I I I AHigator Creek Implementation ~ I I I \~~~ CURLEW ;--- '. r;f~ I:'~j /Ui c;:s '/1--' // ~' ,I U) ~s'\. " ~.;; . ,J 'j; DUNEDlN :) <{ <{ [j ~ <( UNION ST. I t J } "" N.T.S. I ~ 'I i";", \iR I. . 'I~ ]i ' 1\ 1'1 I , I / Ii ; ~ I '&4 ff}! LARGO I .JJ~ 'j) 1".( I 11_- ~'~'-' \ ,. '\~I. ,\, '..QULF i,! I /'fJ~ x~ l . -'i ',' I ( :<>: / B&LLEAIR -s- ) .' . /1' .'/ / l / / /.-$ Ie:; I ~;~~t~1 Cl I I I I I I I I I I I 40 RD~,_ ! m vi :J S.R. 580 \ il: o o OJ Z w -' :5 SAFE'I"f HARBO R ::;: () :2 ~ vi ::i ! 'L-j fB"'f -' LU en PROJECT NAME: PROJECT MANAGER: LEAD AGENCY: BASIN: PROJECT PRIORITY: PROJECT STATUS: PROJECT PURPOSE: North Greenwood Stormwater Retrofit Elliot Shoberg City of Clearwater Stevenson Creek Commission (KID) 7 Problem Priority 6.02 CIP - Joint, Construction Water Quality Description: The City of Clearwater is installing two Continuous Deflection Separation (CDS) units for treatment of stormwater runoff that is currently discharged to Stevenson Creek. The smaller unit will be installed at Pennsylvania A venue between Grant and Marshall Streets and will not be monitored. The larger of the two units will be monitored for an eight-month period and will be installed at Missouri A venue and Palmetto Street. The monitoring will include analyzing pollutant removal efficiency of the unit and characterization of the material collected in the sump. CDS devices are designed to function as gross pollutant traps to capture debris and other floatables, coarse sediment and sediment-bound pollutants. The CDS technology is designed to divert low flows through the unit and let a portion of the major rainfall events bypass the unit to avoid flooding problems. Heavier solids drop into the containment sump and a perforated separation panel keeps the floatable items from leaving the unit. The materials that collect in the sump do not have to be removed after each storm, only when the sump is full. Objectives: I. To monitor the overall ability of the CDS unit to reduce the stormwater pollutant loading to Stevenson Creek. 2. To evaluate the ability of the CDS unit to capture floatables and coarse solids not typically measured, to ensure cost- effective management in future usc budgeting. 3. To collect rainfall, runoff and flow data from eight (8) statistically significant storm events within a period of eight (8) months of sampling. I I I I I 4. Memorial Causeway Bridge water quality mitigation. I STATUS I FY 2001: This project was approved by the City Commission in March 2000 as a design- build contract. The Commission also approved an amendment to this contract, bringing the total from $258,472 to $330,779, in January 2001. The project is cUlTent1y under construction. The CDS unit at the location of Pennsylvania Ave. and Grant St. has been completed. I I FISCAL SUMMARY (FY 2002) Project Cost Plam1ing Design Engineering/Permits Land Acquisition Construction $330,779 I I TOTAL PROJECT COST I $330.779 Funding from Others Secured SWFWMD Unsecured 30% $100,000 I Total Other Funding I $100,000 City Share Stormwater Utility Total City Funding 70% $230,779 $230,779 I TOTAL PROJECT FUNDING $330,779 I Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete $330,779 $ 35,829 $294.950 I I 41 I I I North Greenwood Stormwater Retrofit Project I IX W I u --' w m ~ o ;:) CURLEW RD. i cl .~ J ,I , I, I I N,T,S. , ;',j~, '1 " I ~ I '&u1{. 01 .Ai"""", I I I 'y;;~ i /./ /: , I I, i/ /L--.J /~~I //{'if;;;~;<! xrwi- / ,-'I I,' I ,j "i / BEll.urn ~ a: BELLE R RD. W LARGO -' ,-" a:l I I I o o m z 1-" -' S S~F[TY ELiIlIlOR 2 o ::;; MAIN ST. 'S l~,:~/ -'/~i , --,' i t'-' ~~ I }tee ,. I I I I !ti<, . ~- . ---1 ..,,/ ---- ",./ ,--- ---- c..--""'" -- ~'>". "'~ ~i~";;. ",/,.~.,,:.. :_::~~~. ." ,-'- -- '. .. - --.-.' 1.- . { $'. . I I I 42 .-- /~ I I I I I I I I I I I I I I I I I Project Storm System Expansion Project OTHER PROJECTS Commission Priority 4 Infrastructure Management System (GIS) {No Description Provided} Project Citywide Aerial Photography* Air Conditioner Replacement* 5 TOTAL: Commission Priority 7.02 N/A * No Description Provided for Projects Less Than $100,000 I I 43 Project Cost $4,000,000 $464,000 $4.464.000 Project Cost $22,000 $14,000 PRO,JECT NAME: PRO,JECT MANAGER: LEAD AGENCY: BASIN: PRO,JECT PRIORITY: PRO,JECT STATUS: PRO,JECT PURPOSE: Storm System Expansion Project Tom Miller City of Clearwater City-Wide Commission (KIO) 4 Problem Priority 7.04 P&S - City, Conduct Study Flood & Water Quality Protection Description: The City of Clearwater has completed watershed management plans in those drainage basins identified by the City Comprehensive plan for implementation. Each watershed plan makes recommendation in the form of project altematives to resolve flooding, water quality and environmental problems. Many of those alternatives include the acquisition of flood prone properties that cannot be adequately protected by structural improvements in a manner that is also cost- effective. In effect, to acquire the property is more cost-effective than to design and build an infrastructure improvement project. Historically, the City has waited to acquire flood prone lands until the public need and the availability of funding to address that need are simultaneously realized. Typically, that would occur in reaction to a significant flooding event. The City has not had the benefit of long range watershed improvement plans to identify flood- prone lands for acquisition as a cost-effective solution to overcome flooding problems. As a result, delays in project implementation, combined with the public's frustration over continuous and unabated flooding has led to more contentious resolve that has included escalated property acquisitioin costs and on occasion, added legal costs to the City and to the public property owner. For example, in 2000, the City acquired two duplexes on Spencer Avenue to overcome a series of serious flooding problems. Settlement costs were $300,000. Had that property been acquired in advance of the recurrent flooding event and subsequent litigation that included attorney fees and damages, acquisition at the appraised value of $158,000 may have been a more realistic settlement cost. Objectives: 1. Inform property owners of flood potential. I I I I I 2. Create a permanent property acquisition fund. I 3. Acquire flood-prone properties where benefit cost warrants that purchase. I STATUS FY 2001: I No activity FISCAL SUMMARY Project Cost Planning Design EngineeringlPerrnits Land Acquisition Construction I $4.000.000 I TOTAL PROJECT COST $4.000.000 I Funding from Others Secured 0% Unsecured I Total Other Funding $0 I I City Share Stormwater Utility 1 00% $4.000.000 Total City Funding $4,000,000 TOTAL PROJECT FUNDING $4.000.000 I Requirements Total Project Cost Expended Through 09/30/00 Needed to Complete $4,000,000 $ 0 $4.000.000 I I I 44 I I I Stormwater System Expansion I 'ti4 iDf ~ ~, Ci~, I : ~ \ I, 1\ ,II I ,I i I !' '1- i ) S.R. 5BO I I t J. .f ~ TF": ~ ,,' . , " ,'.',-.',...o.~ .. .0) ,!,I' - I,H vi c :;:, 1--.' CURLEW RD ~"'" '~ ~ N. r.s. ::!: U -' W III vi ::} I I ~ I I I ~ ~ UNION ST. to Ii) f- a a m z w -' -' ~ SAFETY HARBOR 2 u ::;; DUNEDIN "" vi vi ::i , '-../ )71,~;~/ ' ~ J' (' ..} \1 / '1--\, '.... " ,A;f,,,,' i~,\jl{ /' I I o <( o Q:: DREW STREET SR. 6 !-~~ ~-\r_ $'3'f LARGO Q:: RD.W --' L, ~ 'll~/"_ I I I I I I I 45 I I I I APPENDIX I A I I I I I I I I I I I I I I 46 ------------------- REVIEW AND ApPROVAL PROCESS - STORMWATER CAPITAL PROJECTS PLANS & STUDIES (P & S) City Concept Plan Develop Study Scope City Conducts Study Consultant Study Joint Concept Plan Develop Study Scope & Participation Criteria Consultant Study CAPITAL IMPROVEMENT PROJECTS (CIP) City Project Development City Conducts Designs C()~i~sion . ... App~()ves.. . Consriitant . Selecti~n. for .. Design ... Joint Project Development I I I I APPENDIX I B I I I I I I I I I I I I I I 48 I I I Strate ic Priori Infrastructure Maintenance & Improvements I Human Resources Issues I Economic Development I I Quality of Life I I Public Safety I I I I I I I I I I Strategic Objectives/Measures/Targets Ke Intended Outcomes KIO 1. CIP's need to improve LOS. 2. CIP's directly leverage private investment. 3. CIP's need to elevate aesthetics and enhance natural beau 4. Improve Customer Satisfaction 5. Increase Customer trust confidence in city government 6. Develop employees who have the skills and commitment to deliver uali service to our customers 7. Clearwater will be a regional leader of "industries of the mind" (financial, insurance, real estate of technology driven businesses) 8. Clearwater's downtown will be redeveloped into a branded destination 9. Clearwater will be a premier, family coastal vacation destination in Fla. 10. Clearwater will have valued position as a preferred community for families to live. 11. Clearwater will have successful partnerships that result in a well- educated, well-rounded citize 12. Clearwater has a distinctive presence consistent with its natural beauty. 13. Clearwater offers diverse educational, cultural and recreational opportunities. 14. Clearwater is reco nized as a referred lace to live, work and la . 15. Clearwater is a city free from blight. 16. Clearwater is proactive in its promotion (or support) of community well- being. 17. Clearwater strives for overall effective communications. 18. Clearwater is a city that values diversity. 19. Clearwater provides efficient and effective movement of all types of traffic. 20. Clearwater is proactive in its promotion (or support) of community well- being. 21. Clearwater strives for overall effective communications. 22. Clearwater is a city that values diversity. 23. Clearwater provides efficient and effective movement of all types of traffic. I I I I APPENDIX I C I I I I I I I I' I I I I I I 50 !. STORMWATER UTILITY PROJECT LIST I Priority KIO Class WS Location PROBLEM TOTAL COST 2.02 14 F-2 STC North Greenwood Conidor Stormwater Coordination replacement with Enhancement $225,000 Enhancement Project In conjunction with Town Pond, resolve 17 street LOS defICiencies and remove 18 1.01 13 F-1 CZl Myrtia Ave Drainage Improvement Project structures from 100yr fbod. $11,104,000 OveraU water quaity. sedimentation/erosion. 6.00 12 WQ.l STC Stevenson Oeek Estuary Restoration and fbod protection planning project that wiD $7,000.000 also inckJde dredging. 6.04 12 WQ-l AGC Algator Oeek Implementation Projects (elff Mgator Creek Watershed Plan project with $2,216,000 Steven's Park, Mxassin Lake, Olarlnel B) SWFWMD and Pinel1as County. 1.00 11 F-l CZ 1 Town Pond Commercial property fboding and significant $13,030,000 water quaity improvement project. Significant in-structure fboding and as a resul 1.05 11 F-1 AGC Kapok Fbod ResoUtion Project of previous site devebpment, signifICant $16,688,000 reduction in fbod level of service basin wide. 1.02 Remove 33 structures! 78 dweling units from $2,203,240 10 F-l STC Glen Oaks 100yr fbod 1.06 10 F-l AGC Sharkey Road Drainage Improvement Project Property and Street Fboding, bridge $900,000 overtopping 1.24 10 F-1 AGC Replace Coachman Road Bridge span $354,000 Construct parallel BC from aty Fbod Detention 1.32 10 F-l AGC Faciity to N. Lagoon arola & remove existing $944,000 weir. Construct parallal BC on west side Becher to 1.33 10 F-1 AGC channel A; regrade channel 0 from Sunnydala $448,000 to BeCher. 1.04 9 F.l ALC Momingside Meadows Drainage Improvements Property & Street Fboding. $575,000 (Fushing/ Olinabeny/ Moreland! Summerin) 1.07 9 F-l STC Expansion of Lake Bel'evuelUpper Lake Remove 8 structures/17 dweling units from $1,337.884 Bel'evue CUNerts 100yr fbod Spring Branch Fbod Detention Basin/Spring Remove 21 structures! 21 dweling units from 1.08 9 F.l STC Branch Conveyance Enhancements Upper & 100yr fbod $4,157,360 Lower 1.09 9 F-1 STC Jeffords StlBany Rd Detention Pond Remove 12 structures from 100 yr fbod $1.690.634 1.10 9 F-l STC SI. Thomas DrlBellavue Bl.td Creek Restoration Remove 19 structures from 100 yr fbod $1,801,913 1.11 9 F-l STC Crast Lake Expansion & Duncan AvelTumer St Remove 17 structures from 100 yr fbod $2,376,418 Detention Pond 1.12 9 F-l STC Palmetto SI. Sediment Pump Remove 1 structure from lOOyr fbod $544,546 1.13 9 F-l STC Hilcrest Ave Overlbw Bypass CUlvert Remove 42 structures from 100yr fbod $2.299,109 1.20 9 F-l AGC 4-72' RCP Improvements under US Hwy 19 at Fbod Protection $3,080.270 Mgator Oeek 1.21 9 F-l AGC Widen Olannel A from US Hwy 19 to Glff This project is Pinellas County jurisdiction, but $0 Stephens Park must be addressed in this order. 1.22 9 F-1 AGC Soid Waste Transfer Station Entrance CUlvert $208.302 Replacement Widen Olannel A from Old Coachman to US 1.23 9 F.l AGC Hwy 19 end construct bypass channel to new Fbod and major erosion protection. $247,630 treatment pond. 1.25 9 F-1 AGC Widen, deepen Olannel A from N.E. Coachman $427,614 to Old Coachman I I II I I I I , I I , II I I I I I I I SWUPLKIO-Priority SORTFinal.xls 9/271011 I STORMWATER UTILITY PROJECT LIST I Priority KIO Class WS Location PROBLEM TOTAL COST 1.26 9 F-1 AGC Clear/Snag Channel A Erosion Repair BeCher $102,675 to Old Coachman 1.27 9 F-1 AGC Regrade Channel A from Hercules to Sunshine $96,500 Drive and replace road crossings 1.28 9 F-1 AGC Channel A, replace access road culvert $35,000 1.29 9 F-1 AGC Replace Channel B Office Complax access road $21,000 cufJerts 1.30 9 F-1 AGC Replace S. Lagoon Orela cufJerts in Channel C $92,500 1.31 9 F-1 AGC Replace N. Lagoon Orela CUM3rts in Channel C $482,000 1.34 9 F-1 AGC Replace Sunnydale box culverts $59.000 1.35 9 F-1 AGe Replace Private Drive Culvert in Channel F $33,500 1.36 9 F-1 AGC Replace Campbell Rd. CuM3rts $38,500 1.37 9 F-1 AGC Replace Beville Road Culverts $42,200 1.38 9 F-1 AGC berm for Cameron Apt. Complex pond. In $31,400 1.39 9 F-1 AGC Replace Old Coachman Road CuM3rts $206,700 1.40 9 F-1 AGC Restore Connection between Borrow Pit and $48,300 Moccasin lake 5.00 9 E-1 ALC Allen's Creek Gabion Project Major erosion control project. $681,779 5.01 9 E-1 STC Byram Pond Dredging & Expansion - Spring Water Quaity / Maintenance $831,636 Branch Stabilzation Union St to Byram Pond 5.03 9 E-1 AGC Stag Run Boulevard & Wetherington Road $1,500,000 1.03 8 F-1 CZ2 Tropic HiDs Drainage Improvement Project Property & Street Fboding. $550.000 (Burma) 1.14 8 F-1 STC Flagler Dr/CSX Rairoad North Swale Remove 3 structures from 100yr fbod $737,241 Improvements 1.19 8 F-1 ALC AIIans Creek Neighbort1ood Fboding (Rebecca, House Fboding. $600,000 Burnice, Sandra, Canterbury) lpe !alures Incuoe YVllnawara 'assage, I\lr 2.00 8 F-2 An Pari<, Overlaa, Unwood, Beaumont, Collage HiD $5,814,000 2.01 8 F-2 AGC Pipe faiure $25,000 2.03 8 F-2 STC Overbrook Ave Detention Pond Street Fboding I Water Quaity $1,755,000 2.06 8 F-2 STC Major Street Fboding $400.000 2.07 8 F-2 STC Myrtia AvenuelSeminola Streets NE OullaD Major storm pipe faiure imminent and present $814,000 System system is undersized and under homes. 2.09 8 F-2 ALC 415 North Duncan Undeffiized pipe with major street fboding. $126.000 2.10 8 F-2 BCH North Beach Drainage Improvements Minor Street Fboding $470,000 2.12 8 F-2 BCH 228 Do~hin Point, 286 Windward Passage, 333 $78,000 Island Way 2.13 8 F-2 AGC Mari~ St., off N.E. Coachman InsuffIcient storm sewer system 2.14 8 F-2 STC Frankln Street, Uncoh East to Stevenson Water jumps curbs with undersized pipes. $281,300 Creek & Hilcrest west to Stevenson creek Property fboding. 4.03 8 F-3 CZ 1 1802-1811 Apache Trail $78,000 4.04 8 F-3 CRC 2640 Countryside & Enterprise Road (goW $65,000 course\ 7.05 8 0 CRC Curlaw Creek WMP 0 1.15 7 F-1 STC Turner St Box CuM3rtS Remove 5 structures from 100yr fbod $1.554,761 1.16 7 F-1 STC Woodlawn Terrace Storm Sewer Replacement Remove 4 structures from the 100yr fbod $446,783 I I I II :1 1\ I I I I I I I I I I I SWUPLKIO-Priority SORTFinal.xls 9/271012 \\. I STORMWATER UTILITY PROJECT LIST I 2.05 2.08 502 7 Class WS location PROBLEM F-l STC Palmello SI. Drainage Improvements Remove 2 structres from the 100yr fbod F-l STC Sma!Moood Cir Drainage Improvements Remove 2 structres from the 100yr fbod F-2 STC N Missouri AvelPalmello St Drainage Street Fboding I Water Quaity 1m rovements F-2 STC Saturn Ave Drainage Improvements Street Fboding F-2 STC Cearview lake Street Fboding / Water Quaity E-l STC Upper Stevensons Creek Stabiization Erosion WQ-l STC Betty lane Forested Habitat Preservation Site Water Quaity TOTAL COST I Priority KIO 1.17 7 $735,643 I 1.18 7 $161,283 2.04 7 $486.615 $303.382 $620,000 $1.415,843 I 6.01 7 $1.100,000 6.03 Improve fbatabe and sediment iller control to WQ-l STC North Greenwood Stormwater Retrofrt Stevenson Creek; Memorial Cswy. Bridge Mitigation. 7 WQ-l CZ3 Coopers Point Maintenance 5 C-l STC,AGC FDEP Compiance Permit non-rompiance 5 F-2 All Infrastructure Management System Administration 5 F-2 All aty.Wide Aerial Photography Administration 4 WQ-l STC lake Hobart Outfall Control Structure Water Quaity 4 WQ-l AGC Olannel'A'/Soid Waste Transfer Station Offine water quaity improvements to Olanne Treatment Pond 'A' $330,779 6.02 I 7.03 7.01 7.02 $92.000 $1,008,000 $464,000 $22,000 3.00 I I $14.300 6.05 $357,553 I 6.06 WQ-l BSC Imperial Oak Condominium - drainage ditch at Structure faitJre causing aesthetic probems at rear of property this time. Staff monitoring for erosion. $900,000 7.00 0-1 PSC 2997 Eage Estates Circe East MaJunctioning retention area. $26,000 $4,000,000 I 7.04 4 o All .~-. ,- .._~ iI' ~ ~c".. ,,~ ;'t -;;<:- ~'<' > ~~~",i:2\\l~I.' .;. ,<- ....'_ If, ~ ~~, 1l!, J:..,. ~~,-..;. ...:~ land Acquisition Priority Cost I F-1/Stucture Flooding $70,492,906 p r FY01 Stormwater Bond 0 j FY02 Stormwater Bond e FY03 Stormwater Bond FY04 Stormwater Bond FY05 Stormwater Bond R&R Improvements y F-21Street Flooding $11,884,297 I C-1/Regulatory Compliance $1,008,000 I F-3/Bridge Flooding $143,000 E-1/Major Erosion $4,429,258 I WQ-1/ Water Quality & Environmental $12,010,632 I 0-1/other $4,026,000 I Grand Total $103,994,093 I I I SWUPLKIO-Priority SORTFinal.xls 9/271013 I I I I APPENDIX I D I I I I I I I I I. I I I I I 54 I I I Proiect Descriotion Global Positioning Survey Eq Air Conditioner Replacements Stormwater Quality Impr Habitat Restoration & Impr Storm Drainage R&R Allen's Crk Rehab at Hercules Alligator Crk Implementation Cooper's pt Restor & Mgmnt Storm Pipe System Replacement Town Pond N. Greenwood Stmwtr Retrofit Allen's Crk Gabion Stevensons Crk Estuary Rest NPDES FDEP Compliance City Wide Aerial Photography PW Infrastructure Mgmnt Syst N. Grnwd Corr Enh (Stmpipe) Aliens Crk Neighbrh Flooding Alligator Creek Drainage Imprvmnt Morningside/Meadows Drainage Improvements Kapok Mobile Home Park Myrtle Avenue Drainage Improvements N. Beach Neighborhood Drainage Sharkey Rd Drainage Improvements Storm System Expansion Stevensons Creek Implementation Projects Tropic Hills Drainage Improvements I I I I I I I I I I I. I I I I I Capital Improvements Program FY01 FY01 - FY05 Planned Project Funding FY02 FY03 FY04 FY05 FY06 Total 4,000 4,000 14,000 14,000 9,000 9,000 2,000 2,000 5,000 5,000 34,000 34,000 655,000 899,000 1,554,000 32,000 30,000 30,000 92,000 730,000 1,084,000 1,000,000 1,000,000 1,000,000 1,000,000 5,814,000 4,971,000 5,675,000 907,000 100,000 11,653,000 251,000 44,000 295,000 667,000 667,000 1,417,000 1,033,000 2,275,000 2,275,000 7,000,000 44,000 44,000 200,000 768,000 40,000 1,008,000 22,000 22,000 172,000 91,000 67,000 67,000 67,000 464,000 225,000 225,000 600,000 600,000 1,205,000 2,655,000 564,000 4,424,000 575,000 575,000 6,182,000 8,006,000 2,500,000 16,688,000 255,000 9,100,000 9,355,000 470,000 470,000 900,000 900,000 1,000,000 1,000,000 1,000,000 1,000,000 4,000,000 3,255,000 1,072,000 0 1,108,000 500,000 5,935,000 550,000 550,000 15,375,000 23,299,000 18,566,000 6,269,000 5,830,000 3,064,000 72,403,000 Stormwater Planned Projects.xls/Plnd Pj Revs - HafMget 12l>Sep 9/27/01 5:38 PM